HomeSystem ReliabilityM03332Evidence
Topic/Matter Intersection

Topic:"System Reliability" in M03332

Matter: CI# 38024 - P-128.10 - NSPI WO - 2010 Distribution Cutout Replacements - $2,000,606ACE amount - $2,000,971$682K spent to date
1 passage 1 document

System Reliability across all matters →

05303Board Decision Letter 9/21/2010 1 passage
Bv E-mail and Courier p. p. 0
Bv E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 2010 ACE Plan Work Order - P-128.1 0 CI# 38024 - 2010...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $2,000,606 2010 ACE Plan Work Order to replace distribution cutouts, citing reliability improvements for 71,000 customers. The Board reviewed the request, confirmed the project's necessity, and approved the cost as part of NSPI's reliability program.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →