C-1Notice of Appeal (redacted) 1 passage
Complaint Information p. p. 0
Complaint Information DRO made decision on: March 4th, 2026 Type of complaint: Metering Issues Additional details: I have already forwarded the entire e-mail chain with NS Power and the DRO that explains the details of my complaint to boar...

AI summary The complainant disputes NS Power's refusal to compensate for excess solar generation in 2025, citing a DRO decision on March 4, 2026. The complaint highlights metering issues and inadequate compensation for surplus kWh.

C-6NSPI Response to Appeal (redacted) 1 passage
Procedural Background p. p. 0
Procedural Background On February 13, 2026, NS Power received a general complaint from Mr. Cooling regarding NS Power's solar billing process and annual reset of banked solar energy credits. The customer requested clarification on the proc...

AI summary Mr. Cooling filed a complaint with the DRO regarding NS Power's solar billing process and annual reset of banked solar credits. NS Power argued compensation for excess generation is limited under the Electricity Act, while the DRO concluded Mr. Cooling received appropriate compensation under Regulation 3.6.1 and the Nova Scotia Electricity Act.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →