Why do this project now? Due to the NDE results during the planned outage, selective replacement and/or protection work was completed in the superheater and reheat areas of the boiler through removal of thinned tube sections and pad weldin...
AI summary NDE results revealed the need for repairs in boiler superheater and reheat areas to prevent forced outages. Work not included in ACE 2010 requires immediate inclusion in NSPI's next ACE Plan before 2012 to avoid unplanned outages and replacement energy purchases.