HomeSystem ReliabilityM03415Evidence
Topic/Matter Intersection

Topic:"System Reliability" in M03415

Matter: NSPI CI# 38819 - $7,452,511 - 51V Tremont Circuit Breaker & Bus
7 passages 4 documents

System Reliability across all matters →

N-1Redacted Work Order 3 passages
Why do this project? p. p. 7
Why do this project? The load on the 69kV system in the Annapolis Valley has increased to a level where a loss of selected elements (138kV line or 138-69kV transformer) in the area, under peak load conditions, causes the voltage on the 69k...

AI summary The project is necessary due to increased load on the 69kV system in the Annapolis Valley, which risks voltage drops below acceptable levels during peak conditions. The solution involves adding a new 138kV line and a 138kV-69kV autotransformer at the 51 V-Tremont Substation to ensure reliability.

Why do this project now? p. p. 7
Why do this project now? The 2010/11 peak load on the 69kV system in the Annapolis Valley is forecasted to reach levels such that failure of some source elements (138kV line or 138-69kV transformer) during peak load conditions causes the v...

AI summary The 2010/11 peak load on the 69kV system in the Annapolis Valley is expected to reach levels where the failure of certain components could lead to voltage drops and potential outages.

Section 169 p. p. 19
Canaan Road - Tremont Transmission Reinforcement

AI summary The document discusses the Canaan Road - Tremont Transmission Reinforcement project, which involves upgrading transmission infrastructure to enhance system reliability and accommodate increasing electricity demand.

N-2NSPI Redacted Responses to Information Requests 2 passages
Preamble p. p. 0
- 1. Normal system conditions are defined to include all of the following: - a. Expected load conditions. - b. All transmission facilities in service (no line or transformer maintenance). - c. Economically scheduled and dispatched generati...

AI summary The document defines key terms related to system conditions, system elements, breaker back-up, and single contingency in the context of power system operations. These definitions establish the framework for assessing system reliability and performance.

3. ELECTRICALLY REMOTE TRANSMISSION SYSTEM p. p. 0
3. ELECTRICALLY REMOTE TRANSMISSION SYSTEM This category is defined by the buses at which the ultimate fault levels will not exceed 1,500 MVA three-phase. - 1. The Interconnected Transmission System dynamic response shall be stable and pos...

AI summary The document outlines requirements for the Electrically Remote Transmission System, emphasizing stability, voltage control, and fault management. It specifies that the system must remain stable under single contingencies, maintain voltage within 90-110% of nominal, and ensure faults are not left permanently on the system.

06178Board Decision and Order 1 passage
ORDER
ORDER WHEREAS Nova Scotia Power Incorporated ("NSPI") filed applications on July 27, 2010, with the Nova Scotia Utility and Review Board (the "Board") for approval of Work Orders CI# 38819 - 51V Tremont Circuit Breaker & Bus in the amount...

AI summary The Nova Scotia Utility and Review Board approved NSPI's applications for work orders related to electrical infrastructure upgrades, including transmission lines and circuit breaker additions, after considering stakeholder input and reviewing the affiliate transaction with Emera Utility Services.

05705Information Requests 1 passage
IR-5:
IR-5: - Reference Response to ACE Plan IR-T2, Attachment 1, page 4 of 35 - a) NSPI proposes to establish a 138 KV ring bus? What is the incremental cost to establish a ring bus? - b) Please describe more fully the reasons for establishing...

AI summary The document contains a series of questions posed by the regulatory body regarding proposed electrical infrastructure changes by NSPI, including the establishment of a 138 KV ring bus, reconfiguration of a 69 KV bus, and an alternative transmission route, focusing on costs and reliability impacts.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →