Topic/Matter Intersection

Topic:"System Reliability" in M03232

Matter: P-401.32 - Nova Scotia Power Inc. (NSPI) -  Relay Testing Report - 2009Review of Report
4 passages 2 documents

System Reliability across all matters →

N-1NSPI's Relay Testing Report 2009 6/3/2010 2 passages
2009 Test Results Summary p. p. 0
2009 Test Results Summary In 2009 there were 325 relays tested in 22 substations across the province, The results are summarized into the following categories: - Replacement or Repair due to serious functional failmes 10 (9%) - Recalibrati...

AI summary In 2009, 325 relays were tested across 22 Nova Scotia substations. Results showed 74% required no action, 15% needed recalibration, 9% required replacement/repair, and 1% physical maintenance. Highlights infrastructure reliability and maintenance priorities.

2007,2008 & 2009 Test Result Summary p. pp. 0-1
2007,2008 & 2009 Test Result Summary There were a total of 1408 relays tested in 2007, 2008 & 2009 in 63 substations across the province. The below chal1 shows the total combined results from the Relay Test Program for the period of2007 to...

AI summary A total of 1408 relays were tested across 63 Nova Scotia substations from 2007 to 2009 as part of the Relay Test Program. The results are summarized in Figure 9, though specific outcomes are not detailed in the text.

N-2NSPI (NSUARB) IR-1 to IR-3 2 passages
Relay Testing Report 2009 (NSUARB P-401.32) NSPI Responses to UARB Information Requests p. p. 0
Relay Testing Report 2009 (NSUARB P-401.32) NSPI Responses to UARB Information Requests

AI summary The 2009 Relay Testing Report (NSUARB P-401.32) details NSPI's responses to UARB information requests regarding relay testing procedures and grid reliability measures. The document focuses on technical compliance and operational protocols for power system protection.

NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-3: 2 3 Please provide a detailed rationale supporting NSPI's assertion that a ten year cycle for 4 testing relays would be more appropriate. 5 6 Response IR-3: 7 8 The rationale for extending the testing perio...

AI summary NSPI argues that extending relay testing cycles to ten years is cost-effective and reduces risks, citing historical reliability (2% failure rate), backup protections, and reduced likelihood of failures. Testing itself may introduce reliability risks by removing system components during testing.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →