Matter: Nova Scotia Power Inc. - CI 50518 – HYD Ruth Falls Main Dam Refurbishment – $15,445,508 (ATO)
6 passages 6 documents

Surplus Return across all matters →

N-3NSPI (CA) RIR-1 to 18 - Redacted 1 passage
3 # Indicators Condition Choices p. p. 26
CI 50518 CA IR-5 Attachment 19 Page 174 of 423 REDACTED (CONFIDENTIAL INFORMATION REMOVED) 3 # Indicators Condition Choices Data Definitions/Explanations Protection and off road vehicles appear to effectively exclude or divert visitors and...

AI summary The text outlines various indicators and condition choices related to environmental protection, consumptive uses, domestic wells, and calcareous fen within a specific area. It includes data on wildlife disturbance, sustainable consumptive uses, proximity of domestic wells, and calcareous fen identification.

N-9Amended Evidence - Midgard - Redacted 1 passage
p. pp. 4-5
Table 3: Nova Scotia CPI Trend19 Table 4: Canada IPPI Trend20 Table 5: Ruth Falls Archaeological Costs24 Table 6: Comparison of Recent Project Archaeological Costs25 Table 7: Ruth Falls Main Dam Refurbishment Variance Summary28 Table 8: 20...

AI summary The document presents a series of tables detailing various cost-related data, including archaeological costs, labour costs, materials costs, administrative overhead, and other expenses associated with projects such as the Ruth Falls Main Dam Refurbishment and the 2019 ACE and ATO applications.

98138Board Decision 1 passage
2.0 EVIDENCE AND SUBMISSIONS p. p. 4
increased project costs of approximately $2 million. [Exhibit N-1, p. 3] The cost increase associated with the extended construction timeline includes both increased labour and materials expenses. - [15] The final reason noted by NS Power...

AI summary NS Power's ATO application includes a cost increase of approximately $2 million, attributed to extended construction timelines, increased archaeological and Mi'kmaq engagement costs, and additional contingency funds for habitat offsetting costs. These factors are cited as the primary reasons for the variance from the original ACE Plan.

96572IG (Midgard - BCC) IR - 1 to 33 1 passage
10 Request IR-23:
10 Request IR-23: 11 Reference: N-9, page 44 lines 8-14. With respect to the Mi'kmaq observer costs, as noted in Section 4.1 above Midgard considers that NS Power could have known at the time of its ACE submission that its archaeological c...

AI summary Midgard concludes that the increased Mi'kmaw engagement costs associated with NSPI's ACE submission are reasonable. The question focuses on whether NSPI should have known these costs would be higher and the basis for Midgard's assumption, particularly in relation to the Fisheries Act amendments and archaeological costs.

101837Contingency Report #2 - Redacted 1 passage
REDACTED Ruth Falls Main Dam Refurbishment Contingency Report 2 Appendix A Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) p. p. 0
REDACTED Ruth Falls Main Dam Refurbishment Contingency Report 2 Appendix A Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Account NSEB Approved Amount Spend-to-Date Contingency/ Unbudgeted Spend-to-Date Comments $8,074.00 $8,074.0...

AI summary The document outlines a contingency report for the Ruth Falls Main Dam Refurbishment, detailing approved amounts, actual spending, and unbudgeted expenditures. Key items include additional costs for water supply arrangements, meals, Mi'kmaq engagement, and administrative overheads. The report highlights discrepancies in cost allocations and the need for contingency funds.

103022Contingency Report #3 - Redacted 1 passage
REDACTED Ruth Falls Main Dam Refurbishment Contingency Report 3 Appendix A Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) p. p. 0
REDACTED Ruth Falls Main Dam Refurbishment Contingency Report 3 Appendix A Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Account NSEB Approved Amount Spend-to-Date Contingency/ Unbudgeted Spend-to-Date Comments Sponsor/Other Dona...

AI summary The document outlines contingency and unbudgeted spending related to the Ruth Falls Main Dam Refurbishment project, including adjustments for incorrect cost code applications, additional meal costs for community engagement and fish rescue operations, and increased Mi'kmaq engagement expenses.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →