HomeSystem ReliabilityM03417Evidence
Topic/Matter Intersection

Topic:"System Reliability" in M03417

Matter: NSPI CI# 11004 - $1,990,631 - Canaan Rd. Circuit Breaker Additions
1 passage 1 document

System Reliability across all matters →

N-1Redacted Work Order 1 passage
Why do this project? p. p. 6
Why do this project? The load on the 69kV system in the Annapolis Valley has increased to a level where a loss of some source elements (138kV line or 138-69kV transformer) in the area, under peak load conditions, causes the voltage on the...

AI summary The load on the 69kV system in the Annapolis Valley has increased, requiring an additional 138kV supply to maintain reliability during peak load periods. The project involves interconnecting a new 138kV line from 43V-Canaan Road to 51V-Tremont at the 43V-Canaan Road Substation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →