Why do this project? Porcelain cutouts have been failing at a rate of approximately five per day causing customer interruptions. These fail mostly due to them being defective as a result of the manufacturing process. They develop hairline...
AI summary Porcelain cutouts are failing at a rate of five per day, causing customer interruptions and potential pole fires due to manufacturing defects. The program aims to eliminate 5000 interruptions and prevent infrastructure damage from these failures.
Why do this project this way? It has been determined that the best approach to reduce outages caused by cutout failures is to focus on prioritized feeders (as opposed to targeting specific cutout replacements across a number of feeders). T...
AI summary The project prioritizes feeders over specific cutout replacements to reduce outages, with contract work handled by an affiliate. Expenditure variance arises from NSPI labor use increasing overheads and interest, offset by lower contract costs. The 2009 Cutout Replacements Project (CI 35882-0250) is referenced.