Matter: CI# 38022 - P-128.10 - NSPI WO - 2010 Recloser Additions - $1,400,271ACE amount $1,400,271179K spent to date
2 passages 1 document

System Reliability across all matters →

N-1Redacted Work Order 6/29/2010 2 passages
Why do this project now? p. p. 1
Why do this project now? This project will provide improved reliability through avoided customer interruptions.

AI summary The project aims to enhance system reliability by avoiding customer interruptions, ensuring a more dependable service, and minimizing the risk of service disruptions for consumers, thus enhancing overall grid performance.

Why do this project this way? p. p. 1
Why do this project this way? Appropriate sectionalizing of a feeder will improve outage statistics. For instance, installing a recloser at 50% of the length of a feeder with 50% of the customer count before and after the recloser will res...

AI summary Sectionalizing feeders with reclosers improves outage metrics (SAIFI, SAIDI) by 25-50%, enhancing reliability and reducing customer interruptions. Cost-benefit analysis shows $40.22/ACI and $60.34/ACHI savings. NSPI will implement this infrastructure upgrade.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →