Matter: CI# 40425 - P-510 - NSPI WO - Kempt Road Transformer - $1,093,699Zero dollars spent to date
8 passages 6 documents

System Reliability across all matters →

N-1Redacted Work Order 1 passage
Why do this project? p. p. 1
Why do this project? Currently there are three 138-25 kV transformers at Kempt Road Substation that supply area load. Since 2001 there have been four transformer failures at Kempt Road. Most recently there have been two transformer failure...

AI summary Three 138-25 kV transformers at Kempt Road Substation have experienced multiple failures since 2001, with two recent units removed for rewinding. The remaining transformer is at risk of failure due to high fault levels in the area, prompting a proposal to purchase a spare transformer to prevent extended power outages.

N-2Responses to Information Requests IR-1 to IR-14 1/27/2011 2 passages
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-1: 2 3 On page 4 of 20, under "Why do this project now?", NSPI states this project is being 4 advanced at this time to reduce the probability of loss of load due to a transformer failure. 5 Please provide spec...

AI summary NSPI justifies submitting a transformer replacement project as a U&U work order rather than part of the 2011 ACE Plan, citing a 2010 failure of two Kempt Road substation transformers, leaving only one aging unit operational. The project aims to prevent potential load loss if the remaining transformer fails.

NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Response IR-4: (cont'd) 2 3 If NSPI were to lose the most heavily loaded of the 3 transformers at 104H Kempt Road, NSPI 4 could do the following transfers of load: 5 6  transfer 20 MVA on a short-term basis onto the mob...

AI summary NSPI outlines contingency plans for handling transformer failures at the Kempt Road substation, detailing load transfers between transformers and mobile units. The response includes specific MVA redistribution strategies for single and dual transformer outages, ensuring continued service under emergency conditions.

06819Board Decision Letter 4/26/2011 1 passage
CI # 40425 Kempt Road Transformer $1,093,699 p. p. 0
CI # 40425 Kempt Road Transformer $1,093,699 Board staff issued Information Requests ("IRs") on December 24, 2010 and February 21, 2011, to which responses were received by the Board on January 27 and March 29, 2011, respectively. The Boar...

AI summary The Board approved NSPI's request for funding to purchase a fourth transformer for the Kempt Road Substation to improve power supply reliability in downtown Halifax. The Board expressed concerns about insufficient project details and the outdated status of the spare transformer report, but accepted the request due to urgency and alignment with Hydro One guidelines.

06049Information Requests issued by Board Staff 1 passage
IR-1: On page 4 of 20, under "Why do this project now?", NSPI states this project is being advanced at this time to reduce the probability of loss of load due to a transformer failure. Please provide specific information to support the above statement and to justify the decision to submit this project as a U&U work order, and not as a part of the 2011 ACE Plan. IR-2: The work order application, submitted to the Board on November 24, 2010, identifies an estimated start date of 2010-10 and an estimated in-service date of 2011-08. Please provide the work schedule for 2010 and 2011.
IR-1: On page 4 of 20, under "Why do this project now?", NSPI states this project is being advanced at this time to reduce the probability of loss of load due to a transformer failure. Please provide specific information to support the abo...

AI summary NSPI's project aims to reduce transformer failure risks by advancing the work now. The Board requests justification for submitting this as a U&U work order instead of the 2011 ACE Plan and details on the 2010-2011 work schedule. Additional queries focus on substation configurations and contingency capacity.

064262nd Set of Information Requests (IR-15 to IR-29) 2/21/2011 2 passages
IR-18:
IR-18: With reference to the response to IR-5: - a) When were the investigations noted in IR-5 (a) completed? - b) When did NSPI start to use the procedure described in IR-5 (b)? - c) Please describe any measures taken to limit the magnitu...

AI summary The document contains four questions related to the completion of investigations, the implementation of procedures by NSPI, fault current mitigation measures, and unimplemented options. These questions reference prior inquiries (IR-5) and are part of a regulatory proceeding (IR-18).

IR-28:
IR-28: Please provide and discuss assumed transformers' failure rates, and probabilistic risk assessments of the reliability of power supply to customers in the downtown Halifax area, for the following transformer configurations at the Kem...

AI summary The document requests probabilistic risk assessments and failure rate analyses for transformer configurations at Kempt Road Substation across six timeframes, including pre-2009, post-2010, and scenarios with spare transformers. It also asks for economic analyses comparing urgent transformer purchase versus delayed purchase, referencing prior IR-5(b) responses.

06819Board Decision Letter 4/26/2011 1 passage
CI # 40425 Kempt Road Transformer $1,093,699 p. p. 0
CI # 40425 Kempt Road Transformer $1,093,699 Board staff issued Information Requests ("IRs") on December 24, 2010 and February 21, 2011, to which responses were received by the Board on January 27 and March 29, 2011, respectively. The Boar...

AI summary The Board approved NSPI's request to purchase a fourth transformer for the Kempt Road Substation to improve power supply reliability in downtown Halifax, despite concerns about insufficient project justification and outdated transformer requirement reports. The Board also requested an updated report on spare power transformers.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →