Matter: CI# 34622 - P-128.10 - NSPI WO - Upgrade L-8002 - $1,648,189
1 passage 1 document

System Reliability across all matters →

N-1Redacted Work Order 4/30/2010 1 passage
Capital Item Justification p. p. 1
Capital Item Justification Justification Criteria: TRANSMISSION PLANT Sub-Criteria: Name of Report : Document Location: Person Responsible: _ Why do this project? This project is required to increase the clearance from the energized conduc...

AI summary The project aims to increase ground clearance on the 345 kV L-8002 circuit to meet CSA standards, ensuring compliance with safety regulations and preventing potential hazards.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →