HomeSystem ReliabilityM08929Evidence
Topic/Matter Intersection

Topic:"System Reliability" in M08929

Matter: P-884 - Nova Scotia Power Inc. (NSPI) - Integrated Resource Planning (IRP) and M08059--Generation Utilization and Optimization
392 passages 18 documents

System Reliability across all matters →

N-2Hydro Asset Study - REDACTED 3 passages
Section 110
ower’s Renewable Energy Strategy to meet government policy requirements reflecting the public’s desire for cleaner and renewable electricity (40% renewable energy is mandated by 2020). • Reliability – a number of existing hydro assets are...

AI summary NS Power is investing in its hydroelectric infrastructure to meet renewable energy targets, improve reliability, and enhance flexibility for integrating variable energy sources. The Asset Management team is working on long-term capital planning to modernize the aging hydro fleet.

Section 613
   ϭϬ     REDACTED (CONFIDENTIAL INFORMATION REMOVED) REDACTED Hydro Asset Study Appendix C Page 17 of 143  EKs^Kd/WKt Z/E͘Ͳ,zZKWZKhd/KE ^/d  KDD/^^/KE/E' ^d/Dd ^hDDZz&KZ^^ dZ d/Z D EdK>/'d/KE^;ZKͿ^d...

AI summary The text discusses the evaluation of hydro assets, including the analysis of financial and operational factors related to the management and performance of these assets. It emphasizes the importance of accurate cost assessments and the impact of various factors on the overall efficiency and reliability of the hydro system.

Section 706
x /ŶƚĂŬĞůĂƐƐŝĨŝĐĂƚŝŽŶͲĂƚĞŐŽƌLJ͕ƚǁŝŶĞdžƉŽƐĞĚĂďŽǀĞŐƌŽƵŶĚƉĞŶƐƚŽĐŬƐ͖ x ƌĐŚŝƚĞĐƚƵƌĂůůĂƐƐŝĨŝĐĂƚŝŽŶʹĂƚĞŐŽƌLJ͕ƌĞŝŶĨŽƌĐĞĚĐŽŶĐƌĞƚĞ͕ƐƚĞĞůĂŶĚŵĂƐŽŶƌLJ͖    ϯϴ     REDACTED (CONFIDENTIAL INFORMATION REMOVED) REDACTED Hydr...

AI summary The document discusses the evaluation of hydro assets, including the analysis of energy generation, infrastructure planning, and grid management. It highlights the importance of asset management, system reliability, and the integration of renewable energy resources.

N-3NS Power 2019 Ten Year System Outlook dated July 2, 2019 34 passages
Section 10
1 TABLE OF FIGURES 2 3 Figure 1: Net System Requirement with Future DSM Program Effects (actuals are not adjusted for 4 weather) .................................................................................................................

AI summary The document lists figures analyzing demand-side management (DSM) program impacts on system requirements, generating capacity, energy mix forecasts, and infrastructure investments. Key themes include DSM effects on peak demand, firm generating capability, energy mix trends, and transmission/distribution interconnection queues.

Section 14
lined several pre-IRP analyses. To date, NS Power has 5 held two sessions with interested parties and is on track to complete its pre-IRP 6 deliverables for July 31, 2019. 2 M08059, UARB Decision Letter, Generation Utilization and Optimiza...

AI summary NS Power is progressing with pre-Integrated Resource Plan (IRP) analyses, having held stakeholder sessions and aiming to complete deliverables by July 31, 2019. The 2019 load forecast, based on the Statistically Adjusted End-Use (SAE) model and econometric industrial forecasts, informs energy planning and Net System Requirement (NSR) projections.

Section 17
NSR Growth Year (GWh) (%) 2009 12,073 -3.7% 2010 12,158 0.7% 2011 11,907 -2.1% 2012 10,475 -12.0% 2013 11,194 6.9% 2014 11,037 -1.4% 2015 11,098 0.5% 2016 10,809 -2.6% 2017 10,873 0.6% 2018 11,250 3.5% 2019 11,331 0.7% 2020 11,300 -0.3% 20...

AI summary The document presents historical and forecasted Net System Requirement (NSR) growth from 2009 to 2029, showing fluctuating trends. NS Power forecasts peak hourly demand using regression models combining end-use energy forecasts and weather data, with peak demand occurring between December and February due to weather-sensitive loads.

Section 18
ugh an 13 estimated monthly peak demand regression model. The peak contribution from large 14 customer classes is calculated from historical coincident load factors for each of the rate DATE FILED: July 2, 2019 Page 8 of 67 2019 Ten-Year S...

AI summary The document discusses a regression model estimating monthly peak demand, accounting for DSM savings, leading to a flat system peak over the forecast period. Historical and projected net system peak data are presented in Figure 2.

Section 19
remain flat on average over the forecast period. 3 4 Figure 2 shows the historical and forecast net system peak. 5 6 Figure 2: Coincident Peak Demand with Future DSM Program Effects 7 Interruptible Firm Contribution Contribution to Peak to...

AI summary The text presents historical and forecast net system peak demand data from 2009 to 2029, showing trends in interruptible and firm contributions to peak demand. System peak growth fluctuates, with a slight decline in recent forecast years, indicating the impact of demand-side management (DSM) programs on load shaping.

Section 20
2,245 -0.2% 2028 168 2,070 2,239 -0.3% 2029 168 2,060 2,228 -0.5% 8 Forecast value DATE FILED: July 2, 2019 Page 9 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL 1 3.0 GENERATION RESOURCES 2 3 3.1 Existing Generation Resources 4 5 Nov...

AI summary Nova Scotia's generation portfolio includes coal, oil, gas, biomass, wind, tidal, and hydro, with NS Power importing power via interties. The Renewable Electricity Standard (RES) has increased variable renewable energy production, but these resources provide less firm capacity than conventional units, which still meet most firm capacity needs.

Section 27
vice (NRIS) wind projects are assumed to have a firm capacity contribution of 17% as detailed in Section 7.3.1. 6 https://www.npcc.org/Standards/Directories/Forms/Public%20List.aspx DATE FILED: July 2, 2019 Page 12 of 67 2019 Ten-Year Syst...

AI summary The document discusses reductions in Lingan 2's net operating capacity from 153 MW to 148 MW due to an internal steam path restriction, with NS Power not planning to restore it before retirement in 2020. It references MOD-025-2 for generator verification and highlights a 195 MW DSM firm peak reduction in the 2019 Ten-Year System Outlook.

Section 30
etter to address the Board’s 18 concerns regarding the requirement for the Tusket CT for system security, operating 19 reserve requirements, and cost-benefit alternatives analysis. 8 The transmission upgrades being completed for the Mariti...

AI summary The document discusses NS Power's plans for the Tusket CT's system security and operating reserve requirements, the impact of Maritime Link transmission upgrades on firm capacity (43 MW from PH Biomass), and the retirement of Lingan 2. It also outlines NS Power's assessment of Mersey Hydro System redevelopment due to aging infrastructure.

Section 32
ible operation arising from renewables integration, and will continue to 2 be updated annually in the 10-Year System Outlook Report. 3 4 3.3.1 Evolution of the Energy Mix In Nova Scotia 5 NS Power’s energy production mix has undergone sign...

AI summary NS Power's energy mix has shifted toward renewables since the RES, but conventional generation still provides most firm capacity due to intermittency. The 2021 energy mix includes imports and Muskrat Falls hydro, with forecasts showing continued displacement of conventional energy by renewables.

Section 33
Page 16 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL 1 As illustrated in Figure 6 below, NS Power’s firm peak demand has been increasing at a 2 trend of approximately one percent per year. While energy is increasingly being 3 produc...

AI summary NS Power projects a 1% annual increase in firm peak demand, relying on conventional resources and firm imports despite growing renewable energy. The 10-year unit utilization forecast uses the Plexos model, adjusting for changing fuel prices, load forecasts, and system constraints. Steam units provide critical load-following services.

Section 35
1 Figure 7 below provides the current forecast unit utilization of NS Power’s steam fleet. 2 As noted above, assumptions and policy changes could alter the near-term of this 3 utilization forecast, particularly if carbon emission limits af...

AI summary The document presents NS Power's forecasted steam fleet utilization, noting that policy changes, particularly extensions to the NS Cap and Trade program, could alter near-term utilization projections. Forecasts will be updated as policy outcomes clarify, with revised results included in future 10-Year System Outlook reports.

Section 36
Ranges) < 10 25 - 50 25 - 50 10 - 25 10 - 25 10 - 25 10 - 25 10 - 25 10 - 25 10 - 25 Service Hours 7524 6581 6316 7104 6823 7147 6662 6651 6913 7287 Lingan 4 Capacity Factor (%) 62 44 41 43 43 36 36 39 36 35 Unit Cycles (Ranges) < 10 25 -...

AI summary The text presents operational metrics for multiple power generation units, including service hours, capacity factors, and unit cycles, indicating performance data for facilities such as Lingan 4, Point Aconi, Point Tupper, and Trenton 5 over specified ranges.

Section 38
25 10 - 25 10 - 25 25 - 50 25 - 50 25 - 50 10 - 25 10 - 25 10 - 25 10 - 25 Service Hours 1496 1210 2203 4182 3401 4602 3476 4218 4249 4304 Tufts Cove 4 Capacity Factor (%) 46 47 61 60 60 64 66 67 64 64 Unit Cycles (Ranges) 0 > 100 50 - 100...

AI summary The text presents operational data (service hours, capacity factors, unit cycles) for Tufts Cove units 4, 5, and 6 over various periods, which are part of the 2019 Ten-Year System Outlook and Projections of Unit Sustaining Investment. This data is used for infrastructure planning and assessing system reliability.

Section 39
Page 18 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL 1 3.3.3 Projections of Unit Sustaining Investment 2 Unit utilization and reliability objectives have long been the drivers for generator 3 investment planning. Traditionally, in a...

AI summary NS Power is updating its generator investment planning to account for variable renewable integration, introducing a utilization factor (UF) that considers capacity factors, operating hours, unit starts, two-shifting, and asset health to better reflect generator value and operational demands.

Section 41
uly 2, 2019 Page 19 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL 1 factor determination rather than the only consideration as it would have been in 2 the past. 3 4 • Service hours have become a more important factor to consider with...

AI summary The document discusses the importance of service hours and unit cycles in determining the capacity factor of generating units, especially with the increased use of variable-intermittent generation. It highlights that traditional models may underestimate the required investment and that factors like service hours and unit cycles significantly impact equipment failure and maintenance needs.

Section 43
July 2, 2019 Page 20 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL

AI summary This document provides the 2019 Ten-Year System Outlook, a non-confidential overview of the electricity system's future planning and projections.

Section 79
2019 Ten-Year System Outlook NON-CONFIDENTIAL 1 7.0 RESOURCE ADEQUACY 2 3 7.1 Operating Reserve Criteria 4 5 Operating Reserves are generating resources which can be called upon by system 6 operators on short notice to respond to the unpla...

AI summary The 2019 Ten-Year System Outlook discusses resource adequacy, focusing on operating reserve criteria. NS Power must meet reserve requirements as outlined by NPCC and approved by the UARB. NS Power and New Brunswick Power share reserve responsibilities based on a load-ratio share, with specific allocations for ten-minute and thirty-minute reserves.

Section 80
ty will be responsible for is 100 percent 28 of its greatest, on-line, net single contingency, and, NSPI shall be 29 responsible for 50 MW of Thirty-Minute Reserve. 25 https://www.npcc.org/Standards/Directories/Forms/Public%20List.aspx 26...

AI summary The document outlines reserve responsibility formulas for NS Power, including a 40% share of the largest loss-of-source contingency in the Maritimes Area, and details the ten-minute reserve requirements, including spinning and regulating reserves, based on factors like Point Aconi's online status and usage of Maritime Link power.

Section 81
h Maritime Link as the largest 10 source in Nova Scotia will depend on the amount of Maritime Link power used in Nova 11 Scotia. 12 13 7.2 Planning Reserve Criteria 14 15 The Planning Reserve Margin (PRM) intends to maintain sufficient res...

AI summary The document discusses the Planning Reserve Margin (PRM) and its role in ensuring sufficient resources to serve firm customers in Nova Scotia. It references the NPCC reliability criteria approved by the UARB and outlines the requirement for probabilistic evaluation of resource adequacy to ensure that the loss of load expectation (LOLE) does not exceed 0.1 days per year on average.

Section 82
Page 42 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL 1 neighboring Planning Coordinator Areas, transmission transfer 2 capabilities, and capacity and/or load relief from available operating 3 procedures. 4 5 The 2014 IRP Loss of Loa...

AI summary The 2019 Ten-Year System Outlook discusses the 2014 IRP LOLE study, confirming the 20% planning reserve margin (PRM) required by NS Power to meet NPCC reliability criteria. NS Power is updating the LOLE study to establish the PRM for the next planning cycle. The PRM is a minimum requirement, not the optimal capacity for other system needs like load-following and emissions compliance.

Section 90
1 peak load in the near term. The Company expects to be able to manage through this 2 upcoming winter period, and can also find near-term solutions for access to firm capacity 3 if required. NS Power will continue to monitor potential defi...

AI summary The Company is managing near-term peak load and has not accounted for the return of the Tusket CT’s 33 MW capacity in its forecasts. A medium-term outlook is provided in Figure 22, showing available capacity resources compared to customer demand. The planning reserve margin (PRM) is discussed as a measure of generation capacity relative to the NPCC 20% requirement, though it does not account for all system needs such as wind-following and emissions compliance.

Section 94
43 I Community Feed-in-Tariff34 1.0 J Maritime Link Import 153 Total Annual Firm Additions K (G + H + I + J) 44 5 0 0 0 0 0 0 0 0 Total Cumulative Firm Additions (K + L L of the previous year) 44 49 49 49 49 49 49 49 49 49 M Total Firm Cap...

AI summary The text presents a table with various metrics related to energy capacity and reserves, including Total Annual Firm Additions, Total Cumulative Firm Additions, Total Firm Capacity, and Reserve Margin percentages. It includes references to Community Feed-in-Tariff and Maritime Link Import, indicating a focus on renewable energy and grid integration.

Section 95
18% 18% 18% 18% 17% 17% 18% 18% 18% 19% 31 Cumulative estimated Firm Peak reduction based on DSM forecast 32 Includes assumed Lingan 2 retirement once Maritime Link Base Block provides firm capacity service. 33 43 MW from the PH Biomass pl...

AI summary The document discusses NS Power's 2019 Ten-Year System Outlook, focusing on system demand, planning reserve margin, and capacity assessments. It outlines the Firm Peak reduction based on DSM forecasts and mentions the impact of the Maritime Link Base Block and the Community Feed-in-Tariff on system capacity.

Section 97
2019 Page 51 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL

AI summary The 2019 Ten-Year System Outlook provides a non-confidential overview of the electricity system planning and projections for the next decade, focusing on key aspects such as generation, grid reliability, and resource planning.

Section 102
y 2, 2019 Page 53 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL

AI summary The document presents the 2019 Ten-Year System Outlook, providing a non-confidential overview of the utility's system planning and projections for the next decade.

Section 103
1 Under the BES definition and NS Exception Procedure approved by the Board, elements 2 classified as NS BES elements are required to adhere to all relevant NERC standards that 3 have been approved by the Board for use in Nova Scotia. 4 5...

AI summary The document discusses the application of NERC standards in Nova Scotia, the use of Special Protection Systems (SPS) by NS Power to maintain system stability, and the ongoing revision of NPCC Document A-10 to improve reliability and consistency across the NPCC Region.

Section 104
implify the existing methodology to make it less labor-intensive; 29 • Improve consistency across Areas in application and outcomes of the 30 methodology. DATE FILED: July 2, 2019 Page 54 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL

AI summary The text discusses the need to simplify the existing methodology to reduce labor intensity and improve consistency in its application and outcomes across different areas.

Section 107
criteria. The objective of this methodology is to pursue a non-performance based 28 method to identify critical facilities to which NPCC Directory #1 and Directory #4 29 may be applied. 30 DATE FILED: July 2, 2019 Page 55 of 67 2019 Ten-Ye...

AI summary The document outlines a methodology for identifying critical facilities using a non-performance-based approach, referencing NPCC Directory #1 and Directory #4. It is part of the 2019 Ten-Year System Outlook filing.

Section 109
1 The final report summarizing the Phase 2 findings and recommendations of the A-10 2 Working group entitled Classification of Bulk Power System Elements, Document A-10 3 review Phase 2 – Final Report, was submitted to TFCP on November 30,...

AI summary The document outlines the submission of a final report from the A-10 Working Group on the classification of Bulk Power System (BPS) elements, the methodology for classifying BPS buses, and the ongoing applicability of Directory 4 for BPS protection. It also discusses NS Power’s transmission maintenance program aimed at extending asset life and ensuring reliability.

Section 111
19 Page 56 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL

AI summary The document presents the 2019 Ten-Year System Outlook, providing a non-confidential overview of the Bulk Electric System (BES) and related planning efforts, including coordination tasks and system studies.

Section 120
2, 2019 Page 60 of 67 2019 Ten-Year System Outlook NON-CONFIDENTIAL

AI summary The document presents the 2019 Ten-Year System Outlook, providing a non-confidential overview of the electricity system's future planning and projections.

Section 127
1 are not connected to BES buses and the Transmission Owner has not been 2 identified them as BES buses requiring sequence-of-events and fault recording 3 capabilities. 4 5 3. At 1N Onslow and 103H Lakeside there are deficiencies in the mo...

AI summary The text discusses deficiencies in monitoring capabilities at specific substations and updates regarding the correct location of a site mentioned in a prior report. It also outlines a study initiated in 2017 to address transmission line capacity, clearance, and age issues in the Western Valley over a 15-year planning horizon.

Section 130
1 10.0 CONCLUSION 2 3 Customers count on NS Power for energy to power every moment of every day, and for solutions 4 to power a sustainable tomorrow. Environmental legislation in Canada and Nova Scotia 5 continues to drive a transformation...

AI summary NS Power is preparing for environmental regulations that will require increased renewable energy use and reduced emissions. The company is forecasting a potential capacity deficit and is participating in an Integrated Resource Planning (IRP) process to address future energy needs, including studies on renewable energy and demand response programs.

Section 131
re being developed to study specific DR programs. 27 28 The outcome of this IRP process will impact and inform all future Ten-year System Outlook 29 Reports and related long term planning processes. The Company expects the IRP will provide...

AI summary The 2019 Ten-Year System Outlook discusses the impact of the Integrated Resource Plan (IRP) on future planning processes, including the need to address potential capacity deficits and the role of transmission planning, particularly in relation to new load facilities and the Maritime Link.

N-4Draft Terms of Reference 5 passages
Section 5
elopment Goals Act, which established provincial greenhouse gas emission reduction goals of at least 10% below 1990 levels by 2020; at least 53% below 2005 levels by 2030; and “at net zero” by 2050. A growing consensus of economy-wide stud...

AI summary The text outlines Nova Scotia's greenhouse gas emission reduction targets under the Sustainable Development Goals Act, emphasizing the role of electrification in decarbonization. It highlights the need for the 2020 Integrated Resource Plan (IRP) to address renewable energy integration, coal replacement, and grid modernization to meet climate commitments while ensuring system reliability.

Section 7
capabilities and limitations, and how new transmission investments 1 and potential regional interconnections can enable further integration of renewable resources and complement a resource portfolio. In 2018, the Federal Government amended...

AI summary NS Power's Integrated Resource Plan (IRP) addresses renewable integration, coal plant phase-out timelines, and evaluation criteria for resource portfolios. The Federal Government's 2018 regulations mandate coal closure by 2029, but Nova Scotia seeks an equivalency agreement to allow limited coal operation until 2040. The IRP will prioritize affordability, GHG reductions, and reliability, with E3 as the lead consultant.

Section 11
5 IRP Terms of Reference Consultation Appendix A Page 7 of 12 Developing An Electricity Strategy for the Future The IRP process will seek to identify the least-cost, least-risk portfolio. Traditionally, the primary decision criterion used...

AI summary NS Power's Integrated Resource Planning (IRP) process aims to identify the least-cost, least-risk electricity portfolio over 25 years, using cumulative revenue requirement minimization as the primary metric while also evaluating reliability, emissions reduction, and plan robustness. Key considerations include rate impacts, grid stability, and decarbonization alignment.

Section 31
, while recognizing the differences among supply plans in terms of accommodating changes of the first type. Page 5 of 14 IRP Terms of Reference Consultation Appendix B Page 6 of 14 IRP TERMS OF REFERENCE – STAKEHOLDER COMMENTS Stakeholder...

AI summary A stakeholder comments that the IRP TOR lacks emphasis on reliability analysis, critical for assessing capacity benefits of renewables, storage, and the Maritime Link. NS Power agrees, stating reliability contributions will be addressed in the analysis plan and input assumptions.

Section 63
ference This is an external email - exercise caution My apologies. John and I drafted some notes, but I never got around to sending them. So here’s a quick summary of our thoughts: Scope Issues: 1. We appreciate the goal of “a robust, risk...

AI summary The text discusses concerns related to the Integrated Resource Plan (IRP), highlighting the need to address two types of risk in long-term electricity strategy planning. It emphasizes the importance of reliability analysis in the Terms of Reference (ToR) and raises concerns about the proposed schedule for stakeholder comments on modeling results.

N-6Comments - Envigour Policy Consulting, on behalf of QUEST and Marine Renewables Canada 1 passage
Section 2
implicit in the exercise of creating “signposts”, but we believe it would be helpful in making it explicit. Such clarity is particularly important given the lengthy time frame of the Plan – 25 years. …2 We would also note that by explicitl...

AI summary The text advocates for explicitly modeling energy resources at economic prices in the Integrated Resource Plan (IRP) to better assess their systemic value, including capacity from offshore wind, predictability from tidal, scalability from solar PV, and flexibility from storage and demand management. The analysis emphasizes clarity over a 25-year planning horizon.

N-7NSPI's Response to Comments from Interested Parties 2 passages
Section 3
n (adjusted for end-effects). NS Power will continue to use this primary metric to guide resource planning, and will also assess others of increasing importance, including: • Magnitude and timing of electricity rate effects; • Reliability...

AI summary NS Power outlines its approach to resource planning using metrics like rate effects, reliability, grid services, and emissions reduction. An Analysis Plan will evaluate IRP modeling scenarios with alternative futures, employing modeling tools to assess operational feasibility and produce least-cost resource portfolios.

Section 4
ting units). These portfolios will be evaluated for operational feasibility using appropriate electricity system modeling tools, and iterative analysis will be conducted as required. Natural Forces’ comment recognizes and reflects that giv...

AI summary The document discusses the evaluation of portfolios using electricity system modeling tools within the IRP process. Natural Forces emphasizes the need for broader criteria in dynamic energy environments, while NS Power prioritizes minimizing long-term cumulative revenue requirement. Envigour suggests incorporating uncertainty around technology price declines in resource plans.

N-8NSPI Letter update on IRP process 77 passages
Section 21
take into account other factors such as access to economic energy, contribution to emissions reduction, and essential grid services (e.g. inertia, ramping, voltage support, frequency response, etc.). These other benefits will often outweig...

AI summary The text discusses the importance of considering factors beyond economic optimization when determining system capacity, such as emissions reduction and grid services. It highlights that excess capacity may be necessary for grid reliability and mentions the need to refine PRM calculations in the IRP based on resource mix changes.

Section 22
g likely resource mix, NS Power will be able to establish a PRM value and/or methodology to use for system design for the coming years at the conclusion of the IRP. 3.2.2 Capacity Value of Renewables NS Power recognizes a key issue for con...

AI summary NS Power acknowledges the challenge of replacing firm capacity and grid services provided by coal units in Nova Scotia, particularly due to limited interconnection, lack of natural gas, and the mismatch between solar generation and winter peak demand. The Integrated Resource Plan (IRP) will address these issues and establish a PRM value or methodology for system design.

Section 23
12 of 487 with renewables have limitations due to the long duration requirements the storage would need to provide in order to ensure load would be served during the entire timeframe of the peak. In order to ensure the peak demands of the...

AI summary The text discusses the limitations of renewable energy with storage due to long duration requirements and emphasizes the importance of quantifying the contribution of each resource, particularly through the Effective Load Carrying Capability (ELCC) and Loss of Load Expectation (LOLE) methodologies. These methods help determine the guaranteed capacity of renewable resources to ensure reliable system operation during peak demand periods.

Section 24
al method for calculating the capacity value or ELCC of renewables. The results of these ELCC calculations are included in the Capacity Study (Attachment 17). 3.3 Supply Options Study (Attachment 18) In the Supply Options Study, E3 has con...

AI summary The document discusses the method for calculating the capacity value or ELCC of renewables, and the Supply Options Study conducted by E3, which includes cost estimates for new bulk grid supply options and projections from NS Power for existing units. It also highlights the need to consider essential grid services in the IRP Modeling phase due to the increasing availability of renewable energy.

Section 27
will propose draft values for a “high” sensitivity case in the Assumptions Development phase and welcomes feedback on these assumptions. 3.4 Stability Study for Renewables Integration (Attachment 19) NS Power engaged a third-party expert,...

AI summary NS Power conducted a stability study to assess the integration of renewable energy, confirming that current wind capacity is manageable and identifying requirements for increasing wind/solar capacity. The study supports the Integrated Resource Plan (IRP) and outlines integration costs for future renewable scenarios.

Section 35
ng capital costs incurred a range of 6.5% to 10.4% of total NPVRR costs in our main scenarios. It is critical to continue to assess the pattern of these costs and project future costs. 5. Establish requirements to allow increased levels of...

AI summary The text discusses the need to assess capital costs related to wind integration, establish requirements for increased wind on the NSPI system, and enhance coordination among Maritime Provinces for reliability. It also mentions the importance of evaluating technical improvements and the role of battery storage in supporting system stability.

Section 39
ficer/Clerk Nova Scotia Utility and Review Board 1601 Lower Water Street, 3rd Floor P.O. Box 1692, Unit “M” Halifax, NS B3J 3S3 Re: NS Power 2020 Integrated Resource Plan (IRP) – Pre-IRP Workshops In its letter dated October 5, 2018, the B...

AI summary The Nova Scotia Utility and Review Board directed NS Power to complete an Integrated Resource Plan (IRP) by mid-2020, including pre-IRP analyses. These analyses involve studies on loss of load expectation, resource options assumptions, demand response resource assumptions, and transmission requirements for increased renewables.

Section 52
rehensive distribution system the groups and long-term GHG planning analysis Asset Valuation Planning Market Analysis Determines asset values from Develops and deploys proprietary Models wholesale energy markets multiple perspectives tools...

AI summary The text discusses asset valuation, long-term planning, and market analysis, emphasizing the use of proprietary tools and models to support resource planning and forecasting. It also highlights the integration of these analyses into broader market contexts.

Section 64
California Case Study Pacific Northwest Case Study 80% Decarbonization Various Decarbonization Targets GW GW Source: E3 RESOLVE/RECAP IRP Update Appendix 1 Page 51 of 487 19 Attachment 4 - Pre-IRP Deliverables Page 20 of 34 Planning Reserv...

AI summary The text discusses the concept of Planning Reserve Margin (PRM), which is a convention used by utilities to maintain system reliability by holding resources above the forecasted median peak load. It outlines factors that influence PRM, such as unplanned outages and weather conditions, and notes that PRMs vary by utility.

Section 66
20 Attachment 4 - Pre-IRP Deliverables Page 21 of 34 Renewable/Storage Contribution to PRM ¬ In systems with high penetrations of renewable energy and storage, utilities must still maintain acceptable reliability through a planning reserve...

AI summary This text discusses the importance of renewable energy and storage in contributing to the planning reserve margin (PRM) through effective load carrying capability (ELCC). ELCC measures how much of a perfect capacity can be replaced by renewables or storage while maintaining system reliability. Calculating ELCC requires complex models that account for the correlation and probability of production between load and renewables.

Section 73
3,179 2,499 IRP Update Appendix 1 Page 62 of 487 30 Attachment 4 - Pre-IRP Deliverables Page 31 of 34 Key Nova Scotia Challenges Portfolio Optimization Firm Capacity Determining the optimal Maintaining portfolio of renewable, Renewab adequ...

AI summary The document outlines key challenges in Nova Scotia's energy sector, focusing on portfolio optimization and maintaining firm capacity. It highlights the need to balance renewable, hydro, storage, thermal, and demand-side resources while addressing limitations and potential coal retirements.

Section 74
limitations of non- cost portfolio reflects this Demand- Thermal thermal resources Side Firm Fuel Renewable Integration Ensuring firm fuel for Given the limited electric new thermal resources interconnections with natural gas neighboring j...

AI summary The text discusses challenges related to ensuring firm fuel for new thermal resources in Nova Scotia, particularly due to limited natural gas pipeline capacity and the need to maintain grid stability with higher renewable energy penetration. It also includes contact information for Energy and Environmental Economics, Inc. (E3).

Section 80
changes will be part of further discussion through development of the TOR and Analysis plan. Analysis Plan For example: Assumptions • Should IRP objectives move beyond “least cost NPV Revenue Modeling Requirement”? • How do we consider dec...

AI summary The text discusses the development of an Analysis Plan and TOR for an Integrated Resource Plan (IRP), focusing on assumptions related to IRP objectives, decarbonization, and uncertainty. It also mentions essential grid and reliability services, particularly in the context of high renewable energy penetration.

Section 81
9 ESSENTIAL GRID/ RELIABILITY SERVICES Essential Grid/Reliability Service Of particular importance in modeling scenarios with high penetration of renewables Resource Type Energy Firm Capacity Operating Reserves Inertia Frequency Response R...

AI summary The text emphasizes the importance of modeling scenarios with high renewable energy penetration and significant thermal generation retirements, focusing on the provision of essential grid/reliability services and their associated costs.

Section 82
generation retirements is the provision of essential Combustion Turbine grid/reliability services (and the Hydro associated costs of obtaining them). Wind Solar NS Power will work with stakeholders through the Battery Storage Assumptions D...

AI summary The document discusses the importance of grid and reliability services, including combustion turbines, hydro, wind, solar, battery storage, and demand response, in maintaining a stable and reliable grid. NS Power plans to collaborate with stakeholders to understand the opportunities and challenges associated with these services.

Section 85
– Storage – Demand Response IRP Update Appendix 1 Page 78 of 487 11 Attachment 5 - Pre-IRP Deliverables Page 13 of 89 Planning Reserve Margin (PRM) ¬ Planning reserves are resources held by the utility above the forecasted median peak load...

AI summary The text discusses the concept of Planning Reserve Margin (PRM), which is a measure of the additional capacity a utility maintains above the forecasted median peak load to ensure reliability. PRM varies by utility and is typically between 12% and 20%, depending on system characteristics.

Section 86
ty can MW generally maintain lower PRMs PRM • Islanded systems with limited interconnections and load and Traditional Generation resource diversity such as Hawaii must maintain a PRM Nameplate 1-in-2 Capacity around 40% Peak Step 1 Step 2...

AI summary The text discusses the Planning Reserve Margin (PRM) and its relevance to reliability standards, particularly in islanded systems with limited interconnections. It notes that systems like Hawaii must maintain a PRM of around 40% due to limited resource diversity and interconnections. The document also references the Integrated Resource Plan (IRP) and its appendices.

Section 87
12 Attachment 5 - Pre-IRP Deliverables Page 14 of 89 Renewable/Storage Contribution to PRM ¬ In systems with high penetrations of renewable energy and storage, utilities must still maintain acceptable reliability through a planning reserve...

AI summary The text discusses the importance of renewable energy and storage in contributing to the planning reserve margin (PRM) through effective load carrying capability (ELCC). ELCC measures how much renewable or storage capacity can replace firm capacity while maintaining system reliability, with calculations requiring complex models.

Section 90
IRP Update Appendix 1 Page 82 of 487 Attachment 5 - Pre-IRP Deliverables Page 17 of 89 Overview of Jurisdictional Review ¬ E3 conducted a review of reliability standards and planning practices mainly across several North American electric...

AI summary E3 conducted a review of reliability standards and planning practices across North American electric jurisdictions, concluding that NSPI aligns with industry best practices. The review focused on reliability metrics, planning practices, and PRM conventions, with NSPI planning to a 1-day-in-10 year standard or 0.1 days/yr loss of load expectation (LOLE).

Section 91
or 0.1 days/yr loss of load expectation (LOLE) IRP Update Appendix 1 Page 83 of 487

AI summary The text references a loss of load expectation (LOLE) of 0.1 days per year, as part of an Integrated Resource Plan (IRP) update appendix. This metric is used to assess system reliability and planning reserve margins.

Section 92
16 Attachment 5 - Pre-IRP Deliverables Page 18 of 89 Jurisdictional Summary Jurisdiction / Utility Reliability Metric Metric Value Notes 800 MWh/year AESO monitors capacity and can take action if modeled EUE exceeds threshold; 34% AESO EUE...

AI summary The document compares reliability metrics across various jurisdictions, focusing on LOLE (Loss of Load Expectation) and PRM (Planning Reserve Margin) values. Nova Scotia's LOLE is set at 0.1 days/year with a 20% PRM to meet this standard, similar to other regions like ERCOT and NYISO.

Section 93
LOLE is used to set capacity market demand curve; Minimum Installed Reserve Margin NYISO LOLE 0.1 days/year (IRM) is 16.8%; Achieved IRM in 2019 is 27.0% PacifiCorp N/A N/A 13% PRM selected by balancing cost and reliability; Meets 0.1 LOLE...

AI summary The text discusses various approaches to setting reliability standards and reserve margins in electricity systems, including the use of LOLE (Loss of Load Expectation), PRM (Planning Reserve Margin), and LOLH (Loss of Load Hours) across different regions such as NYISO, PJM, SPP, and others. These metrics are used to determine capacity market demand curves and ensure system reliability.

Section 94
Ireland LOLH 8 hours/year total payments to generators (Net-CONE PRM) IRP Update Appendix 1 Page 84 of 487 17 Attachment 5 - Pre-IRP Deliverables Page 19 of 89

AI summary The text includes a table with data on LOLH (Loss of Load Hours) and references to an IRP (Integrated Resource Plan) Update Appendix and Attachment 5 - Pre-IRP Deliverables. These elements are related to energy planning and regulatory processes.

Section 95
17 Attachment 5 - Pre-IRP Deliverables Page 19 of 89 RECAP Model Overview & Assumptions IRP Update Appendix 1 Page 85 of 487 Attachment 5 - Pre-IRP Deliverables Page 20 of 89 E3 Renewable Energy Capacity Planning Model (RECAP) ¬ RECAP is a...

AI summary The document introduces the RECAP model, a loss-of-load-probability (LOLP) model used for evaluating power system reliability in high renewable energy penetration scenarios. It was initially developed for the California ISO over a decade ago and has been adopted by various utilities and regulators across North America, including Nova Scotia Power.

Section 96
19 RECAP: E3’s Renewable Energy Deliverables Page 21 of 89 Attachment 5 - Pre-IRPCapacity Planning Model ¬ RECAP is a loss-of-load probability (LOLP) model used to test the resource sufficiency of electricity system portfolios • This study...

AI summary The RECAP model is a loss-of-load probability (LOLP) model used to assess the sufficiency of electricity system portfolios. It uses a 1-day-in-10-year standard (0.1 days/yr LOLE) to determine the target PRM. The methodology involves calculating hourly load, renewable profiles, available dispatchable generation, hydro dispatch, transmission availability, storage dispatch, demand response, and loss of load.

Section 104
212 Total 393 IRP Update Appendix 1 Page 92 of 487 25 Attachment 5 - Pre-IRP Deliverables Page 27 of 89 Transmission Lines ¬ No internal transmission constraints assumed within Nova Scotia ¬ Maritime Link • Day time capacity of 153 MW star...

AI summary The text discusses transmission line capacities and fuel supply considerations in Nova Scotia, including the Maritime Link's transmission lines and the potential challenges of accessing firm natural gas during winter peak electricity events.

Section 105
PRM ¬ Access to firm natural gas fuel supply during winter peak electricity events could be challenging to NSPI if new capacity is added which would further constrain gas pipeline import capacity ¬ Various options for firm fuel supply exis...

AI summary The document discusses challenges related to accessing firm natural gas fuel supply during winter peak electricity events, especially if new capacity is added, which could further constrain gas pipeline import capacity. It also outlines various options for firm fuel supply and mentions that more information will be provided as the Integrated Resource Plan (IRP) progresses. Reliability metrics such as Loss of Load Expectation (LOLE), Loss of Load Hours (LOLH), and Expected Unserved Energy (EUE) are presented for NSPI in 2020.

Section 106
MWh/yr 49 7.6 Normalized EUE % of annual load 0.0005% 0.00008% 1-in-2 Peak Load MW 2,070 2,070 PRM Requirement % of peak 21.0% 17.8% ¬ High Operating Reserve Requirement Case: 100 MW operating reserve requirement in all hours, approximatel...

AI summary The document discusses two operating reserve requirement cases: a high case requiring 100 MW (5% of NSPI’s peak load) and a low case requiring 33 MW (1.5% of NSPI’s peak load). Operating reserves are critical for maintaining grid reliability and responding to unexpected conditions.

Section 107
29 Load and Resource Balance Attachment 5 - Pre-IRP Deliverables Page 31 of 89 High Operating Reserve Requirement Case

AI summary This section discusses the High Operating Reserve Requirement Case, which is part of the Load and Resource Balance section in the Pre-IRP Deliverables. It outlines the need for maintaining a high level of operating reserve to ensure system reliability.

Section 114
37 Attachment 5 - Pre-IRP Deliverables Page 39 of 89 Conclusions ¬ NSPI requires a 17.8% - 21.0% PRM to maintain a 0.1 days/yr loss of load expectation (LOLE) target • Dependent upon the specific portfolio ¬ Dispatch-limited resources such...

AI summary The text discusses the need for a 17.8% - 21.0% PRM (Planning Reserve Margin) to maintain a 0.1 days/yr loss of load expectation (LOLE) target, highlighting the diminishing returns of dispatch-limited resources like wind, solar, and demand response in contributing to ELCC (Effective Load Carrying Capability). It also notes the variability in reliability metrics and the limitations of using LOLE as a sole measure of system reliability.

Section 115
l and high-renewable systems with equivalent LOLE, the high-renewable systems tend to have more severe (higher magnitude) events • This is due to variability in renewable resource availability ¬ While LOLE is the most common reliability me...

AI summary The text discusses the reliability of high-renewable energy systems, noting that while they have equivalent LOLE metrics, they tend to have more severe reliability events due to variability in renewable resource availability. It also mentions the use of the RECAP model to evaluate resource adequacy through time-sequential simulations, calculating metrics like LOLP and LOLE.

Section 116
usands of • LOLP: Loss of Load Probability years of plausible load, renewable, hydro, • LOLE: Loss of Load Expectation and stochastic forced outage conditions • EUE: Expected Unserved Energy • ELCC: Effective Load-Carrying • Captures therm...

AI summary The text describes a model used for capacity planning, including metrics like LOLE, LOLP, EUE, and ELCC, which evaluate system reliability and renewable resource capacity. It also references the E3 RECAP model and an IRP Update Appendix.

Section 130
175 235 16 600 600 51 188 264 25 700 700 58 201 293 34 800 800 65 214 323 43 900 900 73 227 352 52 1,000 1,000 80 240 381 61 IRP Update Appendix 1 Page 121 of 487 54 Attachment 5 - Pre-IRP Deliverables Page 56 of 89 Nova Scotia Reliability...

AI summary The document discusses reliability metrics, including LOLE (Loss of Load Expectation) and reserve margin standards, with a 20% planning reserve margin required to meet the LOLE standard. It also references the use of the PASA module of PLEXOS for loss of load modeling and mentions the accounting of reserve margin for both dispatchable resources and load.

Section 131
t of System Adequacy (PASA) module of PLEXOS IRP Update Appendix 1 Page 122 of 487 55 Attachment 5 - Pre-IRP Deliverables Page 57 of 89 SPP Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ LOLE: 0.1 days/year ▪ Net...

AI summary The document discusses system adequacy metrics, including LOLE and PRM, and outlines reserve margin accounting methods for both resource and load considerations. It references the use of the PASA module of PLEXOS and mentions GridView and SERVM for loss of load modeling.

Section 132
56 Attachment 5 - Pre-IRP Deliverables Page 58 of 89 MISO Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ LOLE: 0.1 days/year ▪ UCAP: Capacity de-rated for forced outages ▪ ICAP: Installed capacity Reserve Margin...

AI summary The document discusses reliability metrics and reserve margin accounting for MISO and ERCOT, including LOLE, PRM, UCAP, and ICAP, as well as load modeling and reserve margin calculations for the Integrated Resource Plan (IRP).

Section 133
57 Attachment 5 - Pre-IRP Deliverables Page 59 of 89 ERCOT Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ No explicit standard ▪ Dispatchable units are counted by seasonal net sustained capacity Reserve Margin ▪...

AI summary The document discusses reserve margin accounting practices in ERCOT, including how different types of resources are counted and de-rated based on seasonal capacity contributions. It also references a study on market equilibrium and economically optimal reserve margins, as well as the use of SERVM for loss of load modeling.

Section 134
58 Attachment 5 - Pre-IRP Deliverables Page 60 of 89 NYISO Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ LOLE: 0.1 days/year ▪ IRM based on installed nameplate capacity – UCAP requirement is based on capacity Re...

AI summary The text discusses reserve margin accounting and reliability metrics used by NYISO and ISO-NE, including LOLE, IRM, and methods for calculating reserve margins based on installed capacity and demand curves. It also references the Integrated Resource Plan (IRP) and related modeling tools like GE-MARS.

Section 135
59 Attachment 5 - Pre-IRP Deliverables Page 61 of 89 ISO-NE Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ LOLE: Demand Curve ▪ Dispatchable resources counted at – 0.2 days/year installed nameplate capacity – 0.1...

AI summary The document discusses reliability metrics and reserve margin accounting practices, including LOLE thresholds, reserve margin percentages, and how different resources are counted. It references the Integrated Resource Plan (IRP) and mentions energy efficiency and behind-the-meter PV as factors in load modeling.

Section 136
▪ Operating reserves are included IRP Update Appendix 1 Page 127 of 487 60 Attachment 5 - Pre-IRP Deliverables Page 62 of 89 PJM Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ LOLE: 0.1 events/year ▪ Dispatchable...

AI summary The text discusses reserve margin accounting and reliability metrics used by PJM and CAISO, including LOLE, IRM, and PRISM. It outlines how dispatchable units and renewable ICAP are calculated, as well as the use of probabilistic reliability models.

Section 137
61 Attachment 5 - Pre-IRP Deliverables Page 63 of 89 CAISO Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ No explicit reliability standard ▪ Monthly Net Qualifying Capacity (NQC) to calculate total available capa...

AI summary The document outlines reliability metrics and reserve margin accounting practices for CAISO and AESO. CAISO uses the Resource Adequacy (RA) program with a 15% Planning Reserve Margin (PRM) and calculates renewable energy capacity using the SERVM model and RECAP. AESO has a reliability standard of 800 MWh/year Expected Unserved Energy (EUE) but does not specify reserve margin accounting for resources.

Section 138
chment 5 - Pre-IRP Deliverables Page 64 of 89 AESO Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ EUE: 800 MWh/year; NormEUE: 0.0014% ▪ N/A Reserve Margin ▪ Publishes quarterly reports monitoring the existing and...

AI summary The document compares reliability metrics and reserve margin accounting approaches between AESO and Florida. AESO uses EUE and reserve margin thresholds, while Florida uses LOLE and a 15% reserve margin planning criterion. Both entities are developing methods to assess system reliability and capacity.

Section 141
65 Attachment 5 - Pre-IRP Deliverables Page 67 of 89 Australia Reliability Metric(s) and Standard Reserve Margin Accounting – Resource ▪ Expected Unserved Energy (EUE): ▪ N/A 0.002% of total energy demand – Standard is set based on the eco...

AI summary The text discusses reliability metrics and reserve margin accounting in Australia and Great Britain. Australia uses Expected Unserved Energy (EUE) with a standard of 0.002% of total energy demand, while Great Britain uses Loss of Load Hours (LOLH) with a standard of 3 hours/year. Australia does not have an explicit reserve margin requirement, whereas Great Britain accounts for generator availability in reserve margin calculations.

Section 142
tional Grid estimated LOLE during availability for each technology (e.g. CCGT 2017/2018 winter is 0.001 hours/year = 85%) of nameplate ▪ Standard is set based on economic optimum Reserve Margin Reserve Margin Accounting – Load ▪ No require...

AI summary The document discusses the calculation of LOLE (Loss of Load Expectation) during the 2017/2018 winter, estimating it at 0.001 hours/year. It also mentions the standard for reserve margin being based on economic optimum and the de-rated capacity margin monitored in 2021 and 2018. The document references the Integrated Resource Plan (IRP) and includes an attachment related to pre-IRP deliverables.

Section 143
67 Attachment 5 - Pre-IRP Deliverables Page 69 of 89 The Republic of Ireland Reliability Metric(s) and Standard Reserve Margin ▪ LOLE: 8 hours/year ▪ LOLE standard is used to determine a ▪ Standard is set based on economic MW capacity requ...

AI summary The document outlines reliability metrics and reserve margin accounting practices in the Republic of Ireland, including the use of LOLE (Loss of Load Expectation) as a standard to determine capacity requirements and payments to generators. Dispatchable and renewable units are de-rated for forced outage rates (FOR) in capacity calculations.

Section 149
OVERVIEW & DISCUSSION IRP Update Appendix 1 Page 141 of 487 Attachment 5 - Pre-IRP Deliverables Page 76 of 89 {E3 SLIDES (AT TACHMENT 18)} IRP Update Appendix 1 Page 142 of 487 Attachment 5 - Pre-IRP Deliverables Page 77 of 89 RENEWABLES S...

AI summary The document discusses a System Stability Study for Renewables Integration (SSRI) conducted by Power System Consultants (PSC) on behalf of NS Power to assess the impact of additional renewable energy integration on the power system.

Section 150
dy for Renewables Integration (SSRI) Power System Consultants (PSC) were contracted by NS Power to complete a System Stability Study associated with additional levels of Renewable Energy Integration. The primary objective, to assess the in...

AI summary Power System Consultants (PSC) were contracted by NS Power to conduct a System Stability Study for Renewables Integration (SSRI), aiming to assess the integration of increased renewable generation levels in Nova Scotia. The study evaluated the system's capacity to handle up to 600MW of inverter-based generation, explored the impact of adding a second 345kv transmission tie to New Brunswick, and considered alternative system upgrades like synchronous generators and large-scale batteries.

Section 151
ick in service • Calculate short circuit ratios • Assess potential renewable enabling solutions using large scale batteries and synchronous generators PSC’s international experience with South Australia and Ireland was reviewed for ANALYSI...

AI summary The text discusses lessons learned from South Australia's experience with renewable energy integration, including challenges with low system inertia and a major blackout in 2016 caused by transmission interconnector interruptions during an extreme weather event. It highlights the importance of assessing renewable enabling solutions and calculating regulation reserves using historical wind generation profiles.

Section 152
rators caused by transmission interconnector interruptions during an extreme weather event • 850,000 customers lost supply; 90% restored in 8 hours, remainder within approximately 2 weeks Load shedding is used in both the South Australia a...

AI summary The document discusses system stability in Nova Scotia with varying levels of renewable generation, noting that 600MW of inverter-based renewable generation can be accommodated if three thermal units are maintained. Up to 1000MW may be installed with a second tie to New Brunswick. The loss of this tie is identified as the most significant contingency affecting system stability.

Section 153
• The loss of the tie to New Brunswick is the most significant contingency FOR IRP impacting system stability and associated planning and operational actions. SCENARIOS • Other renewable enabling technologies such as large scale batteries...

AI summary The loss of the tie to New Brunswick is a major contingency impacting system stability. Alternative solutions like large-scale batteries and synchronous condensers can help manage inverter-based generation but do not fully eliminate reliability issues. The second tie may change the need for minimum online thermal units, and grid code revisions are seen as a potential solution for system stability.

Section 160
Scenario Development Study Demand Response Analysis Plan Assumptions Stability Study for Assumptions Renewables Integration Modeling E1 Potential Study Analysis/Conclusions Report IRP Update Appendix 1 Page 158 of 487 Attachment 6 - Pre-IR...

AI summary The document outlines the integration of a stability study for renewables into the Integrated Resource Plan (IRP). NSP and consultants are developing a methodology to estimate integration costs of additional wind based on stability issues and potential solutions. This includes defining specific increments of wind capacity beyond 1000 MW and associated interconnection requirements for stakeholder review.

Section 173
th nameplate capacity (Slide 21). Effective capacity changes on slide 23. Please explain. How does RECAP account for the need to “recharge” energy storage capacity and potential loss of availability? Based on changes to weather patterns in...

AI summary The text includes questions about the RECAP model's assumptions, ELCC calculations, PRM and LOLE targets in the IRP, and the potential impact of new federal clean fuel standards on IRP modelling. These questions focus on technical aspects of energy planning and regulatory considerations.

Section 187
IRP Update Appendix 1 Page 187 of 487 Attachment 14 - Pre-IRP Deliverables Page 2 of 7  7KHSODQQLQJUHVHUYHPDUJLQ 350 QHFHVVDU\WRPDLQWDLQDJLYHQOHYHORIUHOLDELOLW\LVDIXQFWLRQRI DQXPEHURIUHVRXUFHDQGV\VWHPYDULDEOHVWKDW...

AI summary The document discusses the Planning Reserve Margin (PRM) and its role in maintaining system reliability as part of the Integrated Resource Plan (IRP) process. It suggests that a single PRM value may not be appropriate across different resource scenarios and recommends using more conservative PRM values. It also notes the need for clarity in the definition of 'operating reserves' under the Electricity Efficiency and Conservation Act (E3).

Section 205
Executive Summary of resource adequacy is an important goal for utilities seeking to provide both reliable and affordable service to their customers. NSPI currently plans to meet a 1-day-in-10-year reliability target, meaning that not more...

AI summary The document discusses resource adequacy planning for Nova Scotia Power Inc. (NSPI), emphasizing the importance of meeting a 1-day-in-10-year reliability target. The study uses E3’s Renewable Energy Capacity Planning (RECAP) model to assess the system's resource adequacy, aligning with industry best practices and incorporating dispatch-limited resources such as wind, solar, and demand response.

Section 206
ectricity sector by incorporating the unique characteristics of dispatch-limited resources such as wind, solar, hydro, battery storage, and demand response into the traditional reliability framework. RECAP calculates reliability metrics by...

AI summary The document discusses the use of RECAP to calculate reliability metrics for the electricity sector, incorporating dispatch-limited resources like wind, solar, hydro, battery storage, and demand response. It also highlights a key finding that NSPI should maintain a planning reserve margin (PRM) between 17.8% and 21.0% to meet a 0.1 days/year loss of load expectation (LOLE) target.

Section 208
ng reserves that should be held above the forecasted annual peak load, calculated as a % of annual peak « Effective Load Carrying Capability (ELCC) of dispatch-limited resources o The expected contribution toward the planning reserve requi...

AI summary The text discusses resource adequacy and reliability in electric power systems, focusing on the importance of maintaining an appropriate planning reserve margin and the factors that influence system reliability, including load characteristics and resource availability.

Section 209
nt production of renewable resources. Ensuring an appropriate level of resource adequacy is an important goal for utilities seeking to provide both reliable and affordable service to their customers. The reliability of a utility can be mea...

AI summary The document discusses the importance of resource adequacy for utilities in providing reliable and affordable service. It explains how reliability is measured through metrics like loss of load events and highlights that there is no single standard for resource adequacy across North America, with various entities setting their own conventions.

Section 210
Attachment 17 - Pre-IRP Deliverables Page 15 of 85 Table 1: Common Reliability Metrics Acronym Name Unit Definition and Comments LOLP Loss of % The probability in a given time period that load + reserves exceeds Load available generation....

AI summary The text introduces common reliability metrics used in electricity systems, specifically focusing on Loss of Load Probability (LOLP) and Loss of Load Expectation (LOLE). LOLP measures the probability of load exceeding available generation, while LOLE estimates the expected number of days per year when load exceeds generation.

Section 211
ge number of days per year where load + Load reserves exceeds available generating capacity at least once during Expectation the day. This is the most common metric that is used to evaluate resource adequacy across North America. However,...

AI summary The text discusses metrics used to evaluate resource adequacy in the electricity sector, including Load Expectation, Expected Unserved Energy (EUE), and Loss of Load Hours (LOLH). These metrics help assess the reliability of the power system by quantifying the frequency, magnitude, and duration of load shortages.

Section 213
h a reliability metric and target value and then calculate what quantity of planning reserve are required to achieve that reliability target. Figure 1: Planning Reserve Margin Calculation Process 1. Establish 2. LOLP 3. Calculate Reliabili...

AI summary The document outlines the process of calculating the Planning Reserve Margin (PRM) using reliability metrics such as Loss-of-Load Probability (LOLP) models. These models help determine the necessary reserve capacity to meet reliability targets, accounting for unexpected outages and extreme conditions like cold weather in Nova Scotia.

Section 214
Attachment 17 - Pre-IRP Deliverables Page 17 of 85 « Unplanned forced generator outages « Higher than normal peak loads (i.e. very cold weather in Nova Scotia) « Operating reserve requirements The PRM is a convention that is typically base...

AI summary The document discusses the Planning Reserve Margin (PRM) and its calculation, noting that it is typically based on a comparison of installed generation capacity to the 1-in-2 median peak load. NSPI uses a winter day with -15°C temperatures for forecasting, which approximates this median peak load. PRM requirements vary among utilities depending on system size and diversity.

Section 220
ishing returns and needs a resource that can shift its production to the highest value hours, i.e. hours with the highest LOLP which are generally the peak net load hours. 1.5 Jurisdictional Review This report conducts a jurisdictional rev...

AI summary The report reviews resource adequacy and reliability practices across various jurisdictions, noting that the LOLE with a 1-day-in-10-years standard is commonly used, aligning with Nova Scotia’s current reliability target. Some jurisdictions use EUE or LOLH instead. Reliability targets are achieved through mechanisms such as an explicit PRM or a capacity market.

Section 221
ion’s subsection. For the jurisdictions with an LOLE reliability standard, achievement of the target reliability standard varies between two primary mechanisms: an explicit PRM and a capacity market. For jurisdictions with an explicit PRM,...

AI summary The text discusses how jurisdictions with an LOLE reliability standard achieve their targets through mechanisms like explicit PRM and capacity markets. Nova Scotia Power uses LOLP modeling to determine PRM, while capacity markets use LOLP modeling to construct capacity demand curves and determine market clearing prices.

Section 222
rately falls to reflect the lower value of this incremental reliability contribution. Table 2 contains a high-level summary of the target reliability metric for each of the evaluated jurisdictions. Table 2: Jurisdictional Summary of Resour...

AI summary The document discusses resource adequacy planning across various jurisdictions, highlighting different reliability metrics such as EUE, PRM, LOLE, and others. Nova Scotia's target is a 20% PRM to achieve a 0.1 LOLE standard.

Section 223
pendix 1 Page 223 of 487 Attachment 17 - Pre-IRP Deliverables Page 26 of 85 Planning Reserve Margin and Capacity Value Study

AI summary The document discusses the Planning Reserve Margin and Capacity Value Study, which is part of the pre-Integrated Resource Plan (IRP) deliverables. This study is critical for assessing the adequacy of generation capacity and ensuring system reliability.

Section 224
NYISO LOLE 0.1 days/year LOLE is used to set capacity market demand curve; Minimum Installed Reserve Margin (IRM) is 16.8%; Achieved IRM in 2019 is 27.0% PacifiCorp N/A N/A 13% PRM selected by balancing cost and reliability; Meets 0.1 LOLE...

AI summary The text compares reliability metrics and reserve margin targets across various electricity systems, including LOLE, EUE, LOLH, and PRM, highlighting how different regions use these metrics to ensure system reliability and manage capacity markets.

Section 227
ced outages of dispatchable generation. Renewable credit is established by an ELCC study and currently stands at 15.2% for wind and 50% for solar. 1.5.3 ELECTRIC RELIABILITY COUNCIL OF TEXAS (ERCOT) The Electric Reliability Council of Texa...

AI summary The text discusses the Electric Reliability Council of Texas (ERCOT) and its approach to reliability and reserve margins in a deregulated energy market. It outlines the expected market equilibrium reserve margin, economically optimal reserve margin, and a purely informational reserve margin, none of which directly influence the actual reserve margin achieved.

Section 228
tically regulators could intervene if a study determined that the energy-only framework was not going to yield and acceptable level of reliability. 1.5.4 NEW YORK INDEPENDENT SYSTEM OPERATOR (NYISO) The New York Independent System Operator...

AI summary The text discusses reliability metrics and reserve margin calculations used by various ISOs, including NYISO and ISO-NE, to ensure system reliability. It highlights the use of LOLE targets, demand curves, and performance-based qualification of renewable energy resources.

Section 229
IRP Update Appendix 1 Page 226 of 487 Attachment 17 - Pre-IRP Deliverables Page 29 of 85 1.5.6 HAWAIIAN ELECTRIC (OAHU) Hawaiian Electric is an investor owned utility that serves multiple Hawaiian islands, including Oahu. Due to the relati...

AI summary The text discusses the reliability planning approaches of Hawaiian Electric, PJM, and CAISO. Hawaiian Electric maintains a 45% planning reserve margin to meet a 0.22 days/year LOLE standard on Oahu. PJM uses a 0.1 days/year LOLE standard and an installed reserve margin of 16.0% for 2019/2020. CAISO applies a 15% PRM monthly, with renewables counted via ELCC methodology.

Section 231
years. PacifiCorp is able to maintain a PRM on the low end of the most similar utilities due to their significant interconnection ties with other entities in the Pacific Northwest. 1.5.11 AUSTRALIA The Australian Energy Market Operator (AE...

AI summary The text discusses resource adequacy practices in various regions, including the use of reliability targets and reserve margin metrics. It highlights differences in approaches, such as Australia's EUE metric and Great Britain's LOLH standard, and notes the absence of explicit PRM requirements in some jurisdictions. The section concludes with a heading indicating a focus on Nova Scotia's resource adequacy.

Section 232
ity to account for forced outages and renewable units are subject to de-rating factors to account for their limited availability (Wind = 10.3% and Solar = 5.5%) 1.6 Resource Adequacy in Nova Scotia Nova Scotia is a member of the Northeast...

AI summary Nova Scotia adheres to resource adequacy standards set by the NPCC and NERC, requiring a 0.1 days/year LOLE standard. NSPI confirms that a 20% PRM is necessary to meet this standard, as demonstrated in a 2014 study.

Section 233
nd Capacity Value Study As described in Section 1.1, this study provides an update of the required PRM and confirms that a PRM of at least 20% is necessary to meet a target LOLE of 0.1 days/year. As a vertically integrated utility, NSPI is...

AI summary This study updates the required Planning Reserve Margin (PRM) to ensure a target Loss of Load Events (LOLE) of 0.1 days per year. Nova Scotia Power Inc. (NSPI) is responsible for developing an Integrated Resource Plan (IRP) that meets system needs, including the PRM, and submitting it to the Nova Scotia Utility and Review Board (UARB). The study uses E3’s Renewable Energy Capacity Planning (RECAP) model to assess resource adequacy.

Section 234
extensively to test the resource adequacy of electric systems across the North American continent, including California, Hawaii, Canada, the Pacific Northwest, the Upper Midwest, Texas, and Florida. RECAP was developed specifically to addr...

AI summary The text discusses the use of RECAP, a tool for evaluating resource adequacy in electric systems across North America, and mentions its application in planning reserve margin and capacity value studies. RECAP incorporates dispatch-limited resources and generates reliability metrics for utility planning.

Section 235
date Appendix 1 Page 231 of 487 Attachment 17 - Pre-IRP Deliverables Page 34 of 85 Planning Reserve Margin and Capacity Value Study RECAP calculates these metrics through by simulating the electric system with a specific set of generating...

AI summary The document describes the RECAP model, which uses Monte-Carlo time-sequential simulations to calculate reliability metrics such as LOLE and target PRM. The model considers various factors including load, weather, renewable generation, and resource availability to provide robust reliability statistics.

Preamble
Appendix 1 Page 244 of 487 Attachment 17 - Pre-IRP Deliverables Page 47 of 85 Figure 17: Example Storage Dispatch During Sample Week After storage has been dispatched, demand response is dispatched if load + operating reserves still exceed...

AI summary The text discusses how demand response is used as a last-resort resource in the RECAP model, with limitations on the frequency and duration of customer participation. The model calculates reliability statistics such as LOLE, LOLH, LOLEV, and EUE after dispatching all resources to meet load and operating reserves.

Party Question/Comment & Response
Party Question/Comment & Response 2.1 Bates White ...we recommend that NSPI apply more conservative – i.e., lower – PRM values in its IRP evaluations… It is our view that the IRP process should be focused on ways to minimize the costs impo...

AI summary Bates White recommends NSPI use lower PRM values in its IRP to minimize customer costs and avoid excess capacity risks. NS Power responds that lower PRM may not reduce costs due to factors like emissions constraints, citing Synapse GUO modeling showing optimal portfolios often include excess capacity for economic or emissions benefits.

Party Question/Comment
r representation of the most stressed transfer levels, which would illustrate the most critical system states to examine for stability purposes. These would be the most likely cases to identify system issues in order to define the appropri...

AI summary The document discusses the results of a PSC study on wind penetration scenarios and system stability. It confirms that wind penetration beyond 1,000 MW was tested and highlights instability at 1,050 MW. The study did not identify new reliability constraints but provided guidance for monitoring as renewables increase.

Party Question/Comment & Response
quivalent resource) may be required to fulfil other system requirements. This is described in the below excerpt from Section 7 of the PSC report (emphasis added): “The study established that while Nova Scotia is connected to New Brunswick,...

AI summary The text discusses the need for thermal units in Nova Scotia's power system, even with the addition of a second tie to New Brunswick. It emphasizes the importance of balancing services, load following, and local voltage control provided by thermal units, regardless of the second tie option.

N-92020 Integrated Resource Plan 25 passages
1.2 Nova Scotia Power's System Transformation p. p. 0
1.2 Nova Scotia Power's System Transformation This IRP represents a blueprint for a significant transformation in the way Nova Scotia Power generates and purchases electricity to serve its customers across the province. The scenarios consi...

AI summary Nova Scotia Power's Integrated Resource Plan (IRP) outlines a strategy to accelerate greenhouse gas emission reductions, aligning with climate goals. The plan emphasizes technological innovation, rate stability, and the role of aging hydro facilities like Wreck Cove, now critical for integrating variable renewable energy.

1.4 Planning Objectives p. pp. 0-9
1.4 Planning Objectives Through the IRP process, Nova Scotia Power undertakes long-term system planning to understand how the electricity system will continue to meet the needs of customers and respond to changes in the electricity plannin...

AI summary Nova Scotia Power uses the Integrated Resource Plan (IRP) process for 25-year system planning to ensure safety, reliability, affordability, and cleanliness. Near-term 'no-regrets' actions are prioritized to align with long-term objectives, addressing future uncertainties while maintaining customer interests.

SAFE p. p. 9
SAFE - • Provide safe electric service throughout the province - • Promote an injury-free workplace where everybody goes home safe every day

AI summary The SAFE initiative focuses on ensuring reliable and safe electricity delivery across Nova Scotia while prioritizing workplace safety to prevent injuries. Key objectives include maintaining service reliability and fostering a culture of safety in operations.

RELIABLE p. p. 9
RELIABLE - • Meet reliability requirements for supply adequacy - • Procure essential grid services for system stability and reliability

AI summary The document outlines objectives related to meeting reliability requirements for supply adequacy and procuring essential grid services to ensure system stability and reliability. These points are presented as key priorities under the 'RELIABLE' section.

1.7 Developing Optimal Resource Plans p. p. 13
1.7 Developing Optimal Resource Plans Nova Scotia Power assessed each scenario by optimizing its resource portfolio and operations using a suite of analytical planning models. Through consultation with stakeholders, and input from the Ener...

AI summary Nova Scotia Power develops optimal resource plans by using analytical models and stakeholder input to assess various technologies. The process considers capital and operating costs, system reliability, and environmental targets to identify the lowest-cost solutions that meet long-term objectives.

1.8 Overview of Key Findings p. pp. 13-20
tricity rates while facilitating carbon reductions in other sectors; this is a consequential finding which supports the electricity sector's role in economic decarbonization of the provincial economy. 2. Decarbonizing Nova Scotia Power's e...

AI summary The analysis emphasizes the need to decarbonize Nova Scotia Power's electricity supply by eliminating coal generation by 2030-2040 and increasing renewable energy to 70% by 2045. This transition must balance affordability, reliability, and sufficient firm capacity while reducing greenhouse gas emissions.

1.9.1 Action Plan p. p. 25
electricity rates for customers. Nova Scotia economic resource plans it can support provincial decarbonization while Power proposes several Action Plan items from this IRP related to electrification: - a. Initiate an Electrification strate...

AI summary The document outlines an Electrification Strategy aimed at supporting provincial decarbonization while maintaining rate stability. It proposes initiatives such as data collection on electrification demand, AMI implementation, and a Thermal Plant Retirement Plan. These actions are part of the Integrated Resource Plan and are subject to NSUARB oversight.

1.9.2 Roadmap p. pp. 26-27
1.9.2 Roadmap As conditions change – either through changes to policy, technology, or economics – Nova Scotia Power will adapt its resource plan to best serve customers. The Roadmap sets out a series of signposts that, if observed, may ind...

AI summary Nova Scotia Power will adapt its resource plan based on policy, technology, and economic changes. Key actions include advancing coal-to-gas studies, conducting system stability analyses with wind integration, and evaluating hydro and thermal unit investments while monitoring for deviations from the Integrated Resource Plan (IRP) assumptions.

2.4.3 System Strength and Stability p. p. 31
2.4.3 System Strength and Stability The next 25 years will see a dramatic transformation in the Nova Scotia generation mix as it moves further towards decarbonization. Theories and physics of power systems were developed around synchronous...

AI summary The document discusses the transformation of Nova Scotia's power generation mix over the next 25 years, emphasizing the shift from synchronous generators to inverter-based and lower-emitting technologies. This transition will impact system stability and require new approaches to ancillary services, as coal-fired generators retire and synchronous inertia decreases.

3.1 Ensuring Reliability p. p. 31
3.1 Ensuring Reliability A reliable electric system is essential to Nova Scotians. Nova Scotia Power plans its electricity system to ensure that loss-of-load events, caused by an electricity supply shortfall, are rare. System reliability m...

AI summary Nova Scotia Power emphasizes the importance of a reliable electric system, planning years in advance to ensure resource adequacy. As the power supply becomes more decarbonized, the integration of variable and intermittent resources like wind and solar introduces new challenges to reliability planning, requiring more comprehensive methods and potential increases in regulation reserves.

3.1.1 Planning Reserve Margin (PRM) p. p. 31
3.1.1 Planning Reserve Margin (PRM) The first step in planning for a reliable grid is load forecasting. Understanding how customer demand may change under different future scenarios is crucial to Nova Scotia Power's planning process. The l...

AI summary The document discusses the Planning Reserve Margin (PRM) as a key component of Nova Scotia Power's grid reliability planning. It outlines the process of load forecasting and the use of a reliability criterion based on a 1-day-in-10-years Loss-of-Load Expectation (LOLE) standard. This standard is translated into a PRM, which is a percentage requirement above expected peak demand to ensure system reliability.

3.1.3.2 Synchronous Inertia p. p. 31
3.1.3.2 Synchronous Inertia Inertial Response is a key property of a power system which helps to ensure reliability. It is the ability of synchronous generators to release kinetic energy stored in their rotating generators in response to a...

AI summary This section discusses the importance of synchronous inertia in maintaining grid reliability, the impact of replacing coal-fired generators with inverter-based and gas turbine generators, and Nova Scotia Power's approach to ensuring sufficient inertia through system modeling and studies. The pre-IRP study recommended minimum inertia levels and the use of various sources to meet these requirements.

3.1.3.3 Variable Renewable Integration Requirements p. p. 31
3.1.3.3 Variable Renewable Integration Requirements In addition to detailing the specific synchronous inertia and reserve requirements described above, the Stability Study for Renewable Integration looked at available options to enable win...

AI summary The Stability Study for Renewable Integration examined options to enable wind integration beyond 600 MW, identifying a second 345 KV AC tie and a domestic mitigation option with a synchronous condenser and battery. Nova Scotia Power allows parallel selection of these options in the IRP process, despite not being tested in the stability study.

4.5.2.1 Reliability Tie p. p. 73
4.5.2.1 Reliability Tie The Reliability Tie comprises development of a new 345 kV AC line between Onslow, Nova Scotia and Salisbury, New Brunswick. This transmission option was an available resource in all the key scenarios. During the Pre...

AI summary The Reliability Tie involves constructing a new 345 kV AC line between Onslow, Nova Scotia, and Salisbury, New Brunswick. It was identified as a critical resource for system stability and enabling the integration of up to 400 MW of additional wind capacity. Alternative solutions, such as synchronous condensers and battery storage, were also considered.

5.2 Sensitivity Analysis p. p. 73
5.2 Sensitivity Analysis In addition to modeling the key scenarios, Nova Scotia Power also conducted a series of sensitivities to understand how the optimal portfolio for a certain key scenario will vary given different assumptions for cer...

AI summary Nova Scotia Power conducted a sensitivity analysis to evaluate how changes in input parameters affect the optimal resource portfolio. This includes varying DSM levels, technology costs, sustaining capital, Mersey Hydro retirement, and operating parameters such as inertia constraints and import availability.

5.2.4 Imports p. p. 73
5.2.4 Imports Imported energy from outside Nova Scotia and the Reliability Tie are components that are seen in all key scenario resource plans; they help Nova Scotia Power both meet future demand and integrate renewable resources. Nova Sco...

AI summary Nova Scotia Power evaluates the impact of imported energy and the Reliability Tie on resource plans, considering scenarios with limited non-firm imports and reduced system inertia from the Reliability Tie. These analyses help understand how future demand and renewable integration might be affected.

5.3.1 Developing Resource Portfolios p. p. 73
5.3.1 Developing Resource Portfolios Nova Scotia Power utilized the PLEXOS capacity expansion and production simulation modeling software in developing the optimal resource portfolios during the Portfolio Study phase of the IRP. PLEXOS is...

AI summary Nova Scotia Power used PLEXOS modeling software to develop optimal resource portfolios from 2021 to 2045, minimizing investment and operation costs while meeting GHG reduction targets and reliability constraints. The PLEXOS modules were used for capacity expansion, production cost modeling, and system operability checks.

5.3.3 Assessing Operability p. p. 73
5.3.3 Assessing Operability To access the operational behaviour of the future resource portfolio, Nova Scotia Power conducted and reviewed hourly unit commitment simulations in PLEXOS MT/ST for several key scenarios, including scenarios th...

AI summary Nova Scotia Power conducted hourly unit commitment simulations in PLEXOS to assess the operability of future resource scenarios, including those with high variable generation and thermal unit retirements. These simulations help validate system and unit operability constraints and refine capital assumptions for the Final Portfolio Study.

5.4 Evaluation of Resource Portfolios p. p. 73
5.4 Evaluation of Resource Portfolios One of the main objectives of the IRP is to develop a robust, risk-weighted lowest-cost long-term electricity strategy that delivers energy in a safe and reliable manner. In addition, Nova Scotia Power...

AI summary Nova Scotia Power evaluates resource portfolios using metrics like 25-year NPVRR, resource adequacy, GHG emissions, and robustness to ensure affordability, reliability, and decarbonization. The Integrated Resource Plan (IRP) considers various scenarios, including the impact of DSM, DER penetration, and electrification on costs and rates.

6.1 Resource Additions and Retirements p. p. 88
ombined-cycle gas generation is selected in six of the scenarios, with more combined-cycle capacity required in the scenarios that did not have access to firm imported energy via Regional Integration. The construction of a new Regional Int...

AI summary The text discusses energy generation scenarios in Nova Scotia, highlighting the selection of combined-cycle gas generation and the construction of a new Regional Interconnection. Wind and solar are key resources, with solar being less suitable due to lower capacity factors and seasonal generation profiles.

6.6 Reliability p. p. 94
6.6 Reliability As described in Section 5.3.2, Nova Scotia Power included a Reliability Assessment phase in the IRP process due to the significant changes in generating capacity anticipated by the end of the planning horizon. Scenarios 2.0...

AI summary Nova Scotia Power conducted a reliability assessment as part of the Integrated Resource Plan (IRP) process, analyzing scenarios with significant renewable energy penetration by 2045. All three scenarios met the reliability criterion of 0.1 days/year loss of load expectation (LOLE), with installed firm capacity close to the lowest cost firm capacity unit.

IRP Scenario 2.0C (2021) Pre-IRP Study (2020) p. p. 94
IRP Scenario 2.0C (2021) Pre-IRP Study (2020) LOLE Target (days/yr) 0.10 0.10 Achieved LOLE (days/yr) 0.25 0.19 Achieved LOLh (hrs/yr) 1.99 1.29 PRM Target (UCAP) / (ICAP) 9% / 21% 9% / 21% Achieved PRM (UCAP) / (ICAP) 6% / 18% 7 / 19% Fig...

AI summary The table compares reliability statistics from the IRP Scenario 2.0C (2021) and the Pre-IRP Study (2020), showing the LOLE and PRM targets and achieved values. The achieved LOLE and PRM values are slightly higher in the 2021 scenario compared to the 2020 study.

6.8.2 Wind p. p. 99
6.8.2 Wind Nova Scotia Power tested a series of sensitivities to investigate the potential impact of technology cost and integration requirements on both the level and timing of wind capacity builds. The results of the first two scenarios,...

AI summary Nova Scotia Power tested various wind energy scenarios, showing that lower wind costs and integration requirements lead to earlier wind capacity installations and coal retirements. Lower inertia requirements had minimal impact on resource plans, while removing integration constraints led to late wind additions and higher curtailment, suggesting the need for further analysis.

6.8.4 Imports p. p. 99
6.8.4 Imports Because Regional Integration and the Reliability Tie play a key role in many of the optimal resource plans developed for the key scenarios, three import sensitivities were modeled in order to evaluate the robustness of this f...

AI summary The document evaluates the impact of three import sensitivities on Nova Scotia's Integrated Resource Plan (IRP). Reducing non-firm imports leads to earlier wind and natural gas combined-cycle unit development. Removing the Reliability Tie results in less wind and higher costs. The Reliability Tie's contribution to inertia is tested, showing that its full inertia provision is not critical to the asset's value.

7.2 Action Plan p. pp. 110-112
7.2 Action Plan As set out in the IRP Terms of Reference, The IRP Action Plan describes the key tasks to be undertaken in the next five years to implement the long-term electricity strategy. These Action Plan items are built on the items i...

AI summary The IRP Action Plan outlines steps for developing a regional integration strategy to enhance reliability and access to low-carbon energy, and proposes an electrification strategy to support decarbonization while maintaining rate stability. Key actions include developing a reliability tie and regional interconnection, conducting studies on firm import options, and initiating electrification programs with oversight from UARB.

N-9-(i)Appendices A-N 207 passages
Section 2
.......................................................................... 2 1 Background........................................................................................................11 1.1 Nova Scotia Policy Landscape .............

AI summary The document outlines a study analyzing Nova Scotia's greenhouse gas emissions and energy demand using the PATHWAYS model. It covers policy context, methodology, scenario analysis, and results on emissions reduction, energy demand, and biofuel usage, concluding with implications for climate and energy strategies.

Section 9
n the electricity sector, as well as by enabling complementary reductions in buildings and transportation from electrification. Over the last decade, the electricity sector in Nova Scotia has reduced emissions by more than 30% relative to...

AI summary Nova Scotia's electricity sector reduced emissions by 30% since 2005 through renewable energy adoption. Continued integration of low-carbon resources like wind and hydro is needed to maintain this progress while ensuring reliability and affordability. NSPI must meet growing energy demand without increasing carbon emissions.

Section 12
Nova Scotia Power IRP Final Report Appendix A Page 15 of 64 infrastructure and initiatives needed to achieve those targets, and developing a strategy to support those markets. 5. Building electrification is dependent on reducing costs and...

AI summary The report emphasizes the need for infrastructure and strategies to achieve decarbonization targets, highlighting building electrification's dependence on cost reductions and incentives. It notes the importance of cold climate heat pumps, their high upfront costs, and the need for government or NSPI support. Peak electricity demand impacts from electric heating and an alternative low-carbon biofuels scenario are also discussed.

Section 56
IRP Final Report Appendix A Page 51 of 64 efficiency of the heat pump technology (Figure 24). The Moderate Electrification case could generate a smaller peak impact of between 155 MW and 552 MW. This analysis shows the impact of heat pump...

AI summary The analysis explores the impact of heat pump electrification on peak electricity loads in Nova Scotia, estimating a potential increase of 155 MW to 552 MW. It highlights the need for further investigation into peaking capacity requirements and reliability impacts, while suggesting mitigation strategies such as ground source heat pumps and hybrid systems with existing thermal backup sources.

Section 65
el costs. E3 will undertake a more detailed review of costs in Phase 2 of this analysis.  Electricity Sector Modeling: This study did not perform detailed dispatch or capacity expansion modeling. Efforts to more completely characterize po...

AI summary The analysis highlights the need for more detailed electricity sector modeling, including dispatch and capacity expansion, to assess impacts on peak load and grid reliability. It also emphasizes the importance of evaluating consumer adoption of low-carbon technologies and the technical feasibility of integrating these technologies into the grid.

Section 123
$1,000 $500 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 2042 2044 2020 IRP FINAL ASSUMPTIONS SET 45 Nova Scotia Power IRP Final Report Appendix B Page 47 of 112 2020 IRP: PLANNING RESERVE MARGIN MARCH 11, 2020 2020 IRP FINAL ASS...

AI summary Nova Scotia Power engaged E3 to conduct a Planning Reserve Margin (PRM) and capacity value study, updating assumptions for the Integrated Resource Plan (IRP) process. The study ensures resource adequacy, reliability, and affordability of power supply by evaluating load characteristics and resource availability.

Section 124
en calculate what quantity of planning reserves are required to achieve that reliability target. Planning Reserve Margin and Capacity Value Study, Energy + Environmental Economics, July 2019 2020 IRP FINAL ASSUMPTIONS SET 47 Nova Scotia Po...

AI summary The document discusses the Planning Reserve Margin (PRM) required by Nova Scotia Power to achieve a 0.1 days/year loss of load expectation (LOLE) target. It states that a PRM range of 17.8% to 21.0% is needed, with 20% being the base case assumption.

Section 125
will maintain its existing PRM of 20% as the base case assumption and iterate on portfolios to determine specific PRM requirements as illustrated in the Analysis Plan overview. 2020 IRP FINAL ASSUMPTIONS SET 48 Nova Scotia Power IRP Final...

AI summary Nova Scotia Power will maintain a 20% Planning Reserve Margin (PRM) as the base case assumption in the 2020 Integrated Resource Plan (IRP). The PRM will be calculated using the Unforced Capacity (UCAP) method, and Effective Load Carrying Capacity (ELCC) will be used for valuing thermal, hydro, and renewable resources. The Reliability and Operability Assessment phase will ensure a 0.1 Days/year Loss of Load Expectation (LOLE) metric is met.

Section 160
RP FINAL ASSUMPTIONS SET 106 Nova Scotia Power IRP Final Report Appendix B Page 108 of 112 SUMMARY (CONT.) • For IRP modeling, assumptions about cost and operational constraints to address these services will be considered. The assumptions...

AI summary The document outlines assumptions for the Integrated Resource Plan (IRP) modeling, focusing on grid services required to accommodate inverter-based generation. Key grid services include ramping reserve, system strength, Volt-Ampere-Reactive support, and synchronous inertia. These will be modeled as dynamic constraints to ensure stable system operation with renewable resources.

Section 161
essential grid services will be represented in the model as dynamic constraints, which will enable the model to integrate renewable resources at any level by ensuring provision of the services. 2020 IRP FINAL ASSUMPTIONS SET 108 Nova Scoti...

AI summary The document discusses the need for additional ramping and regulation reserves due to increased variability from renewable energy and coal unit retirements. It references a stability study that outlines the relationship between inverter-based generation and ramping reserve requirements, and presents an interconnection option to support renewable integration.

Section 177
criteria against which potential plans and resource portfolios will evaluated under each scenario, as shown in Table 6 below: Metric Description Minimization of the cumulative present value of 25 year NPV Revenue Requirement the annual rev...

AI summary The document outlines criteria for evaluating potential plans and resource portfolios under different scenarios, including minimizing revenue requirements, reliability requirements, grid services, plan robustness, emissions reduction, and flexibility. These metrics are detailed in Table 6.

Section 214
l revenue requirements 25 year NPV Revenue Requirement over the planning horizon (with and without end-effects adjustment) Average Annual Relative Rate Impact - 25-yr Magnitude and timing of electricity rate effects 10 year NPV Revenue Req...

AI summary The text outlines various criteria for evaluating electricity plans, including revenue requirements, reliability requirements, grid services, plan robustness, emissions reductions, and flexibility. These factors are analyzed over different planning horizons and involve quantitative and qualitative assessments.

Section 216
ffects ($MM) $16,431 Essential Grid Services • Essential Grid Service requirements are met as modeled 10-yr NPVRR ($MM) $6,805 Resource Adequacy & PRM • Reliability Tie: 2035 • Regional Integration: n/a Average Annual Relative Rate Impact...

AI summary The document outlines key metrics from Nova Scotia Power's Integrated Resource Plan (IRP), including financial effects, CO2 emissions, and scenario evaluations. It highlights the Essential Grid Services, Resource Adequacy, and Plan Robustness, while noting non-compliance with the Sustainable Development Goals Act and increased exposure to natural gas prices.

Section 218
10 Nova Scotia Power IRP Final Report Appendix E Page 12 of 72 2.0A LOW ELEC. / BASE DSM / NET ZERO 2050 / CURRENT LANDSCAPE 11 Nova Scotia Power IRP Final Report Appendix E Page 13 of 72 2.0A LOW ELEC. / BASE DSM / NET ZERO 2050 / CURRENT...

AI summary The document presents scenario metrics and evaluation from Nova Scotia Power's Integrated Resource Plan (IRP) Final Report, including net present value of resource requirements (NPVRR), reliability tie construction, CO2 emissions, and grid service considerations over a 25-year period.

Section 224
21 of 72 2.1C M I D E L E C . / B A S E D S M / N E T Z E R O 2 0 5 0 / R E G I O N A L I N T E G R AT I O N Scenario Metrics & Evaluation 25-yr NPVRR ($MM) $12,983 General Notes • Reliability Tie built in 2031 (earlier than previous runs)...

AI summary The document presents scenario metrics and evaluation for a 25-year Net Present Value Rate of Return (NPVRR) of $12,983 MM, with adjustments for end effects and considerations for reliability, resource adequacy, and emissions reduction targets under the Integrated Resource Plan (IRP). It includes details on coal unit retirements, grid services, and CO2 emissions.

Section 230
72 3.1C M I D E L E C . / B A S E D S M / A C C E L . N E T Z E R O 2 0 4 5 / R E G I O N A L I N T E G R AT I O N Scenario Metrics & Evaluation 25-yr NPVRR ($MM) $13,576 General Notes • 1 coal to gas conversion in 2030 • Regional Intercon...

AI summary The document presents scenario metrics and evaluation data for two different Integrated Resource Plan (IRP) scenarios, focusing on Net Present Value of Resource Recovery (NPVRR), CO2 emissions, and grid reliability. Key elements include coal-to-gas conversion, regional interconnection, and solar energy deployment.

Section 231
28 Nova Scotia Power IRP Final Report Appendix E Page 30 of 72 3.2B HIGH ELEC. / MAX DSM / ACCEL. NET ZERO 2045 / DISTRIBUTED RESOURCES 29 Nova Scotia Power IRP Final Report Appendix E Page 31 of 72 3.2B HIGH ELEC. / MAX DSM / ACCEL. NET Z...

AI summary This section presents the financial and environmental metrics for the Integrated Resource Plan (IRP) under the HIGH ELEC. / MAX DSM / ACCEL. NET ZERO 2045 / DISTRIBUTED RESOURCES scenario. It includes Net Present Value of Resource Recovery (NPVRR), carbon emissions, and reliability considerations such as the Reliability Tie and Regional Integration.

Section 252
e time periods Essential Grid Services 10-yr NPVRR ($MM) $7,470 $7,179 • No change relative to 3.1C Resource Adequacy & PRM • Reliability Tie: 2029 Average Annual Relative Rate Impact • Regional Integration: 2030 2021-2030 (%) 1.9% 1.5% 20...

AI summary The document outlines essential grid services and resource adequacy considerations, including a 10-year NPVRR, reliability tie in 2029, and regional integration by 2030. It also compares new installed capacity under the 2.1C.WIND-1 scenario, with a focus on low wind cost assumptions and net-zero 2050 goals.

Section 260
2021-2030 (%) 0.7% 0.8% • NPVRR is reduced relative to 3.1C in two of three metrics, slightly higher in 10-yr NPV due 2021-2045 (%) 0.7% 0.8% to advancement of investment Essential Grid Services Total CO2 Emissions 2021-2030 (MT) 26.8 41.8...

AI summary The text discusses CO2 emissions projections and grid reliability considerations under different scenarios, including the impact of wind energy on grid inertia and the need for flexibility in energy imports. It also references the Integrated Resource Plan (IRP) and mentions reliability tie and regional integration timelines.

Section 263
Scenario Metrics & Evaluation Sensitivity Base (2.1C) 25-yr NPVRR ($MM) $12,901 $12,983 General Notes • Inertia constraint is lowered from base of 3266 MW.sec to 2200 MW.sec in all hours • Slight change to wind profile build is observed: •...

AI summary The document presents scenario metrics and evaluation results for a 25-year and 10-year NPVRR under a sensitivity scenario and base scenario (2.1C). Key changes include adjustments to inertia constraints, wind profile builds, and the timing of the Reliability Tie and wind build. The analysis indicates minimal impact on overall resource plan optimization.

Section 264
overall resource plan optimization 2021-2030 (%) 0.7% 0.8% • Cost differences are small over all three NPV metrics 2021-2045 (%) 0.8% 0.8% Essential Grid Services • Current studies indicate that 2200MW.sec of online kinetic inertia is not...

AI summary The document discusses the optimization of the resource plan from 2021 to 2045, highlighting small cost differences across NPV metrics and the need for additional stability studies due to insufficient kinetic inertia. It also mentions CO2 emissions and reliability tie and regional integration timelines.

Section 267
ent and replacement energy costs, NPVs incorporating MT/ST Production 10-yr NPVRR ($MM) $6,996 $7,022 Costs are not significantly lower than the base scenario 2.1C Essential Grid Services • This run is intended as a test case to understand...

AI summary The text discusses the financial and environmental impacts of different energy scenarios, including NPVRR, CO2 emissions, and grid reliability considerations. It highlights the importance of grid services, reliability tie, and regional integration in managing wind energy penetration and ensuring system flexibility.

Section 271
system stability studies for the 2021-2045 (%) 0.8% 0.8% Western region of Nova Scotia due to changes in essential grid service provision; cost of any mitigation not included in decommissioning NPV Total CO2 Emissions 2021-2030 (MT) 42.7 4...

AI summary The document outlines system stability studies and CO2 emissions projections for Nova Scotia from 2021 to 2045, highlighting the impact of changes in essential grid service provision and the role of hydro assets in ensuring reliability and reducing fuel price volatility.

Section 273
• No change relative to 2.1C 2021-2030 (%) 1.1% 0.8% 2021-2045 (%) 0.8% 0.8% Resource Adequacy & PRM • Reliability Tie: 2024 Total CO2 Emissions 2021-2030 (MT) 43.5 41.8 • Regional Integration: 2026 Total CO2 Emissions 2031-2045 (MT) 35.1...

AI summary The document presents comparative data on CO2 emissions and resource adequacy for different timeframes and scenarios, including a reliability tie in 2024 and regional integration in 2026. It also includes a comparison of new installed capacity in 2045 under the 2.1C scenario.

Section 280
25-yr NPVRR ($MM) $13,361 $12,983 General Notes • High case is modeled as a +50% increase in annual Sustaining Capital estimates for all thermal steam units (gas and coal) • Reliability Tie is built 6 years earlier and Regional Interconnec...

AI summary The document presents financial and environmental impacts of different scenarios for a 25-year and 10-year period, including changes in capital estimates, retirements of gas and coal units, and the impact on CO2 emissions. These scenarios involve adjustments to infrastructure timelines and resource replacements, affecting NPVRR and emissions outcomes.

Section 286
e Impact 2021-2030 (%) 1.1% 0.8% Essential Grid Services 2021-2045 (%) 1.1% 0.8% • No significant change from 2.1C Resource Adequacy & PRM Total CO2 Emissions 2021-2030 (MT) 41.8 41.8 • Reliability Tie: 2029 Total CO2 Emissions 2031-2045 (...

AI summary The document outlines CO2 emissions projections for Nova Scotia Power from 2021 to 2045, showing minimal changes in emissions and grid reliability. It also includes release notes for data tables related to the Integrated Resource Plan (IRP) modeling results from PLEXOS simulations.

Section 628
hen calculate what quantity of planning reserve are required to achieve that reliability target. Planning Reserve Margin and Capacity Value Study, Energy + Environmental Economics, July 2019 2020 IRP ASSUMPTIONS SET 46 PLANNING RESERVE MAR...

AI summary The document discusses the Planning Reserve Margin (PRM) and its role in achieving a reliability target of 0.1 days/year loss of load expectation (LOLE). Nova Scotia Power proposes maintaining a 20% PRM as the base case and iterating on portfolios to determine specific PRM requirements.

Section 662
eves NSPI has not fully incorporated our request to study alternative, lower costs of capital and if the use of such enables Nova Scotia to decarbonize quicker than using NSPI’s ownership assumptions. Paul Chernick, President of Resource I...

AI summary The document discusses concerns regarding NSPI's approach to incorporating alternative, lower costs of capital and its impact on decarbonization. It also highlights issues with the inequitable treatment of renewable generation's ELCC and suggests financial benefits for ratepayers through the sale of surplus environmental attributes to other sectors.

Section 663
raints. AREA requests that NSPI consider modelling additional decarbonization efforts in each scenario and at what price other sectors would need to pay NSPI to affect such additional decarbonization. Alternative Resource Energy Authority,...

AI summary The Alternative Resource Energy Authority (AREA) requests that Nova Scotia Power (NSPI) consider additional decarbonization efforts in each scenario and the cost implications for other sectors. The document references the Integrated Resource Plan (IRP) and discusses ELCC assumptions based on studies by E3, including the impact of wind energy on the planning reserve margin.

Section 671
c project, which used load and wind forecasting and aggregation capabilities to perform near real-time load shifting of commercial and residential loads and provide new ancillary services to the grid. Electrification of Nova Scotia’s space...

AI summary The text discusses strategies for integrating renewable energy into Nova Scotia’s grid, including demand response frameworks, electrification of heating and transportation, and curtailment of surplus wind and solar generation. These strategies aim to reduce integration costs and support the Province's net zero GHG emissions goal by 2050.

Section 672
generation that can’t be integrated into the NS Power system or for which there isn’t sufficient export capacity to produce hydrogen can be another element of a wind and solar integration strategy. (4) hydro imports offer a relatively high...

AI summary The text discusses the potential for hydro imports via the Maritime Link to assist with wind and solar integration in the NS Power system. It highlights the flexibility of hydro imports and the regulation capacity provided by the Maritime Link, which can help offset generation/load imbalances caused by rapid changes in wind and solar output.

Section 687
• Capacity factors for each of the hydro resources during winter peak hours (hours with any LOLP) in each of the last several years • Effect of the 2016 drought (or other hydrological events) on effective hydro capacity over long winter pe...

AI summary The text requests information on hydro resource capacity factors during winter peak hours, the impact of the 2016 drought on hydro capacity, and the historical frequency of droughts affecting Nova Scotia hydro capacity.

Section 695
On behalf of the Consumer Advocate, Resource Insight would like to submit some additional comments on the draft analysis plan. Previously, we suggested including resiliency testing related to a major natural disaster. We have reflected on...

AI summary The Consumer Advocate, through Resource Insight, suggests adding a section to the Integrated Resource Plan (IRP) to assess the impact of extreme natural disasters on Nova Scotia’s energy infrastructure, considering scenarios like sea level rise and category 5 hurricanes, and evaluating potential damage to thermal, hydro, solar, and wind facilities, as well as transmission and distribution systems.

Section 704
Digby Submissions February 14, 2020 Page 2 of 62 Nova Scotia Power IRP Final Report Appendix H Page 143 of 321 The ability of the utility system to accommodate renewable energy technologies is very much driven by the degree of variability...

AI summary The text discusses the challenges of integrating renewable energy into the utility system due to variability and the need for reliability and voltage control. It highlights the potential of energy storage and smart grid technologies to address these issues, while noting the regulatory constraints and the need for future voltage regulation changes.

Section 842
for the Municipality of the District of Digby Sigma Energy Storage Inc. November 2018 - CONFIDENTIAL page 35 (up to 1079 tonne/year) Clean Microgrid Eco Industrial Reduction Fossil LCOE: 7.2 ¢/kWh 38 person per with Biomass CHP Park fuel c...

AI summary The document outlines a clean microgrid project with a biomass combined heat and power (CHP) system for the Municipality of the District of Digby, proposing reductions in fossil fuel consumption and greenhouse gas emissions, along with potential economic benefits for the municipality and Nova Scotia.

Section 885
1 IV. Provision of essential grid services for system stability and reliability (slide four, row four) 2 E1 recommends the following: 3 • all CRPs that do not meet requirements for essential grid services be eliminated at the 4 reliability...

AI summary E1 recommends eliminating CRPs that fail to meet essential grid service requirements during reliability screenings and incorporating integration costs into the IRP NPV. EfficiencyOne questions how robustness is measured and suggests combining it with the 25-year NPV metric. They also recommend quantifying total emissions per CRP and clearly defining metrics for other emissions types.

Section 966
Envigour Memo Februray 18, 2020 Page 10 of 13 Nova Scotia Power IRP Final Report Appendix H Page 248 of 321 recognition that energy consumers and citizens first value the fundamental integrity of their energy delivery systems: safe, reliab...

AI summary The text emphasizes the importance of safe, reliable, and affordable energy systems while highlighting the need for communities to prioritize local environmental and social issues. It advocates for technological change guided by performance standards and price signals rather than specific technologies, allowing communities to choose solutions that best fit their unique conditions.

Section 969
can offer improved prospects for civil dialogue and more stable conditions for change. Smart Energy Communities, by definition, spend less time shouting at each other and more on building the future. 6) Restoring public trust and confidenc...

AI summary The text discusses the importance of restoring public trust in decision-making institutions through inclusive processes and highlights the challenges and changes in the power grid due to climate events, technological advancements, and the need for local resilience and GHG emission reductions.

Section 970
ys to generate and manage energy at the local level - digitization, automation • A global drive to reduce GHG emissions • Local revenue generation and energy cost security and stability Communities have new energy solutions available to th...

AI summary The text discusses the impact of new energy solutions on communities and the challenges faced by energy service providers and system operators. It highlights changes in business models, customer relationships, and grid management due to advancements in local energy generation and distribution.

Section 996
dition, modularity in design (i.e., using several smaller units versus one larger unit) and equipment selection allows for built- in redundancy and the ability to operate over a wider range, depending on the system’s intended use. 1. Synch...

AI summary The document discusses the technical and performance specifications of Hydrostor’s A-CAES (Advanced Compressed Air Energy Storage) system, including response times for charge and discharge, and its similarity to natural gas–fired facilities. It also touches on the concept of synchronous inertia and its role in grid frequency stability.

Section 1011
model to integrate renewable resources at any level by ensuring provision of the services. 2 Page Natural Forces Memo February 14, 2020 Page 2 of 4 Nova Scotia Power IRP Final Report Appendix H Page 271 of 321 We suggest inclusion of VAR s...

AI summary The document suggests reconsidering the inclusion of VAR support as a binding constraint in the Integrated Resource Plan (IRP) model, noting that it can often be resolved with low-cost solutions. It also highlights concerns about using the Stability Study for determining grid service requirements due to its focus on extreme scenarios rather than normal conditions.

Section 1013
es has also been very successful (e.g. demand side contribution to short-term operating reserves has been very successful. This can also offset or contribute to ramping requirements.). We would welcome further information on the assumption...

AI summary The text discusses the success of demand side management in contributing to short-term operating reserves and the importance of interconnector treatment in the IRP modelling. It requests further information on assumptions regarding grid service capabilities and interconnector flows, highlighting their impact on grid reliability and renewable energy integration.

Section 1062
Category Participant Assumption Comment NS Power Response 6. Planning CA Use longer averaging period for TUC DAFOR (7 years vs 3) To avoid subjectivity, NS Power selected a three year Reserve Margin (Chernick & average for all units in ord...

AI summary The document discusses assumptions related to reserve margin planning and the use of different methods for calculating Effective Load-Carrying Capability (ELCC) and Installed Capacity (ICAP) for various types of generation. NS Power responds to recommendations regarding the averaging period for TUC DAFOR and the treatment of non-thermal generation in ELCC calculations.

Section 1063
at reliability obligations (i.e. 0.1 Adjustments; ICAP method results in a PRM of 20%; UCAP days/year LOLE) are maintained in all years of the plan; method results in a PRM of 7%to 9%. Dynamic under will iterate if required. capacity expan...

AI summary The text discusses planning reserve margin assumptions in the Integrated Resource Plan (IRP), including reliability obligations, capacity expansion strategies, and the need to revisit hydro ELCC assumptions. It also references a request to make numerical values from Figure 27 visible.

Section 1079
10. Imports CA Reflect correlation of temperature & load (NL, NS & NB) This type of granularity is not included in NS Power’s long (Chernick & and availability /cost of imports. term planning model. Wilson) 10. Imports CA Potential cost of...

AI summary The text discusses the impact of imports on Nova Scotia Power's planning model, including the correlation of temperature and load, potential costs of new transmission, the significance of an 800 MW tie line, and the assumption that imports may underestimate emissions from New Brunswick. Reliability and operability screening is also mentioned as part of the process.

Section 1091
Category Participant Assumption Comment NS Power Response 14. Renewable Natural Setting required minimum levels for remaining NS Power agrees that these more detailed wind Integration Forces requirements important - synchronous inertia int...

AI summary Natural Forces argue that renewable integration requirements should consider synchronous inertia based on the largest system infeed/outfeed, but NS Power finds it difficult to model this in the IRP and will use static values. They also note that the PSC Stability study models specific contingencies, but additional analyses will be done during the Reliability and Operability phases.

Section 1092
during the Reliability and Operability assessment phases of the IRP modeling plan. 14. Renewable Natural Proposed grid service level limits should be low rather NS Power agrees; resource portfolios with high levels of Integration Forces th...

AI summary The text discusses the importance of considering grid service level limits and the flexibility of renewable resources during the Reliability and Operability assessment phases of the Integrated Resource Plan (IRP) modeling plan. NS Power agrees with the approach and emphasizes the need to analyze variable generation's contribution to ancillary services and grid reliability.

Section 1102
Category Participant Comment NSP Response 1.2 Analysis Plan CA - Resource Insight Revise to bill effects metric (customers more NS Power will use the 10-year NPV Evaluation Criteria concerned about bills than rates): evaluation criteria as...

AI summary The document discusses revisions to evaluation criteria for resource planning, emphasizing the importance of billing effects over rate effects and ensuring that reliability requirements are met. NS Power agrees to use a 10-year NPV evaluation method and will not consider plans that fail to meet reliability standards.

Section 1124
Category Participant Comment NSP Response 3.1 Screening Dalhousie Need to show how grid resiliency modelled in Applicable reliability targets will be met by Reliability scenarios viable resource portfolios. Transmission & Distribution cons...

AI summary The document discusses grid resiliency modeling and reliability targets, noting that the IRP model does not account for location-specific storm hardening. It also addresses the evaluation of resource strategies under the Comparator case, with NS Power arguing that non-compliance with the SDGA makes additional strategies unnecessary.

Section 1137
ar NPV Revenue Requirement annual revenue requirements over the planning horizon (adjusted for end-effects) Magnitude and timing of electricity rate effects 10 year NPV Revenue Requirement Reliability requirements for supply adequacy Evalu...

AI summary This document outlines the 2020 Integrated Resource Plan (IRP) interim modeling progress and includes participant comments and responses from Nova Scotia Power. It discusses reliability requirements, plan robustness, greenhouse gas reduction, and flexibility in decision-making.

Section 1187
Nova Scotia Power IRP Final Report Appendix I Page 26 of 44 Comments on Interim Modeling Progress Page 5 of 6 Flexible solar (e.g., solar that is curtailed in advance in order to provide upward dispatch flexibility in addition to downward...

AI summary The document discusses the potential of flexible solar and advanced wind/solar technologies to provide operational reserves and system inertia, which could be less expensive than peaker units. It also highlights concerns about wind and solar being screened out in initial capacity expansion modeling due to low assumed capacity benefits, requesting explicit tracking of this issue during evaluations.

Section 1188
discussion, we received some assurance that NS Power will be sensitive to this point during the evaluation. We request that this issue be explicitly tracked and documented as the evaluation proceeds. 4. ELCC for other units. During discuss...

AI summary The discussion highlights concerns regarding NS Power's handling of ELCC values and the use of DAFOR in modeling. There is a request for NS Power to share assumptions and use a longer averaging period for DAFOR to ensure realistic modeling and avoid unnecessary capacity acquisitions.

Section 1196
owth rate, would return to the low adjusted to moderate the original steep ramp up forecast in roughly 2026. A 10% drop in annual energy in in electrification over the first 10 years of the 2020 would require a 2% per year growth rate to r...

AI summary The text discusses the impact of energy demand changes on peak demand forecasts and resource planning, referencing the Sustainable Development Goals Act (SDGA) and the PATHWAYS study. It suggests that without changes to load forecasts, resource portfolios may not align with future demand and recommends a more expansive response from NS Power to address potential recessions.

Section 1201
removal of the anomalously high DAFOR for TUC1 in 2016. These updated DAFOR forecasts were used in the reliability/operability study using E3s RECAP tool, which evaluate the required Planning Reserve Margin to meet the reliability standard...

AI summary The text discusses the removal of an anomalously high DAFOR for TUC1 in 2016 and the use of updated DAFOR forecasts in a reliability/operability study using the E3s RECAP tool. It also addresses modeling assumptions for inertia constraints, including how different resources contribute to meeting these constraints and any operational restrictions.

Section 1359
Thank you for a very informative report and presentation on July 9th. We appreciate the opportunity to comment on the results so far. Our comments below are divided into three sections. First, we request some further documentation or poten...

AI summary The comment requests further documentation or modification of methods, suggests enhancements to scenarios, and highlights key pre-2030 decisions related to the IRP, including coal unit retirements, wind energy expansion, and inter-provincial reliability tie planning. The commenter encourages thorough analysis and possible delays in the IRP process.

Section 1374
Wind costs and constraints: NS Power’s assumptions and modeling methods may be unreasonably constraining near-term wind builds in the model. The issues relate to NSP’s cost assumptions for wind and the reliability constraints imposed durin...

AI summary The analysis questions NS Power's assumptions and modeling methods regarding wind energy costs and reliability constraints. It argues that NS Power's 2019 capital cost of $2,100 per kW is higher than market rates and that the cap on wind build at 100 MW may be overly restrictive. Alternative operational responses are suggested to accommodate additional wind capacity.

Section 1375
operational responses to accommodate additional wind. First, under hourly conditions of high wind and high imports without the reliability tie, wind generation could be capped at 700 MW. Second, under conditions of high wind, a minimum con...

AI summary The text discusses potential operational responses to accommodate additional wind generation, including capping wind generation at 700 MW during high wind and high import conditions, and establishing a minimum conventional capacity requirement during high wind hours. NS Power may model these constraints in its planning models or estimate curtailment costs exogenously.

Section 1377
commitment to deal with extreme conditions, and the cost of those actions, and use that cost in lieu of the reliability-tie cost. The combination of the cost assumption and reliability requirements may be resulting in misleading model resu...

AI summary The text discusses concerns regarding the modeling assumptions in the Integrated Resource Plan (IRP), particularly around the reliability tie and wind energy development. It highlights potential misleading results due to cost assumptions and reliability requirements, and raises policy questions about when wind should be built relative to operational constraints. The IRP process is criticized for not adequately addressing these issues.

Section 1394
would not appear to be held in reserve as is Wreck Cove. We also understand their capacity and energy output to be limited in low-water years. Why would these units merit a 95% ELCC value? John D. Wilson and Paul Chernick • Resource Insigh...

AI summary The document provides a technical review of Nova Scotia Power's Integrated Resource Plan, focusing on grid reliability and stability, and comments on the PSC Renewable Integration report. It highlights concerns about the modeling of grid services and the representation of renewable energy integration.

Section 1397
r synchronous condensers per 1 MW of wind diverges significantly from current industry practices on evaluating and mitigating grid strength. Identification and Explanation of Findings Case Selection & Clarity Case 1: The contingency event...

AI summary The document discusses the evaluation of grid strength in the context of synchronous condensers and wind power, highlighting discrepancies in industry practices. It identifies a case involving the simultaneous loss of two AC ties (N-2), which deviates from standard N-1 planning criteria. A remedial action scheme is noted to prevent the loss of both AC links, but the contingency event requires clarification and consistency across simulations.

Section 1398
oss of a single tie to New Brunswick...” The contingency event involving the AC lines to New Brunswick should be clarified, assessed for validity, and held consistent across all cases and simulations. Case 1: At the time of event, the powe...

AI summary The document discusses a contingency event involving the loss of AC connections to New Brunswick and the impact on grid stability. It highlights the importance of understanding the initial power flow conditions, the behavior of the HVDC link, and the absence of the Wreck Cove Hydro unit, which could have increased system inertia and stability.

Section 1399
of 245 Nova Scotia IRP Review a stabilizing and economic plant like Wreck Cove (or if Wreck Cove was not available, some thermal capacity) was not committed. Case 2: The contingency evaluated was the loss of 1 of 2 poles of Maritime HVDC l...

AI summary The document evaluates different contingency cases in the Nova Scotia Integrated Resource Plan (IRP), focusing on the impact of losing capacity from the Maritime HVDC link and the implications of high imports from New Brunswick during high wind events. It questions the validity of selected cases and suggests operational strategies that prioritize local generation.

Section 1400
ind and low load conditions and appears overly challenging to system operations. Reduced imports via utilization of generation within Nova Scotia would likely be the most prudent operational strategy. Probability of Occurrence of Scenarios...

AI summary The text discusses the operational strategy of Nova Scotia Power (NSP) during low load conditions and the importance of understanding the frequency and duration of specific grid conditions to evaluate mitigation strategies. It highlights the need for context on how often these conditions occur and their impact on economic cost/benefit analyses.

Section 1401
3 Nova Scotia Power IRP Final Report Appendix J Page 124 of 245 Nova Scotia IRP Review Frequency Stability & Inertia Requirements Existing System (Section 5.1) Case 1: This case is key because it was used to determine the 2766 MW-s inertia...

AI summary The document discusses frequency stability and inertia requirements in the existing and modified power systems. Case 1 is highlighted for determining inertia minimums, while Case 4 suggests potential improvements in system stability through better voltage regulation. Case 3 simulation fails due to non-convergence, leaving conclusions uncertain.

Section 1402
d to indicate if additional checks were performed to try to confirm that the result was indeed due to an infeasible operating condition. Therefore it is difficult to draw a defendable conclusion here. Case 4: Additional wind was added by b...

AI summary The text discusses issues with a case involving the addition of wind power and the tripping of AC ties, leading to load-shedding stages. It highlights concerns about the contingency being an N-2 event and the lack of defined acceptable load shedding levels. The analysis of a system with an additional 345kV line is noted as not being thoroughly scrutinized due to unresolved questions in the base case.

Section 1403
4 Nova Scotia Power IRP Final Report Appendix J Page 125 of 245 Nova Scotia IRP Review System with Synchronous Condenser and BESS (Section 5.3) This section was not given a high level of scrutiny at this time because the base cases (covere...

AI summary The proposed mitigations of a 200 MVA synchronous condenser and a 200 MW BESS were not sufficiently justified due to lack of performance criteria and analysis. The analysis also overlooked the potential of Wreck Cove Hydro, a large and flexible hydro asset, to address load shedding and grid-strength concerns.

Section 1406
ncil of Texas (ERCOT) has been requiring this functionality for many nears from its wind turbine fleet. ● Utilization of under-frequency FFR from wind power plants that are curtailed. This functionality enables wind turbines which have alr...

AI summary The text discusses various methods for providing frequency response in power systems, including under-frequency FFR from wind power plants, demand-side resources, and the potential impact of the Wreck Cove Hydro Plant on system stability. These approaches are informed by practices in ERCOT and highlight the importance of integrating diverse resources for grid reliability.

Section 1407
have a substantial impact on the stability of the power system. Its status and utilization in the study work should be made explicit because of its potential importance to the system. Short-Circuit Strength Short-circuit strength was only...

AI summary The text discusses the importance of short-circuit strength and power quality in grid stability, noting that short-circuit strength was only discussed qualitatively and that NSP's use of a ratio method for synchronous condensers is not industry-accepted. It also mentions that power quality is typically an application-specific issue, not a systemic one.

Section 1408
t of long-range planning efforts. While it’s correct that weak grids can exacerbate the problem, it often is in conjunction with resonances on the system, for instance due to long, high-voltage cable. Regulation Reserve It is unclear why P...

AI summary The document discusses the relevance of regulation reserves in the context of Nova Scotia's power system, noting that while regulation reserves are necessary for system stability, their inclusion in the PSC analysis may be questionable given the timeframe and the interconnected nature of Nova Scotia's grid with New Brunswick.

Section 1410
atively small, will not influence the PSC stability analysis, and will have a relatively small effect on the IRP modeling. It should be given lower priority than the other stability analysis comments. Curtailment The second phase of the st...

AI summary The text discusses the limited impact of small-scale curtailment on PSC stability and IRP modeling. It highlights that while curtailment of wind energy may occur due to load or export limits, it can be economically beneficial and used for fast frequency response during system events.

Section 1415
storage, will in fact, enable more, cost effective wind energy to be integrated to the grid without significantly more infrastructure investment. Some of these additional benefits are outlined below. Wind Integration in NSPI’s IRP At the J...

AI summary The document discusses the integration of wind energy into the Nova Scotia electricity system, referencing the PSC study and the inertia constraint required for system stability. It highlights the increase in inertia threshold from 2,766 MW.sec to 3,266 MW.sec to account for potential losses, and notes a stakeholder's concern regarding the stringency of this threshold.

Section 1416
CanREA Memo July 17, 2020 Page 2 of 5 Nova Scotia Power IRP Final Report Appendix J Page 132 of 245 Recognizing the Contribution that Wind can Play in Reducing Inertia Requirements In response to a question by Dan Roscoe regarding this sli...

AI summary The document discusses the contribution of wind energy in providing synthetic inertia, specifically Fast Frequency Response (FFR), and how this differs from synchronous inertia. CanREA highlights that this topic is being addressed by the Offshore Energy Research Association (OERA) on behalf of the Nova Scotia Department of Energy and Mines.

Section 1417
urisdictions on the role that existing non- synchronous/inverter-based resources such as wind can play in providing frequency response services and by so doing reduce Nova Scotia’s inertia constraint. CanREA agrees that FFR and synchronous...

AI summary CanREA agrees that FFR and synchronous inertia are distinct services but highlights that FFR can help mitigate reduced synchronous inertia's effects on frequency control. This is supported by AEMO's findings, suggesting that FFR can allow meeting frequency standards with less synchronous inertia, applicable to Nova Scotia as well.

Section 1418
f FFR by inverter-based generating resources and energy storage can play a significant role in helping to meet Nova Scotia’s system reliability needs in the context of diminishing synchronous inertia. In a recent report from the US Nationa...

AI summary The text discusses the role of inverter-based generating resources and energy storage in providing frequency response and system reliability, referencing studies from NREL and examples from ERCOT and FERC. It also notes that CanREA members are considering whether obligations for FFR and primary frequency response should be placed on non-synchronous resources in Nova Scotia.

Section 1420
ductions in costs to customers. In fact, this is likely to be a primary objective of placing such an obligation on these resources – the added benefit of enhanced decarbonization should also be noted. As the slide from the July 9th Present...

AI summary CanREA highlights the potential for additional wind integration in Nova Scotia without major infrastructure investment if new and existing wind projects are required to provide FFR. This could enhance decarbonization and should be considered in the Integrated Resource Plan (IRP). The IRP process is critical for informing policymakers on renewable procurement targets.

Section 1438
ration scenarios. If it were available, it is not clear that, if presented with a zero emissions case in the study window, the model might well choose it over gas generation with carbon sequestration. In addition, there is a risk that plan...

AI summary The text discusses the potential risks associated with natural gas generation in the context of emissions and climate goals. It highlights that natural gas may carry a higher carbon emissions factor due to upstream fugitive methane emissions, and that current emissions factors may not fully account for these risks. There is concern that relying on natural gas could become the most cost-effective response to declining GHG levels, despite its environmental impact.

Section 1448
Nova Scotia Power IRP Final Report Appendix J Page 159 of 245 Page 2 within various scenarios increase the demand for natural gas given the intermittent nature of more renewables. At least one Combined Cycle (“CC”) gas unit has been select...

AI summary The document discusses the increased demand for natural gas due to the intermittent nature of renewables, the continued use of aging liquid-fueled combustion turbines, and reliability concerns related to fuel supply for these units. Heritage Gas has provided infrastructure to support NSPI, and the model scenarios include the use of these units until 2045.

Section 1449
hen the units are more likely to be called upon. Availability of fuel supply has decreased following the closure of local refineries. Reliability issues associated with maintaining units out to their 2 Page 16 – IRP Modeling Results Worksh...

AI summary The text discusses the impact of aging power generation units and decreased fuel supply on reliability, as well as the potential increase in peak load due to electrification and its implications for transmission and distribution costs. Heritage Gas notes that these issues were not previously considered in Integrated Resource Plans.

Section 1457
ling Results Release (p.5) or indicate where they are publicly available. 2 System Inertia NS Power 2020 IRP 8 The table includes Lingan 2 as providing an inertia contribution though Clarify the inertia contribution of Lingan 2 prior to an...

AI summary The text discusses the inertia contribution of Lingan 2 and the carbon costs associated with diesel CTs in the NS Power 2020 IRP. It requests clarification on the inertia contribution of Lingan 2 before and after replacement by the Maritime Link and asks for the carbon costs used in the analysis of diesel CTs.

Section 1505
portantly, we believe this approach to be fundamentally flawed and biased towards less renewables and higher costs. PSC study The 700 MW “limit” on installed capacity is derived from the PSC study 1. As we noted before, the PSC study analy...

AI summary The text criticizes the PSC study's 700 MW capacity limit, arguing it is biased towards less renewables and higher costs. It explains that the study examined stressed system conditions, including a 600 MW wind generation finding, but cautions against extrapolating these results to normal conditions.

Section 1507
ld be a more effective remedy; reduction of the import level has the double benefit of creating more space for conventional generation, while at the same time reducing the severity of the contingency. In effect, wind is being limited in or...

AI summary The text discusses the operational limitations of wind capacity in stressed system conditions and suggests that reducing import levels could be a more effective remedy. It emphasizes that wind curtailment is a common practice in systems with renewable energy ambitions, particularly during rare instances when high wind output coincides with stressed system conditions.

Section 1508
ating the problems. 3 In fact evidence suggests that there is a positive correlation between wind output and demand, reducing the likelihood of occurrences of high wind output at time of low demand. 3 Page Natural Forces Memo July 17, 2020...

AI summary The document discusses the unpredictability of stressful events in power systems, particularly the loss of the AC intertie, and highlights that while such events are unpredictable, the system conditions under which they occur are predictable. Mitigation strategies such as curtailment of wind or imports are recommended. International practice supports curtailment of wind output during high wind and stressed system conditions.

Section 1509
he amount of wind which can be installed to the amount of wind output that the system can safely accommodate in the most stressful system conditions would, quite frankly, not even enter consideration. To take Ireland as an example; both Ir...

AI summary The text discusses the challenges of integrating high levels of wind energy into the power system, using Ireland as an example. It highlights how Ireland accommodates up to 70% wind output during peak times, despite limitations on installed capacity. It also references the Synchronous Inertial Response (SIR) requirement in the Integrated Resource Plan (IRP) model, based on a PSC study with a safety margin.

Section 1510
e of 2,766 MW-sec from the PSC study is from Case 01 (revised), which had three thermal generation units on-line. However the PSC report also notes that the system would be stable with only two units. It is also worth noting once more, tha...

AI summary The PSC study indicates that the Nova Scotia system can remain stable with fewer SIR requirements if the AC intertie is not in service or operating at lower levels. Case 2 of the study shows stability with only 1,788 MW-sec of SIR when the AC intertie is out of service, suggesting that the high SIR requirement is tied to the contingency of high import levels on the AC intertie.

Section 1511
th as a contingency event. If the AC intertie were in service but at a lower MW level, the results would be at least as good, or indeed better. In summary, in relation to the minimum SIR requirement:  The minimum level of 3,266 MW is not...

AI summary The text discusses the minimum SIR requirement, suggesting it may be overly conservative based on the PSC and IRP studies, and notes that lower import levels on the AC intertie would reduce the SIR requirement. It also highlights significant and prolonged changes in demand projections due to the COVID-19 pandemic, which differ from recovery timelines in other countries.

Section 1514
ough there are no firm import arrangements (interconnector flows follow the market). This approach significantly reduces the generation installed capacity requirement in each system, and in aggregate. Emulated or Synthetic inertia The poin...

AI summary The document discusses the lack of firm import arrangements and the impact of HVDC interconnectors and RES on providing synthetic inertia. It highlights the potential future significance of developments in this area. The SBA participated in an IRP stakeholder meeting and provided comments on modeling results.

Section 1517
I. Modeling Questions, Concerns and Suggestions a. System Inertia-Based Generation Requirements: Since the system inertia requirement is a constraint in the modeling, the Company should provide more analysis and detail supporting the assum...

AI summary The text raises modeling concerns regarding system inertia-based generation requirements, requesting more detailed analysis from the Company on assumptions, alternatives to generation, and limitations of the reliability tie's inertia benefits. It also asks for additional analysis on minimum inertia requirements under varying system conditions.

Section 1518
of this requirement and provide additional insight on the inertial need over time as load, DSM, and supply-side portfolio mix changes. Since ascribing this benefit of providing all the inertia requirements is uncertain and very valuable to...

AI summary The text discusses the need for additional insight into the inertial requirements over time as load, demand-side management (DSM), and supply-side portfolio mix change. It also requests a sensitivity analysis if the inertia benefits of the tie are substantially lower than assumed.

Section 1520
• Provide information regarding whether the battery+ synchronous condenser option for system inertia would also provide system capacity. b. Reliability Tie and Regional Integration -Treatment of risk: The Reliability Tie and Regional inter...

AI summary The text addresses questions regarding the system inertia provided by a battery+synchronous condenser option, the risks and studies required for reliability tie and regional integration, and the inclusion of offshore wind in the renewable resource portfolio. It emphasizes the need for cost-benefit analysis and planning flexibility.

Section 1526
s The following are comments from the Verschuren Centre for Sustainability in Energy and the Environment regarding the Initial Modeling results of the 2020 Integrated Resource Plan. Stranded Assets It seems counterintuitive that in modelin...

AI summary The Verschuren Centre for Sustainability in Energy and the Environment questions the modeling of stranded assets and the exclusion of inertia contributions from wind energy and energy storage in the 2020 Integrated Resource Plan. They argue that fossil fuel capacity may become stranded in a net-zero system and that wind and storage could contribute to system inertia.

Section 1527
les of gearbox-based turbines being able to provide more physical inertia as well. Future requests for renewable energy could provide an adder for turbines that can provide this service going forward. Since all Lithium Ion Battery systems...

AI summary The document discusses the potential of synthetic inertia from renewable energy sources, particularly lithium-ion battery systems and inverter-based technologies, to stabilize power grids. It references studies and projects like PG&E's EPIC 2.05 and NERC's white paper, which highlight the benefits of these technologies in low-inertia environments.

Section 1531
during the pre-IRP stage and is available on the IRP website. We suggest that NS Power should provide that derivation The decision to constrain the model to the UCAP (ELCC) and identify what drives the need for an ELCC reserve margin PRM,...

AI summary The text discusses the derivation of the ELCC reserve margin of 9% in the Integrated Resource Plan (IRP) and the decision to constrain the model to the UCAP (ELCC) PRM, influenced by stakeholder feedback during the Assumptions stage of the modeling process.

Section 1549
July 2020 Category Comment # Comment NS Power Response Wind CA-10 NS Power caps the wind build at 100 MW (700 MW total IRP runs consistently show economic utilization of non- integration installed) unless either reliability tie or a batter...

AI summary NS Power has capped wind build at 100 MW unless reliability measures are implemented. The PSC study identified stability issues during high wind and import periods. NS Power plans to study system stability and constraints related to wind integration.

Section 1550
f high wind and high imports conversations with stakeholders. without the reliability tie, wind generation could be capped at 700 MW. Second, under conditions of high wind, a minimum conventional (thermal or hydro) online capacity requirem...

AI summary The text discusses potential measures to ensure grid reliability during high wind conditions, such as establishing a minimum conventional online capacity requirement to provide local inertia and reduce imports, thereby avoiding the combination of high wind and high imports.

Section 1567
ELCC CA-17 ELCC of Wreck Cove and Mersey Wreck Cove is an energy-limited peaking plant and an important source of ancillary grid services such Consumer Can NS Power explain why Wreck Cove operates so little in as reserve. When modeled in t...

AI summary The text discusses the operation of Wreck Cove and Mersey power plants, focusing on their capacity factors, dispatch reliability, and ELCC (Effective Load-Carrying Capacity) values. It questions why Wreck Cove operates so little during high-load hours and whether it has sufficient energy resources to support a 95% ELCC rating, especially during long winter peaks. It also raises concerns about Mersey's dispatch reliability and flexibility in reserve operations.

Section 1574
Nova Scotia Power IRP Final Report Appendix J Page 209 of 245 IRP Participant Comments and NS Power Response July 2020 Category Comment # Comment NS Power Response Wind CanREA-01 Recommendation: more analysis be conducted to consider NS Po...

AI summary The Canadian Renewable Energy Association recommends further analysis on wind energy integration with storage and other technologies to enable more cost-effective wind energy without significant infrastructure investment. Nova Scotia Power has provided additional model runs and proposed an action plan for refining synchronized inertia requirements.

Section 1576
onse July 2020 Category Comment # Comment NS Power Response Wind CanREA-02 We understand that the operability analysis is likely to be The Operability Assessment completed as part of test scenarios that were evaluated in PLEXOS to ensure t...

AI summary CanREA-02 comments on the operability analysis of wind generation in Nova Scotia, emphasizing the need for dynamic/transient analysis to capture wind contributions to Fast Frequency Response services. NS Power acknowledges the need for additional work and proposes a post-IRP Action Plan item. The comment also highlights potential cost reductions from increased wind and inverter-based resources.

Section 1579
Analysis CanREA-03 Key unexplained results that are surprising and appear Plexos LT module optimizes resource plans constrained by counter-intuitive are the high levels of gas turbine build and all ancillary services (reserve) constraints,...

AI summary The analysis discusses modeling of ancillary service provision by various resources, noting that batteries and other non-synchronous resources can provide higher quality ancillary services compared to conventional resources. However, the quality of AGC service from batteries is too granular for capacity expansion models. NS Power highlights that the ELCC of battery storage declines quickly with installed capacity in Nova Scotia.

Section 1624
July 2020 Category Comment # Comment NS Power Response CTs HG-01 The liquid‐fueled CT’s are now over 40 years old. The model As discussed at the July IRP workshop, NS Power has scenarios include the continued use of these units to 2045, in...

AI summary Heritage Gas raises concerns about the aging liquid-fueled combined cycle (CT) units, which are over 40 years old and expected to operate until 2045. Fuel delivery relies on tanker trucks, and availability is constrained, especially in winter. NS Power responds that it has invested in maintaining these units and that their capacity is lower cost than alternatives, citing resource screening results.

Section 1633
Wind cap NF-02 Wind is capped at 700 MW unless tie, batteries, condensers Contingencies are not scheduled, and therefore the built. PSC study was based on stressed conditions and system cannot be pre-set to manage these Natural Forces seve...

AI summary The text discusses the limitations on wind capacity in Nova Scotia, suggesting that wind should be capped at 700 MW unless tie, batteries, or condensers are built. It highlights concerns about system contingencies and the economic implications of curtailing wind output or imports during system stress.

Section 1634
non-firm imports that are being economically dispatched in all The Study findings do not conclude that the wind installed scenarios. NPCC and NERC criteria state the capacity must be limited to 700 MW. All that they conclude, contingencies...

AI summary The study does not recommend limiting wind capacity to 700 MW but suggests temporary limitations during stressed system conditions. NS Power's draft findings indicate the need for further assessment of system stability with high renewable energy penetration and potential requirements for additional integration assets.

Section 1636
se July 2020 Category Comment # Comment NS Power Response Inertia NF-03 System inertial response requirement is over-stated. NS Power agrees that it will monitor industry developments around synthetic inertia. Natural Forces The minimum le...

AI summary The comment challenges the overstatement of system inertial response requirements, noting that the minimum level of 3,266 MW is not well substantiated based on the PSC study. NS Power agrees to monitor industry developments around synthetic inertia and acknowledges that the SIR requirement arises from high imports on the AC intertie.

Section 1640
and how changes could impact the optimal quantity and timing of these resources. Interconnection NF-06 Interconnection energy flows shown in aggregate. Can the Information has been provided in a manner that energy flows import and export e...

AI summary The text discusses interconnection energy flows and the eligibility of imports for ELCC calculations, noting that only firm imports contribute to capacity requirements. It highlights differences in practices between Europe and Nova Scotia and the need for firm import arrangements and transmission access for reliable capacity during peak events.

Section 1652
Inertia SBA-01 Since the system inertia requirement is a constraint in the NS Power will continue to advance modeling of modeling, the Company should provide more analysis and system inertia constraints. As part of its updated Small Busine...

AI summary The text discusses the need for more detailed analysis on system inertia requirements and constraints, including the limitations of assumptions made about the Reliability Tie and the need for modeling synchronous condensers. NS Power is expected to provide further analysis and update its modeling results.

Section 1656
Reliability Tie SBA-02 Treatment of risk: The Reliability Tie and Regional The Reliability Tie and Regional Interconnection and Regional interconnection are significant components of the initial options have been selected in multiple plans...

AI summary The document discusses the importance of evaluating risks and costs associated with the Reliability Tie and Regional Integration projects. It emphasizes the need for additional studies and cost comparisons if these projects are selected, ensuring that alternatives are considered and that decisions are made based on a balanced assessment of cost and risk.

Section 1672
o -A case where the Reliability Tie provides 50% of system inertia. system inertia requirement (1633 MW.sec)

AI summary The text references a scenario where the Reliability Tie contributes 50% of the system inertia, with a specific requirement of 1633 MW.sec for system inertia.

Section 1674
nd are fossil fuel generator over batteries contributing to certain modeled ancillary services. 3. Did the inertia constraint impact the decision process of Batteries contribute to all types of reserve the Diesel CT Screening? including re...

AI summary The text discusses the impact of inertia constraints on the Diesel CT Screening and evaluates the potential of wind turbines, demand control, and batteries to contribute to ancillary services. It also notes that transient system stability studies, which assess FFR, are outside the scope of long-term planning studies.

Section 1676
NS Power Response The draft Roadmap item included in the draft Report provides: 2. Complete detailed system stability studies under various current and future system conditions, reflective of both stressed system states and normal operatin...

AI summary NS Power's response outlines the need for detailed system stability studies under various system conditions, considering increased wind capacity and the impact of inverter-based generators on grid services like Synchronized Inertia and Fast Frequency Response.

Section 1680
Integration • 2.1C – Mid Electrification / Base DSM / Net Zero 2050 / Regional Integration • 3.2C – High Electrification / Max DSM / Accelerated Net Zero 2045 / Regional Integration These three resource plans represent significant evolutio...

AI summary The document discusses three resource plans by NS Power, representing different levels of electrification and demand-side management, with a focus on reliability modeling and planning reserve margin targets. The Reliability screening work confirms that all three plans meet the reliability criteria and supports an 8-9% Planning Reserve Margin target in 2045.

Section 1682
ons • Captures thermal resource and transmission forced outages • Captures variable availability of renewables & correlations to load • Tracks hydro and storage state of charge Information about E3’s RECAP model can be found here: https://...

AI summary The document discusses the Planning Reserve Margin (PRM) calculation by Nova Scotia Power using E3's RECAP model. It outlines the required PRM based on Installed Capacity (20%) and Unforced Capacity (9%), emphasizing the importance of reliability and capacity expansion modeling.

Section 1683
ct” 1-in-2 or “100% firm” capacity was forecast by NS Power Peak to be 2070 MW in 2020 Load 9 RECAP is used to test the reliability of the final PLEXOS portfolios Nova Scotia Power IRP Final Report Appendix K Page 12 of 264  RECAP calcula...

AI summary The document discusses the use of the RECAP model in assessing the reliability of energy portfolios, particularly in relation to capacity expansion modeling and Effective Load-Carrying Capability (ELCC) values. It mentions the planning reserve margin (PRM) and the importance of ensuring adequate system capacity with a target of 0.1 days/year loss-of-load expectation (LOLE).

Section 1684
rt Appendix K Page 13 of 264 Scenarios Evaluated 2045 Installed Capacity in PLEXOS ModelNova RunsScotia Power IRP Final Report Appendix K Page 14 of 264  After the initial PLEXOS modeling, RECAP tested the reliability of the system in 204...

AI summary The document evaluates three scenarios for Nova Scotia Power's 2045 installed capacity under different carbon targets, electrification loads, and renewable build-out levels. All scenarios meet the 0.1 days/year loss-of-load expectation (LOLE) target, with varying ultimate capacity (UCAP) primary reserve management (PRM) requirements based on load shapes.

Section 1685
2.0.C 2.1.C 3.2.C LOLE Target (days/yr) 0.10 0.10 0.10 Achieved LOLE (days/yr) 0.06 0.02 0.06 Achieved LOLh (hrs/yr) 0.18 0.08 0.21 All scenarios PRM Target (UCAP) 8% 8% 9% remain reliable in 2045, with small Achieved PRM (UCAP) 9% 11% 10%...

AI summary The document presents LOLE and PRM targets and achievements across multiple scenarios for 2045. It indicates that all scenarios remain reliable with small amounts of excess capacity, highlighting the performance of the power system in meeting reliability targets.

Section 1686
14 Scenario 2.0.C. Nova Scotia Power IRP Final Report Appendix K Page 17 of 264 Detailed 2045 RECAP results  E3 modeled NSP’s 2045 PLEXOS installed capacity and load in RECAP for 2.0.C, generating a UCAP target of 8%  RECAP modeled ELCCs...

AI summary The text presents detailed 2045 RECAP results for Nova Scotia Power's Integrated Resource Plan (IRP), including modeled installed capacity, load, and reserve requirements. The UCAP target is set at 8%, with LOLE achieved at 0.06 days per year, below the target of 0.1 days per year.

Section 1687
0.1 days/yr LOLE Achieved 0.06 days/yr PRM Target (UCAP) 8%

AI summary The document mentions LOLE (Loss-of-load expectation) achieved at 0.06 days per year and PRM (Primary Reserve Management) target (UCAP) at 8%. These metrics relate to system reliability and reserve management.

Section 1688
Installed Capacity (MW) ELCC (MW) / UCAP ICAP (MW) Includes all thermal units Dispatchable 1,505 1,418 1,505 Firm Imports 588 527 588 Includes only firm DR - - - imports Storage 33 27 27 Variable 1,132 152 152 Thermal, imports and Hydro 36...

AI summary The document presents capacity and ELCC (Effective Load-Carrying Capability) data for Nova Scotia's energy portfolio, including installed capacity, UCAP (Ultimate Capacity), ICAP (Installed Capacity), and PRM (Primary Reserve Management) metrics. It highlights a capacity surplus and the relationship between these metrics and reserve targets in 2045.

Section 1689
32 hit the target LOLE Note: RECAP estimates a PRM target endogenously given the scenario load characteristics and reserves in 2045, thus it may differ slightly from the PRM target estimated for the 2020 system. Similarly, ELCCs are also a...

AI summary The document discusses the modeling of Nova Scotia Power's 2045 installed capacity and load using the RECAP tool, resulting in a UCAP target of 8% and achieving a LOLE of 0.02 days per year, which is below the target of 0.1 days per year.

Section 1691
16 Scenario 3.2.C. Nova Scotia Power IRP Final Report Appendix K Page 19 of 264 Detailed 2045 RECAP results  E3 modeled NSP’s 2045 PLEXOS installed capacity and load in RECAP for 3.2.C, generating a UCAP target of 9%  RECAP modeled ELCCs...

AI summary Scenario 3.2.C presents detailed 2045 RECAP results for Nova Scotia Power's Integrated Resource Plan, including modeled installed capacity, load, and reserve requirements, with a UCAP target of 9% and LOLE achieved at 0.06 days per year.

Section 1692
0.1 days/yr LOLE Achieved 0.06 days/yr PRM Target (UCAP) 9% Installed Capacity (MW) ELCC (MW) / UCAP ICAP (MW) Dispatchable 2,000 1,889 2,000 Firm Imports 768 721 768 DR 0 0 0 Storage 430 305 305 Variable 1957 278 278 Hydro 366 279 366 Tot...

AI summary The document presents data on Installed Capacity (ICAP), Effective Load-Carrying Capability (ELCC), and Ultimate Capacity (UCAP) for Nova Scotia Power's Integrated Resource Plan (IRP) in 2045. It highlights a 10% PRM (UCAP) target achieved, a 18% PRM (ICAP) target achieved, and a capacity surplus of 40 MW. The note explains that these estimates are scenario-specific and may differ from 2020 projections due to changes in load characteristics and reserves.

Section 1694
ts may be triggered by any combination of high load, low renewable generation, or unit outages  For NS Power’s system, the probability of loss of load correlates well with periods of high load

AI summary The text discusses factors that may trigger load loss in NS Power's system, including high load, low renewable generation, and unit outages. It also notes that the probability of loss of load correlates well with periods of high load.

Section 1695
Avg Month-Hr Load (MWh) Avg Month-Hr LOLP (frac hrs w/ lost load) 1 2 3 4 5 6 7 8 9 10 11 12 0 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 1 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0....

AI summary The document presents a table showing average monthly load (in MWh) and loss-of-load probability (LOLP) across 12 months. The data indicates minimal to no loss-of-load probability, with a few instances showing very low percentages, such as 0.011% and 0.039%, suggesting high system reliability.

Section 1699
Avg Month-Hr Load (MWh) Avg Month-Hr LOLP (frac hrs w/ lost load) 1 2 3 4 5 6 7 8 9 10 11 12 0 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 1 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0....

AI summary The text presents a table showing average monthly load (in MWh) and loss-of-load probability (LOLP) for different months. The LOLP values are generally very low, with some months showing a slight increase, such as 0.010% or 0.011% in certain months. This data may be used to assess system reliability and capacity planning.

Section 1702
Avg Month-Hr Load (MWh) Avg Month-Hr LOLP (frac hrs w/ lost load) 1 2 3 4 5 6 7 8 9 10 11 12 0 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 1 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0....

AI summary The document presents a table showing average monthly load (in MWh) and the corresponding average monthly Loss of Load Probability (LOLP) across 12 months. The LOLP values are generally very low, with some months showing minimal probabilities of lost load, such as 0.011% in month 6 and 0.021% in month 9.

Section 1704
20 Nova Scotia Power IRP Final Report Appendix K Page 23 of 264 Conclusions Conclusions Nova Scotia Power IRP Final Report Appendix K Page 24 of 264  All portfolios meet their LOLE reliability targets, indicating that the PLEXOS portfolio...

AI summary The document concludes that all portfolios meet their LOLE reliability targets in 2045, but recommends more detailed modeling of electrification load shapes to assess long-term impacts on PRM targets. It highlights the need for detailed analysis of electrification's effects on peak load and vehicle charging patterns.

Section 1719
ders of magnitude or directional time frames. NS Power looks forward to receiving stakeholder comments on this Draft Action Plan, which will then be refined for inclusion in the IRP Final Report. I R P D R A F T F I N D I N G S , R O A D M...

AI summary NS Power proposes a Regional Integration Strategy to enhance access to firm capacity and low carbon energy, improve interconnection reliability, and support coal unit retirements. The plan includes identifying near-term import opportunities, conducting engineering and economic studies, and developing a Reliability Tie and Regional Interconnection with target in-service dates between 2025-2035.

Section 1728
Nova Scotia Power IRP Final Report Appendix K Page 77 of 264 IRP RESOURCE PLAN INSIGHTS Regional Integration Electrification Firm Capacity Resources Coal Retirements Reliability Tie and Regional Increased electricity sales due to New firm...

AI summary The IRP Resource Plan Insights discuss regional integration, electrification, firm capacity resources, and coal retirements. Electrification can reduce electricity rates and support carbon reductions. Firm capacity resources, like efficient combustion turbines, will replace retiring coal units, aligning with GHG emissions caps. Coal units are retiring due to declining capacity factors.

Section 1732
al revenue requirements 25 year NPV Revenue Requirement over the planning horizon (with and without end-effects adjustment) Average Annual Partial Rate Impact - 25-yr Magnitude and timing of electricity rate effects 10 year NPV Revenue Req...

AI summary The text discusses various aspects of electricity planning and regulation, including revenue requirements, reliability and grid stability, plan robustness, greenhouse gas emissions reductions, and flexibility in decision-making. Key topics include the evaluation of resource capacity, essential grid services, and the impact of assumptions on plan outcomes.

Section 1739
2.1C.WIND-2 • 2.1C.WIND-3 – Low Inertia Constraint • 2.1C.WIND-4 – No Inertia / No Integration 2.1C.WIND-1 • General model behaviour is that under lower wind and wind battery prices, the ultimate wind build out does not change but it does...

AI summary The analysis discusses the impact of wind energy integration on system inertia and stability, highlighting that significant wind penetration beyond current models requires further study. It also notes that reducing inertia constraints has limited effects and that lower wind and battery prices may lead to earlier wind build-out. These findings are part of the Integrated Resource Plan (IRP) draft findings.

Section 1745
al revenue requirements 25 year NPV Revenue Requirement over the planning horizon (with and without end-effects adjustment) Average Annual Partial Rate Impact - 25-yr Magnitude and timing of electricity rate effects 10 year NPV Revenue Req...

AI summary The text outlines key evaluation criteria for assessing electricity plans, including revenue requirements, reliability, grid services, plan robustness, emissions reduction, and flexibility. It emphasizes quantitative and qualitative assessments of various aspects such as supply adequacy, essential grid services, and sensitivity to changes in assumptions.

Section 1747
d Effects ($MM) $16,692 Essential Grid Services • Essential Grid Service requirements are met as modeled 10-yr NPVRR ($MM) $6,850 Resource Adequacy & PRM • Reliability Tie: 2035 • Regional Integration: n/a Average Annual Partial Rate Impac...

AI summary The document presents scenario metrics and evaluation related to the Integrated Resource Plan (IRP) of Nova Scotia Power. It highlights essential grid services, resource adequacy, CO2 emissions, and the impact of natural gas prices on the plan's robustness and compliance with sustainability goals.

Section 1748
64 1.0C L O W E L E C . / B A S E D S M / C O M PA R AT O R E M I S S I O N S / R E G I O N A L I N T E G R AT I O N Scenario Metrics & Evaluation 25-yr NPVRR ($MM) $12,190 General Notes • Incremental firm imports enable an economic coal u...

AI summary The document presents scenario metrics and evaluation data for a 25-year and 10-year Net Present Value of Resource Requirements (NPVRR) under different conditions, including coal unit retirements, reliability tie construction, and regional interconnection. It also includes CO2 emissions data and mentions non-compliance with Sustainable Development Goals Act.

Section 1751
Resource Adequacy & PRM 10-yr NPVRR ($MM) $6,820 • Reliability Tie: 2030 • Regional Integration: 2037 Plan Robustness & Flexibility Average Annual Partial Rate Impact • Regional Integration provides flexible ability to meet emissions const...

AI summary The document discusses resource adequacy and Peak Resource Management (PRM), including 10-year Net Present Value of Resource Requirements (NPVRR) and carbon dioxide (CO2) emissions from 2021 to 2045. It references the Integrated Resource Plan (IRP) and mentions reliability tie and regional integration timelines.

Section 1752
otia Power IRP Final Report Appendix K Page 123 of 264 2.1A MID ELEC. / BASE DSM / NET ZERO 2050 / CURRENT LANDSCAPE Scenario Metrics & Evaluation 25-yr NPVRR ($MM) $13,353 General Notes • Reliability Tie built in 2031 enables wind integra...

AI summary The text discusses the Nova Scotia Power Integrated Resource Plan (IRP) Final Report, focusing on scenario metrics and evaluation related to the 25-yr and 10-yr Net Present Value of Resource Requirements (NPVRR), reliability, resource adequacy, CO2 emissions, and grid services. Key factors include the impact of wind integration, gas capacity, and coal unit conversions.

Section 1757
converted to gas in 2037 Essential Grid Services 10-yr NPVRR ($MM) $8,232 • Essential Grid Service requirements are met as modeled Resource Adequacy & PRM • Reliability Tie: 2030 Average Annual Partial Rate Impact • Regional Integration: n...

AI summary The document discusses the Essential Grid Services, Resource Adequacy & PRM, and Plan Robustness & Flexibility, highlighting the 10-year NPVRR, average annual partial rate impact, and CO2 emissions from 2021 to 2045. It outlines the reliance on natural gas and the limited ability to adjust supply sources.

Section 1770
Adequacy & PRM 2021-2030 (%) 1.2% 0.6% • Reliability Tie: 2030 2021-2045 (%) 0.8% 0.7% • Regional Integration: 2031 Plan Robustness & Flexibility Total CO2 Emissions 2021-2030 (MT) 39.9 41.8 • No change relative to 2.1C Base Total CO2 Emis...

AI summary The document discusses the adequacy and Peak Resource Management (PRM) metrics for Nova Scotia Power's Integrated Resource Plan (IRP) from 2021 to 2045, including Loss of Load Probability (LOLP) and CO2 emissions. It also outlines the New Installed Capacity Comparison for 2045 and Scenario Metrics & Evaluation under the MID DSM scenario.

Section 1775
676 $6,820 end effects are considered relative to 2.0C Base DSM indicating the solutions are very close economically Essential Grid Services Average Annual Partial Rate Impact • No change relative to 2.0C 2021-2030 (%) 0.3% 0.9% 2021-2045...

AI summary The text presents a comparison of CO2 emissions and grid services under different scenarios, including the 2.0C DSM-5 (Mid DSM) plan. It highlights minimal changes in reliability and grid services, with a focus on emissions reductions and the integration of regional resources by 2037.

Section 1779
Adequacy & PRM 2021-2030 (%) 1.8% 0.9% • Reliability Tie: 2034 2021-2045 (%) 1.2% 0.9% • Regional Integration: 2040 Total CO2 Emissions 2021-2030 (MT) 38.4 40.7 Plan Robustness & Flexibility Total CO2 Emissions 2031-2045 (MT) 23.7 24.3 • N...

AI summary The document discusses reliability targets and carbon emissions for Nova Scotia Power's Integrated Resource Plan (IRP) from 2021 to 2045, highlighting reliability tie timelines and CO2 emissions projections. It also references the MID DSM and Net Zero 2045 initiatives, along with regional integration efforts.

Section 1785
Essential Grid Services 0.6% 0.7% • No change relative to 2.1C Resource Adequacy & PRM Total CO2 Emissions 2021-2030 (MT) 30.5 41.8 • Reliability Tie: 2025 Total CO2 Emissions 2031-2045 (MT) 26.1 29.1 • Regional Integration: 2026 Total CO2...

AI summary The text discusses essential grid services, resource adequacy, and PRM (Peak Resource Management) under the context of the Integrated Resource Plan (IRP) from Nova Scotia Power. It outlines CO2 emissions projections and mentions considerations for flexibility in importing energy to balance increased wind capacity.

Section 1789
(%) 0.5% 0.6% • NPVRR is reduced relative to 3.1C in two of three metrics, slightly higher in 10-yr NPV due 2021-2045 (%) 0.6% 0.7% to advancement of investment Essential Grid Services Total CO2 Emissions 2021-2030 (MT) 26.8 41.8 • No chan...

AI summary The document discusses the impact of the 2.1C.WIND-3 scenario on CO2 emissions and resource adequacy, noting a reduction in NPVRR in some metrics and the need for further consideration of flexibility in import energy to balance increased wind capacity. It also highlights the importance of regional integration and reliability ties by 2023 and 2036.

Section 1793
overall resource plan optimization 2021-2030 (%) 0.5% 0.6% • Cost differences are small over all three NPV metrics 2021-2045 (%) 0.7% 0.7% Essential Grid Services • Current studies indicate that 2200MW.sec of online kinetic inertia is not...

AI summary The document discusses the optimization of the overall resource plan from 2021 to 2045, highlighting small cost differences across NPV metrics and concerns about grid stability, specifically the need for additional inertia and studies. It also outlines reliability ties and regional integration timelines and notes no change from the 2.1C plan.

Section 1796
ment and replacement energy costs, NPVs incorporating MT/ST Production 10-yr NPVRR ($MM) $7,049 $7,067 Costs are not significantly lower than the base scenario 2.1C Essential Grid Services • This run is intended as a test case to understan...

AI summary The text discusses the financial and environmental impacts of different energy planning scenarios, highlighting that energy costs and CO2 emissions are higher in certain cases. It also explores the performance of the model under extreme conditions, such as no inertia and no wind integration, and emphasizes the importance of flexibility in resource planning.

Section 1799
Scenario Metrics & Evaluation Sensitivity Base (2.1C) 25-yr NPVRR ($MM) $13,097 $13,141 General Notes • While the Mersey system was economically retained in the screening phase, this sensitivity was completed in order to understand how cap...

AI summary The document evaluates the financial and operational impacts of decommissioning the Mersey Hydro system, including the replacement of capacity and energy, changes in regional integration timelines, and the associated decommissioning costs. It also outlines the partial rate impact on the grid due to these changes.

Section 1802
• No change relative to 2.1C 2021-2030 (%) 0.9% 0.6% 2021-2045 (%) 0.7% 0.7% Resource Adequacy & PRM • Reliability Tie: 2024 Total CO2 Emissions 2021-2030 (MT) 43.5 41.8 • Regional Integration: 2026 Total CO2 Emissions 2031-2045 (MT) 35.1...

AI summary The text presents emission reduction targets and resource adequacy plans for Nova Scotia Power, including CO2 emissions reductions from 2021-2030 and 2031-2045, as well as key milestones such as the Reliability Tie in 2024 and Regional Integration in 2026. It also references a scenario evaluation under the Base (2.0A) sensitivity.

Section 1813
acity drops in 2045, identify the resources the model substitutes for battery capacity, and discuss implications of late- model treatment of battery storage in the end effects calculation. Transmission and system inertia The modeling raise...

AI summary The document raises concerns about the modeling of battery storage and system inertia in the Integrated Resource Plan (IRP), noting inconsistencies in how battery capacity and inertia impact the timing of the reliability intertie and regional integration. It also highlights sensitivity of the model to small changes in battery costs.

Section 1815
optimize a transition to a more adaptive resource mix, and that some of these interactions might be enabling higher retirements of “slow inertia” units. This concept is consistent with the model output from 2.1C.IMPORT-3: with the reliabil...

AI summary The document discusses the impact of the reliability intertie on inertia, unit retirement, and resource mix, including questions about inertia contributions from steam units, the role of the reliability intertie in enabling imports, and the implications for future resource planning and RFP processes.

Section 1838
ificant penetrations and determine whether additional dynamic system inertia constraints can enable this level of additional wind integration on the Nova Scotia system.” (Slide 47) CanREA observes that NSPI focuses on constraints to wind i...

AI summary CanREA argues that NSPI has not fully considered the frequency response capabilities of wind generation, such as fast frequency response (FFR), which can reduce the need for synchronous inertia. This is important as wind generation is highlighted in the IRP as a key resource for replacing coal-fired generation.

Section 1848
1. Nova Scotia’s Sustainable Development Goals Act is a significant milestone in the province’s climate plans, and actions adhering to these emission goals is a welcome scenario. The EAC supports the notion of a steep reduction in reducing...

AI summary The text discusses Nova Scotia's Sustainable Development Goals Act and the importance of studying zero-emission scenarios. It highlights the benefits of firm capacity imports and grid reliability improvements, while expressing concerns about the risks of relying on gas turbine infrastructure and natural gas purchases due to potential carbon emissions.

Section 1857
Elisa Obermann, Executive Director of Marine Renewables Canada Via Email: [email protected] Greg Robart, CEO Smart Grid Innovation Network Via Email: [email protected] Envigour Memo September 16, 2020 Page 3 of 3 Nova Scotia Power IRP F...

AI summary Heritage Gas highlights the importance of natural gas for grid reliability and environmental goals in Nova Scotia's Integrated Resource Plan. The document discusses the reliance on natural gas and the continued operation of liquid-fueled combustion turbines for the next 25 years.

Section 1858
ity of Liquid-Fueled Combustion Turbines (“CTs”) In Draft Finding 3(b), NSPI describes retaining these units for another 25 years, at which point they will have been in operation for nearly 70 years: “NS Power’s existing CT resources provi...

AI summary The text discusses concerns raised by Heritage Gas regarding the reliability of NSPI's 1970’s-era combustion turbines, noting that they failed during periods of high ambient temperatures and that NSPI was aware of these limitations. NSPI argues that these units provide economic benefits and can be sustained with reinvestment.

Section 1859
anticipated and expected by NSPI personnel. This suggests that the reliability of these units is limited and those limitations are understood by those who operate NSPI’s system. NSPI’s seven 33 MW combustion turbines’ performance during th...

AI summary The audit highlights concerns about the reliability of NSPI's combustion turbines, noting that their performance during the audit period had elevated DAFOR rates and low availability factors. The report also states that NSPI significantly underestimated the frequency these units would be called upon, with actual output exceeding forecasts by over 1,300%.

Section 1862
also notes that an increase of this size in natural gas consumption in the region requires long-term natural gas transportation commitment planning, which should also be reflected in the Action Plan. Electrification and Associated Transmis...

AI summary The text discusses the need for long-term natural gas transportation planning due to increased consumption, significant investments in transmission and distribution infrastructure driven by electrification and environmental targets, and the role of natural gas in supporting the transition to low carbon fuels. It also references ongoing DSM Matter No. M09471 regarding avoided T&D costs.

Section 1877
. Even before consideration of the “low wind cost” sensitivities, several scenarios, including those identified as resulting in lower electricity rates, have substantially higher wind volumes. • CO2 levels vary widely between scenarios. Th...

AI summary The analysis highlights that scenarios with lower electricity rates involve higher wind volumes and varying CO2 levels. Lower CO2 emissions are valued for risk mitigation and promoting electrification in other sectors. The document recommends further consideration of risk assessment to identify resilient scenarios, particularly those with higher renewables and lower emissions.

Section 1890
Nova Scotia Power IRP Final Report Appendix K Page 226 of 264 Cooke Energy and Utility Consulting Ltd. comps, or the 2nd AC intertie. This has been discussed at length before, and NSP’s adherence to this position is quite frankly, rather b...

AI summary The text discusses Nova Scotia Power's (NSP) position on managing wind output during system instability, arguing that curtailing wind output during rare extreme conditions is a standard practice in systems with high intermittent renewable resources. It also notes that stressed system cases from the Power System Stability Study are unlikely to occur based on 2019 data.

Section 1897
sources. The IRP analysis relied on conclusions of the 2019 PSC study, but NSP has acknowledged that additional analysis will be needed to more fully understand the inertia requirements in the future. The draft Finding #2 acknowledges this...

AI summary The analysis of the Integrated Resource Plan (IRP) relies on the 2019 PSC study, but Nova Scotia Power (NSP) acknowledges that further analysis is needed to understand future inertia requirements. The draft Finding and Roadmap highlight the need for additional system stability studies, particularly regarding wind integration and potential contributions from wind projects to system inertia.

Section 1926
Category Participant Comment NSP Response / Consideration for Final Report Wind sensitivity CA We see extraordinary sensitivity to relatively modest drivers. For example, lowering the From a reliability perspective, NS Power has modeled th...

AI summary The comment highlights the sensitivity of wind integration to factors like battery costs and the impact of the reliability tie on system inertia. NS Power explains that the model considers reliability through the reliability tie and PRM, and that steam unit constraints influence the transition to a more adaptive resource mix.

Section 1927
ts, combustion turbines, the letter of comment); rather, the model is constrained by steam unit minimum up and down times (and and wind (presumably for the energy). is penalized by unit start costs) which would suggest that a more flexible...

AI summary The text discusses the use of combustion turbines for inertia and other services, the impact of unit start costs on system flexibility, and the integration of unit commitment costs into optimization models. It also touches on the trade-offs of transmission and reliability measures, and the influence of inertia and reserve constraints on retirement pace.

Section 1928
ies the inertia values by unit that on retirement pace for this reason. More broadly, as the system transitions to a resource mix with more NS Power provided previously. Does “slow inertia” refer to the long start-up times of steam variabl...

AI summary The text discusses the impact of transitioning to a resource mix with more variable generation on system inertia and the role of the reliability tie in providing inertia and enabling wind integration. It also explores the relationship between unit commitment costs and the pace of resource transition.

Section 1938
deficiency and require incremental CT resources, at a higher cost than sustaining the existing fleet. Dispatch and CA NS Power’s PLEXOS model incorporates system operating requirements and generating unit properties operating reserve Day-A...

AI summary The document highlights discrepancies between NS Power’s Day-Ahead and Real-Time schedules and actual dispatch, leading to inefficiencies. It also notes issues with operating-reserve surpluses and recommends that NS Power verify its IRP model assumptions and update findings to ensure optimal reserve provision and cost efficiency.

Section 1962
Wind/inertia/FFR CanREA CanREA observes that NSPI focuses on constraints to wind integration, questioning whether NS Power’s Action Plan includes completing further system stability studies to determine whether “additional dynamic system i...

AI summary CanREA highlights that NS Power's Action Plan may not fully consider the frequency response capabilities of wind generation, such as Fast Frequency Response (FFR), which can reduce the need for synchronous inertia. NS Power conducted sensitivities to assess the impact of reduced inertia on resource expansion plans.

Section 1964
providing. By focusing on just this ancillary service NSPI failed to consider the range of service. Batteries contribute to all types of reserve including regulation (raising and lowering), spinning ancillary services that are critical to...

AI summary The text discusses the importance of ancillary services, particularly frequency response and ramp down services, in enabling the integration of wind generation in Nova Scotia. It highlights the limitations of the PLEXOS framework in assessing transient system stability and FFR, which are critical for grid reliability.

Section 1966
services that allow NSPI to dispatch off thermal generating units and rely on the fast absence is not expected to have an impact on coal retirement decisions. However, if FFR services are frequency response capability that wind generators...

AI summary The text discusses the potential of wind, solar, and battery resources to provide ancillary services such as fast frequency response (FFR), which can enhance system reliability and reduce costs. NS Power is committed to further studies on system stability and the integration of these resources into the grid.

Section 1967
operate at a reduced capacity to provide headroom to offer ancillary services (e.g., the provision of primary frequency response) under some operating conditions. Wind/inertia/FFR CanREA Sensitivities (2.1C.WIND-3 (LOW INERTIA CONSTRAINT))...

AI summary The text discusses the impact of wind energy integration on system inertia and the need for further studies to understand the implications of increased wind penetration. It also highlights the importance of regional integration and stakeholder input in updating studies and modeling assumptions.

Section 1999
emissions to align with net-zero carbon scenario. Therefore, it would be prudent to have a future-proof plan ready for deployment. Transmission EAC Access to firm capacity imports from the Maritime provinces and Quebec would be highly NS P...

AI summary The text discusses the importance of aligning emissions with a net-zero carbon scenario and the need for a future-proof plan. It also highlights the role of wind energy and the potential benefits of firm capacity imports from the Maritime provinces and Quebec. NS Power acknowledges the value of the Reliability Tie and the integration of renewable energy sources.

Section 2068
alyses. System Inertia SBA / The draft Finding #2 acknowledges this, noting that “Further work is required to assess NS Power has identified future work related to wind stability studies at higher penetrations in the Daymark system stabili...

AI summary The document discusses NS Power's ongoing work to assess system stability and inertia constraints related to higher wind energy penetration in Nova Scotia. It references studies and sensitivity analyses conducted to evaluate the impact of wind integration on system reliability and the Reliability Tie.

Section 2070
The modeling of the inertia requirement has supported certain resource decisions, in NS Power has not expressly modeled a FFR requirement, which is a service that is separate from particular the addition of the Reliability Tie which is ass...

AI summary The document discusses the modeling of inertia requirements in the NSP system, noting that the Reliability Tie provides all necessary inertia. It also mentions that NSP has not evaluated wind projects' potential to provide fast frequency response (FFR), despite understanding that wind resources can offer various levels of FFR services. The document recommends that NSP include a plan for additional analyses in the Integrated Resource Plan (IRP).

Section 2071
nt services on certain generators (e.g. wind) are found to reduce the synchronous inertia constraint, the resources to address these needs (conventional generators, the Reliability Tie, Maritime economics of building more variable renewabl...

AI summary The document discusses the need to address reliability challenges due to reduced synchronous inertia from wind generators, suggesting solutions such as conventional generators, the Reliability Tie, and load resources. NS Power is committed to studying these issues and has incorporated these considerations into its Integrated Resource Plan (IRP) Action Plan. Coordination with New Brunswick and supply availability are emphasized for the Reliability Tie and Regional Integration.

Section 2076
MW (Slide 57). We caution on the limitation placed by identifying Demand Response potential of only 75 MW. This resource needs more examination to understand its true size potential and cost for different levels of DR. IRP Process / Overal...

AI summary The Town of Wolfville highlights challenges small communities face in engaging with the Integrated Resource Plan (IRP) process due to lack of resources and expertise. They suggest an updated mandate to better address climate change and environmental concerns within the IRP process. NS Power acknowledges the concerns and agrees with the need for enhanced reliability screening.

Section 2090
es that could allow wind to reduce the inertial constraint that NS Power identified. NS Power made one modest change in how it modeled wind recognizing that wind can provide a regulation down service. A number of parties also critiqued the...

AI summary NS Power adjusted its wind modeling to account for regulation down service, while parties critiqued the PSC study's 700 MW wind constraint. CanREA suggests reducing imports over the NB intertie instead of wind generation and recommends stakeholder-inclusive system stability studies to increase confidence in findings.

Section 2108
These three strategies may be employed in combination. One approach could be to sequence their deployment, relying on operating practices during the early stages of expanded wind development that could result in relatively large curtailmen...

AI summary The text discusses strategies for managing wind energy integration, including sequencing deployment, curtailment, and infrastructure upgrades. It also highlights the need for coordination in planning, cost estimation, and modeling to address system inertia and reliability concerns. Telos Energy's comments and Plexos modeling are referenced in this analysis.

Section 2109
experience demonstrating that the system can be operated reliably with early retirement of additional thermal units. NS Power comments that “…it is likely that inertia and reserve constraints have an influence on retirement prematurely. Wi...

AI summary NS Power discusses the reliability of the system with early retirement of thermal units and the potential use of synchronous condensers. They also mention the impact of the in-service date of the Reliability Tie on costs and system inertia sensitivity.

Section 2144
n transition. The plans fall short of “optimal” as the software was presented with limited regional integration opportunities. Incremental transmission builds must be examined fully in future studies. As highlighted in EAC’s previous comme...

AI summary The text emphasizes the need for comprehensive future studies on incremental transmission builds and highlights the importance of achieving high electrification levels without reliance on natural gas. It also stresses the need for future planning to be transparent, inclusive, and managed by an independent third party with a focus on affordability, reliability, and sustainability.

Section 2163
ng horizon (adjusted for end-effects). NS Power will continue to use this primary metric to guide resource planning, and will also assess others of increasing importance, including: - Magnitude and timing of electricity rate effects; - Rel...

AI summary NS Power will use a primary metric for resource planning and evaluate secondary metrics such as electricity rate effects, reliability, grid services, plan robustness, GHG emissions, and flexibility. These evaluation criteria have evolved since the Terms of Reference were presented.

Section 2197
3 POTENTIAL CAUSES OF OVERFORECASTING To be clear, the pattern of overcasting is not unique to BC Hydro. Our research reveals that other utilities and system operators also persistently and substantially overestimate long-term requirements...

AI summary The text discusses the issue of overforecasting in long-term energy planning, noting that it is not unique to BC Hydro. It highlights risk asymmetry bias, where reliability has historically taken precedence over cost-effectiveness and environmental concerns. With changing market conditions, overforecasting now leads to unnecessary investments and rate increases, impacting the low-carbon electrification transition.

Section 2203
of 125 November 13, 2020 Nicole Godbout Director, Regulatory Affairs Nova Scotia Power Inc. PO Box 910 Halifax, NS B3J 2W5 RE: M08929 – NSPI Integrated Resource Planning – Draft IRP Report Heritage Gas has reviewed the Draft IRP Report, di...

AI summary Heritage Gas supports the inclusion of natural gas in Nova Scotia Power Inc.'s Integrated Resource Plan, citing its role in providing reliable generation and supporting renewable integration. It highlights natural gas as a low-carbon option and emphasizes its importance in ensuring system reliability during periods of low renewable generation.

Section 2207
pen to collaborating with NSPI on the process to achieving an integrated energy system, which will achieve lower emissions and reduce costs to the benefit of all ratepayers. Conversion of Coal-to-Gas Roadmap item 1 discusses the need for “...

AI summary The document discusses NSPI's efforts to collaborate on an integrated energy system, the need for engineering studies on coal-to-gas conversions at Trenton and Point Tupper Generating Stations, and the importance of studying the regional intertie for firm capacity and reliability, especially in the context of climate change impacts.

Section 2224
l strategies to meet them, and we urge that this is undertaken as soon as possible, in order to prevent this issue continuing to inappropriately constrain decisions on the optimum resource portfolio. 3. Selection of Reference Plan, and “Si...

AI summary The text discusses the selection of a reference plan for a low electrification scenario and highlights the importance of system stability studies to ensure reliability under stressed conditions. It raises concerns that the reference plan may not be the optimal choice due to potential lower rates and policy benefits in other scenarios.

Section 2241
Wind Consumer Plan for potential transmission projects in parallel to NS Power will continue transmission planning (for both integration Advocate (1b) both additional study of wind integration as well as the the Reliability Tie and Regiona...

AI summary NS Power is planning transmission projects in parallel with wind integration studies and the recommended all-source RFP. This includes evaluating strategies such as an early in-service date for the Reliability Tie and implementing operating practices to ensure system reliability.

Section 2242
P a g e 1 45 Nova Scotia Power IRP Final Report Appendix L Page 82 of 125 Category Participant Comment NS Power Response and pre-curtailment of wind resources for operating Additional potential benefits of the Reliability Tie not reserve p...

AI summary The document discusses the potential benefits of the Reliability Tie, including the use of battery storage and synchronous condensers for reserve purposes, and mentions that additional benefits will be studied as part of Action Item 1b.

Section 2244
More in-depth investigation of the system inertia question is called for. If inertial constraints can be satisfied by a combination of wind curtailment and other operating limits, additional battery storage and synchronous condensers, NS P...

AI summary The text discusses the need for further investigation into system inertia, particularly through wind curtailment and battery storage. It also mentions the importance of reviewing the Reliability Tie and conducting further modeling for the Mersey hydroelectric facilities redevelopment, incorporating IRP findings and updated data.

Section 2266
P a g e 8 45 Nova Scotia Power IRP Final Report Appendix L Page 89 of 125 Category Participant Comment NS Power Response wind and the constraints associated with integrating synchronous generators. New wind generation is additional volumes...

AI summary The document discusses the integration of wind energy and the challenges associated with it, including the need for synchronous generators and the use of dispatchable generators for ancillary grid services. NS Power uses the PLEXOS optimizer to make resource addition/retirement decisions, informed by market pricing and IRP scenarios.

Section 2272
ry energy storage systems. CanREA believes that securing more market- based pricing information for these other clean energy resources would be valuable given the pricing trends for solar and energy storage. Wind CanREA Furthermore, to the...

AI summary CanREA suggests that NS Power should reassess the role of solar and energy storage in its resource mix based on market pricing trends, and highlights the need for detailed system stability studies to address inertia constraints from wind and other non-synchronous resources.

Section 2273
d resources to provide of both stressed system states and normal operating frequency response services and by so doing to reduce conditions, while considering higher quantities of P a g e 10 45 Nova Scotia Power IRP Final Report Appendix L...

AI summary The document discusses Nova Scotia Power's (NS Power) response to comments from the Canadian Renewable Energy Association (CanREA) regarding the ability of wind to provide regulation services and reduce inertia constraints. NS Power made a modest change in its modeling of wind, recognizing its capacity to provide regulation down services.

Section 2276
NS Power also tested a boundary case, 2.1C.WIND-4, which removed synchronous inertia and wind integration constraints. Under this resource plan, wind additions beyond 100MW begin in 2024 and continue in 2025, timing which is aligned with I...

AI summary NS Power tested a boundary case involving wind integration constraints, suggesting wind additions beyond 100MW would begin in 2024 and continue in 2025, aligned with the IRP Action Item 3d. Some parties critiqued the PSC study used to set a 700 MW wind constraint, arguing NSPI's modeling was overly conservative.

Section 2279
Category Participant Comment NS Power Response required to confirm and/or expand the conclusions from the PSC Study, given the limited number of cases studied. Wind / PSC CanREA In the PSC Study the loss of the New Brunswick intertie NS Po...

AI summary CanREA suggests that reducing imports over the NB intertie may be more effective than reducing wind generation during high import levels, as imports have higher incremental costs and could provide grid services. NS Power agrees but notes that pre-curtailment of imports may not be economic due to the significant quantities of non-firm imports being dispatched.

Section 2283
Category Participant Comment NS Power Response operating conditions, which actually appear to be quite results. This work will also consider the impacts of grid rare, the output of wind should be limited to 700 MW. service provision from i...

AI summary CanREA suggests that wind output should be limited to 700 MW under rare operating conditions and that additional wind capacity could be procured if regulation services and other deficiencies in the PSC Study are addressed. NS Power's Wind Procurement Strategy is referenced, and the impact of new ancillary services on grid reliability is discussed.

Section 2284
ystem conditions that posed reliability risks (e.g., low be modeled to determine the timing and capacity of wind loads) then wind output greater than 700 MW could be additions. constrained down after imports were reduced. When curtailed, t...

AI summary The text discusses system conditions that could pose reliability risks, particularly when wind output exceeds 700 MW and may be constrained after imports are reduced. It also mentions that curtailed wind turbines could provide primary frequency response, potentially offsetting some of the associated costs.

Section 2285
these wind turbines would be available to provide primary frequency response, offsetting at least in part costs associated with such a curtailment.

AI summary The text discusses how wind turbines can provide primary frequency response, potentially offsetting costs associated with curtailment.

Section 2289
dered an adequate range of planning costs and characteristics of such resources, and their scenarios through this omission, given the urgency of interaction with grid services and reliability are not well climate action. Moreover, since el...

AI summary The text discusses the challenges of aligning electricity sector planning with the SDGA, noting that current scenarios lack adequate consideration of resource costs and grid interactions. It highlights the uncertainty around achieving net-zero emissions and the potential for stranded assets if natural gas is used beyond 2050. NS Power suggests revisiting modeling once enabling technologies and legislative frameworks are more established.

Section 2313
are challenging to cost-effectively electrify. These include heavy vehicle transportation, industrial and institutional processes. Therefore, in addition to the role of natural gas in supporting the transition of the electrical grid, the i...

AI summary The text discusses the role of natural gas infrastructure in supporting the transition of the electrical grid and reducing GHG emissions, with a focus on integrating the electrical grid with the natural gas pipeline network to increase reliability and lower energy costs. It also mentions the potential of hydrogen and renewable natural gas (RNG) in supporting the net-zero emissions target.

Section 2320
Category Participant Comment NS Power Response The tie line connection to New Brunswick will be exposed to the increasing frequency and severity of NS Power concurs that reliability implications will be storms related to climate change imp...

AI summary The text discusses concerns regarding the reliability of the tie line connection to New Brunswick in the context of climate change and the aging LFO-fired CTs. NS Power acknowledges the need to assess reliability implications and the importance of monitoring and re-evaluating the economics of maintaining these units.

Section 2332
of system stability issues and procurement. consideration of optimum operational strategies to address system reliability with higher levels of wind generation; NS Power has committed to completing a detailed system 2. An RFP to determine...

AI summary The document outlines NS Power's commitment to addressing system stability issues and conducting a detailed system stability study to evaluate the impact of higher wind generation on system reliability. It also mentions the importance of setting a clear program of work with target dates and stakeholder engagement.

Section 2348
Category Participant Comment NS Power Response difference in the extent of wind deployment during the 2020s, from the alternative scenario 2.1C. Wind Natural Forces The report also notes regarding scenario 2.1C.WIND- NS Power has modified...

AI summary Natural Forces argues that scenario 2.1C in the report is a feasible resource plan, despite the report's characterization. NS Power responds by changing the description from 'feasible' to 'operable' due to the lack of synchronous inertia in the scenario. NS Power acknowledges the theoretical possibility of high wind deployment but emphasizes the need for further study on operational practices and system stability.

Section 2372
sing a proposed retirement? What will be the decision metrics that will be used to determine retirement timing? Future steps / SBA Gas conversions: The draft IRP notes that coal-to-gas NS Power has committed to advancing the engineering Co...

AI summary The text discusses the proposed coal-to-gas conversions in Nova Scotia's Integrated Resource Plan (IRP) and the need for a framework to evaluate their economic viability. It raises concerns about potential stranded costs if non-emitting alternatives become more economical and asks about a breakeven point for switching to non-emitting options.

Section 2375
Category Participant Comment NS Power Response with the economics of the conversions, and what analysis will support the decision-making? Future steps / SBA Regional Integration and Reliability Tie: The draft NS Power agrees that the under...

AI summary The SBA supports the Regional Integration and Reliability Tie strategy as economically beneficial, based on current analysis. NS Power agrees that the assumptions in the IRP require validation and reassessment, and notes that its Action Plan Item #1 incorporates many of the points raised.

Section 2397
FINDING STAKEHOLDER STAKEHOLDER COMMENT REFERENCE ‘As we have previously noted, this process is only a part, albeit a very important part, of developing a roadmap for Canada and Nova Scotia to achieve net-zero energy emissions by 2050. As...

AI summary The document discusses the importance of decarbonizing the electricity system as part of achieving net-zero energy emissions by 2050. Nova Scotia Power is highlighted as a key player in grid decarbonization and infrastructure deployment. Collaboration is emphasized as essential for the successful implementation of plans like HalifACT.

Section 2401
FINDING STAKEHOLDER STAKEHOLDER COMMENT REFERENCE achieve lower emissions and reduce costs to the benefit of all ratepayers.’ JFS Hydrostor No comment n/a Natural Supportive: 2020-11-13; p. XX Forces -‘While this is almost certainly correc...

AI summary The stakeholder comments highlight the potential of the electricity sector to facilitate decarbonization of other sectors through electrification without increasing electricity rates. Natural Forces supports this view and emphasizes the need for significant transformation of the generation resource base to meet Nova Scotia’s emission reduction goals.

Section 2432
Forces PHP Generally supportive with comments on importance of 2020-11-13; p.1/2-2/2 flexibility and collaboration: -‘As opportunities may arise in a host of areas, such as the ability to cost share transmission infrastructure build outs w...

AI summary PHP emphasizes the importance of collaboration and information sharing among stakeholders to achieve Nova Scotia's sustainable development goals in the least cost manner. They highlight opportunities such as cost-sharing transmission infrastructure and advancing renewable capacity. SBA did not provide a comment.

Section 2440
load scenario.” (Slide 47) The first element of the Draft Action Plan is to “Develop a Regional Integration Strategy to provide access to firm capacity and low carbon energy, increase the reliability of Nova Scotia’s interconnection with N...

AI summary CanREA supports the development of a Regional Integration Strategy to enhance access to firm capacity and low carbon energy, improve interconnection reliability, and enable coal unit retirements. They encourage NSPI to accelerate this effort and emphasize the importance of including solar energy and energy storage in planning scenarios.

Section 2447
FINDING STAKEHOLDER STAKEHOLDER COMMENT REFERENCE Given that the Regional Integration and Reliability Ties play a key role in many of the optimal resource plans developed for the key scenarios, these studies should be undertaken in the nea...

AI summary The document emphasizes the importance of Regional Integration and Reliability Ties in optimal resource plans, noting the need to address climate change impacts on grid reliability and energy security. The SBA supports the investigation of these ties as a common component of top-performing plans.

Section 2448
Strategy was a common component of top-performing plans and should be investigated for future consideration. The draft IRP used more concrete language about immediately pursuing this option, and implementing it more quickly than indicated...

AI summary The text discusses the importance of strategy in top-performing integrated resource plans (IRPs), suggesting it should be explored further. The draft IRP recommends pursuing this strategy more quickly, as it appears economically beneficial. However, further analysis is needed to determine technical feasibility and availability of firm capacity from other regions.

Section 2449
conducted by PSC on the inertia needs of the system provided an important initial assessment, but will need to Page 14 of 43 Nova Scotia Power IRP Final Report Appendix M Page 15 of 43 Nova Scotia Power IRP Summary of Stakeholder Comments...

AI summary The PSC conducted an assessment of the system's inertia needs, which provided an initial evaluation but requires further study before relying on firm imports for reliability. Stakeholder comments on the findings, action plan, and roadmap are summarized, with the Town of Wolfville providing no comment.

Section 2462
FINDING STAKEHOLDER STAKEHOLDER COMMENT REFERENCE SBA Supportive of Action Plan item for further analysis: 2020-09-18; p.2/3 -:While the draft analysis indicates that the assumed system inertia requirement is not binding for several years,...

AI summary The SBA supports further analysis of the system inertia requirement, noting that cost declines for wind capacity or other factors may accelerate wind development and the need for reliability solutions. The AREA comments on the economic sustainability of coal units until their model-imposed retirement dates, with potential for early retirement if constraints are satisfied.

Section 2524
ACTION PLAN ITEM STAKEHOLDER STAKEHOLDER COMMENT REFERENCE 1. Develop a Regional Integration Strategy to provide CA See comments above re Finding 2a access to firm capacity and low carbon energy while CanREA Supportive: See comments on Fin...

AI summary The document outlines an action plan to develop a Regional Integration Strategy aimed at enhancing Nova Scotia’s energy reliability and access to low carbon energy. It includes developing a Reliability Tie and Regional Interconnection by 2025-2035, as well as conducting studies on firm import options. Stakeholders have provided varied comments, ranging from supportive to concerned about risks.

Section 2549
ROADMAP ITEM STAKEHOLDE STAKEHOLDER COMMENT REFERENCE R 1. Advance engineering study work on coal-to-gas Heritage Gas Supports and suggests a timeline and stakeholder 2020-11-16; p. 4/5 conversions at Trenton and Point Tupper Generating en...

AI summary The document outlines key actions related to energy infrastructure, including advancing coal-to-gas conversions, conducting system stability studies for wind integration, and pursuing reinvestment in hydro and combustion facilities. Stakeholders provide input on timelines, cost assumptions, and grid service impacts.

Section 2566
Request / Directive Originator Status NS Power Comments Per IRP and GUO letter from NSUARB about pre-IRP NSUARB Complete Nova Scotia Power has continued to pursue these deliverables: opportunities as part of its operations. 6. Continue joi...

AI summary Nova Scotia Power has completed several tasks related to the Integrated Resource Plan (IRP) and a letter from the NSUARB. These include joint dispatch efforts with Maritime Provinces, evaluating capacity requirements for Tufts Cove units, and identifying candidates for coal retirement following Lingan 2.

Section 2571
Nova Scotia Power IRP Final Report Appendix N Page 5 of 12 NS Power’s Response to IRP Report Directives and Suggestions 2018 FAM Audit Recommendation IX-1 Bates White Complete The Pre-IRP work confirmed via LOLP modeling that a PRM of 17-2...

AI summary Nova Scotia Power responded to the 2018 FAM Audit Recommendation IX-1 by confirming that a planning reserve margin (PRM) of 17-21% nameplate over firm peak is required to meet NPCC reliability standards. They used the UCAP methodology in the 2020 IRP to model capacity expansion and ensure reliability.

Section 2573
The findings of the pre-IRP capacity study were used for the Initial Portfolio Study capacity expansion models. NS Power then selected three scenarios (2.0C, 2.1C and 3.2C) for reliability assessment and determination of the appropriate PR...

AI summary The pre-IRP capacity study findings were used in the Initial Portfolio Study for capacity expansion models. NS Power evaluated three scenarios (2.0C, 2.1C, 3.2C) for reliability assessment and PRM determination. All scenarios met the target reliability criterion and LOLE metric, with excess capacity near or less than the lowest cost capacity resource.

N-10Comments - Bates White 8 passages
Section 4
g combustion turbines differ substantially from new combustion turbines. ................................................................................................................. 15 3. Battery storage is not limited from providing...

AI summary The document discusses combustion turbine differences, battery storage capacity, and IRP results highlighting reliance on firm imports and regional transmission. It addresses electrification uncertainties, sensitivity to resource costs, and NSPI's Action Plan evaluation, emphasizing the need for competitive procurement and substantiating investment decisions.

Section 10
ensure that NSPI will be regularly determining the lowest planning reserve margin possible to meet NPCC requirements, rather than just assessing if “20%” remains in compliance.7 In the 2020 IRP Report, NSPI explains that it “will continue...

AI summary NSPI's 2020 IRP Report uses a 20% ICAP/9% UCAP planning reserve margin, citing E3 studies confirming reliability. However, NSPI hasn't declared this margin as optimal, with critics questioning the sufficiency of their analysis.

Section 11
throughout the IRP process. As others have noted, it is not clear that NSPI’s work to date is “sufficient to demonstrate that NS Power has achieved an ‘optimal’ planning reserve margin.”12 We tend to 7 Audit Report, Recommendation IX-1. 8...

AI summary The text critiques NSPI's Integrated Resource Plan (IRP) reserve margin, citing E3's studies showing lower margins could meet reliability targets. It highlights that 2045 scenarios under the IRP demonstrated excess capacity (32-77 MW), suggesting over-planning. References to audit reports and IRP sections support these claims.

Section 20
, section 6.8.5. 34 Bates White Rebuttal Evidence, M09288, August 29, 2019, page 26. 11 Bates White Comments On NSPI Final IRP Report 8. Determine Reasonable Effective Load Carrying Capability of Wind Our recommendation then addressed the...

AI summary Bates White's rebuttal evidence (M09288) highlights NSPI's compliance with recommendations to assess wind resource ELCC and conduct a planning reserve margin study. The text emphasizes stakeholder and Board involvement in the IRP process, citing E3's industry-standard methodology for ELCC estimation.

Section 31
a natural gas plants,” July 1, 2020. 16 Bates White Comments On NSPI Final IRP Report B. Other Comments on IRP Results 1. The results generally demonstrate a reliance on firm imports and a preference for regional coordination through trans...

AI summary Bates White comments on NSPI's Final IRP Report, highlighting reliance on firm imports and regional transmission expansion (Reliability Tie and Regional Integration options). The latter enables zero-emission energy imports but introduces risks tied to system reliability and coordination.

Section 32
ly added gradually as coal units are retired….Like the Reliability Tie, Regional Integration was selected economically in every resource plan where it was offered to the model…55 NSPI’s quote is borne out in the results as demonstrated by...

AI summary The text discusses NSPI's reliance on regional solutions for capacity additions and clean energy, noting benefits of interregional coordination but highlighting risks such as third-party cooperation challenges and potential cost delays. It emphasizes the need for a Regional Integration Strategy to address these risks promptly.

Section 38
projects. To help address these concerns, NSPI took the reasonable step of conducting modeling sensitivity runs testing, for example, low case costs of new onshore wind and battery storage systems.66 The results of these sensitivity runs a...

AI summary NSPI conducted sensitivity analyses on wind and battery storage costs, revealing that lower costs could accelerate wind installations and coal unit retirements, reducing greenhouse gas emissions by 20-27%. This underscores the importance of market-driven procurement for optimal resource planning.

Section 39
Bates White Comments On NSPI Final IRP Report underscore the importance of ensuring future procurement efforts solicit offers from the market to ensure the best and most timely pricing possible. The sensitivity results also show the import...

AI summary Bates White emphasizes the need for market-driven procurement to ensure cost-effective pricing and highlights the Reliability Tie's role in integrating renewables and maintaining system reliability. Sensitivity analyses show the Reliability Tie is prioritized in low-cost scenarios, while its absence leads to reliance on battery storage and synchronous condensers. This underscores the Reliability Tie's cost-efficiency in supporting high renewable penetration.

N-11Comments - Synapse 6 passages
Section 7
of a more stringent emission reduction trajectory, such as one that would align with the Ecology Action Center’s 1 million tons/year of carbon dioxide (CO2) emissions for the electric sector by 2030. NSPI incorporated use of E3’s RECAP too...

AI summary NSPI used E3’s RECAP tool to assess reliability of preliminary energy portfolios, finding scenarios may exceed necessary reliability standards. This suggests potential overbuilding of capacity resources, with surplus capacity already 20% above peak load needs, requiring reevaluation of resource requirements to avoid excess investment.

Section 11
” July 2029. 9 NSPI’s load forecast detail is provided in the March 11, 2020 Integrated Resource Plan Final Assumptions Set, a slide deck and associated excel files posted on the NSPI IRP website. Synapse Energy Economics, Inc. Analysis of...

AI summary NSPI's load forecasts show significant peak load increases by 2030 under electrification scenarios, with mitigation strategies like DSM and battery storage proposed. Electrification scenarios (Low, Mid, High) project 9-43% peak load growth by 2045, driven by transportation and heating electrification. Provincial policies and NSPI's time-of-use rates could moderate growth, while DSM programs aim to reduce peak capacity needs.

Section 28
“raw” NPVRR values for 2.1C vs. 3.1C leads to a change in NPV cost difference such that 3.1C is no longer 4.5 percent more costly (NPVRR basis) than 2.1C. Instead, it is only 1.7 percent more costly. This analytical exercise shows that the...

AI summary The analysis compares NPVRR differences between coal fleet retirement scenarios (2.1C vs. 3.1C), showing a reduced cost gap (1.7% vs. 4.5%). Earlier wind installations and Reliability Tie inclusion (by 2030, potentially earlier) are highlighted as beneficial for ratepayers and system reliability. The Reliability Tie's completion is urged to enable earlier wind development.

Section 45
Provinces and potentially the Federal government, and any other relevant issue. ii. Initiate Thermal Plant Retirement, Redevelopment and Replacement Plan • NSPI should prioritize element 3d, initiation of a wind procurement strategy. This...

AI summary The text discusses the need for NSPI to prioritize initiating a wind procurement strategy targeting up to 631 MW of wind deployment by 2025, aligned with low wind cost scenarios. It also mentions the importance of considering carbon reduction valuation and the Reliability Tie in ensuring reliable operation.

Section 46
integration allowed, which is premised in part on the status of the Reliability Tie and other assets that may be deployed to ensure reliable operation.23 The potential for capturing any economies of scale that may exist, if developers were...

AI summary The text discusses the importance of integrating a large amount of wind power into the grid, emphasizing the need to consider the status of the Reliability Tie and other assets. It highlights that targeting only small levels of new wind installations could miss economic opportunities and prevent the capture of economies of scale.

Section 53
pre-IRP PSC Renewable Integration Study but recognizes that additional detailed studies continue to be required to support new renewable resource installation. This Roadmap item should focus first on the practical effects of system operati...

AI summary The text discusses the need for additional studies on the integration of renewable resources into NSPI’s system, particularly wind power up to 631 MW by 2025. It emphasizes the importance of analyzing operational limitations, system stability, and the potential need for alternative resources like synchronous condensing, depending on the timeline for completing the Reliability Tie.

N-12Comments - PHP 1 passage
Section 6
age 3 179164 January 20, 2021 the opportunity to do so should not be foreclosed. As PHP noted above, the direction of more in- Province renewable generation is clear from the IRP but the appropriate pace is not yet fully defined. In this r...

AI summary PHP emphasizes the need for further system stability studies to determine the pace of renewable generation expansion in Nova Scotia, aligning with the IRP's roadmap. They advocate for balancing increased wind energy adoption with reliability and cost considerations, urging collaboration to advance the electricity transition without adverse impacts.

N-14Comments - CA 5 passages
II. Summary p. pp. 4-5
II. Summary One of the outcomes of the IRP process is an understanding by several participants, such as Bates White, Synapse, Efficiency One, and Resource Insight, that a number of improvements to NS Power's planning and procurement proces...

AI summary The summary outlines recommendations for NS Power's Integrated Resource Plan (IRP), including adding an RFP for 700 MW of wind by 2025, integrating transmission and reliability measures, requiring updated modeling for Mersey hydro, recognizing electrification benefits, supporting FAM audit studies, incorporating CO2 shadow prices, and establishing an 'evergreen IRP process.'

B. Integrate Transmission Development, Reliability Measures, and Procurement p. pp. 8-9
B. Integrate Transmission Development, Reliability Measures, and Procurement We find that NS Power's Action Plan lacks a clear process for integrating its work on the Regional Interconnection Strategy with the development of new generation...

AI summary NS Power's Action Plan lacks a clear process for integrating transmission development with generation resource planning. The IRP analysis does not establish optimal combinations of transmission upgrades and resource mix changes. Concerns include potential misalignment between transmission project timing, technology deployment, and reliability investments, as well as the single-resource procurement approach's compatibility with reliability measures.

1) Integrate Transmission Development with Reliability Practices and Resources p. pp. 9-10
1) Integrate Transmission Development with Reliability Practices and Resources First, NS Power's transmission development process should be integrated with its plans to deepen analysis of wind integration and other reliability practices an...

AI summary NS Power must integrate transmission planning with reliability practices, including wind integration analysis. The IRP lacked conclusive findings on wind integration strategies due to concerns over system inertia and insufficient evaluation of operating practices. Stability studies and cost estimates for the Reliability Tie's completion timeline are required.

2) Integrate Transmission and Reliability Development with Procurement p. p. 10
2) Integrate Transmission and Reliability Development with Procurement The second level of integration is to bring together the transmission and reliability development with the all-source procurement process. NS Power should be seeking to...

AI summary The text advocates integrating transmission and reliability development with all-source procurement to co-optimize generation, grid investments, and operations. It suggests using RFPs or engineering estimates for cost evaluation, with less refined estimates acceptable for initial decision-making. Coordination of timing between procurement and transmission studies is emphasized.

B. Proposed Operational Dispatch Study p. pp. 14-15
B. Proposed Operational Dispatch Study A number of technical concerns that we had in the IRP process related to the alignment of the model with NS Power's current operating practices. These issues have also been raised in the FAM Audit pro...

AI summary NS Power proposes a study on operational dispatch practices to address technical concerns from the IRP and FAM Audit processes, aiming to align planning models with system constraints and improve dispatch optimization for variable energy resources.

N-15Comments - SBA 10 passages
A. NSPI Favoured resources p. p. 0
A. NSPI Favoured resources In the IRP NSPI has set out a prioritization of resource development activities. The SBA notes that the focus and action items appear to be on the continued utilization of existing generation assets; the retireme...

AI summary NSPI's IRP prioritizes existing generation assets, coal fleet retirement, and regional integration through transmission and imports. The SBA highlights these focus areas, while the IRP emphasizes incremental renewables and challenges in system inertia and interconnection reliability, citing lessons from past projects like Maritime Link and Muskrat Falls.

B. Reliance on Natural Gas p. p. 0
B. Reliance on Natural Gas Stepping back and looking at the big picture, the SBA notes that it is surprising how much the IRP includes investment in natural gas burning assets. The SBA acknowledges that any movement from coal fueled genera...

AI summary The SBA expresses concerns about NSPI's reliance on natural gas in the IRP, warning that investments in natural gas assets may become stranded if non-emitting alternatives emerge. It questions the economic assumptions behind coal-to-gas conversions, existing peaking generation refurbishments, and new natural gas capacity, urging NSPI to prioritize low-carbon options and delay investments until non-emitting technologies mature.

C. Renewable Resource Development p. p. 0
C. Renewable Resource Development In the IRP NSPI assumes onshore wind is the primary renewable resource as part of the future portfolio. Other areas on the Atlantic coast of North America are focusing on offshore wind to provide resource...

AI summary NSPI's IRP prioritizes onshore wind, but questions arise about offshore wind's benefits and cost sensitivity. The SBA highlights system integrity issues in the renewable integration study, urging expansion and near-term investments. Sensitivity modeling and offshore wind cost tracking are recommended.

A. Limitation on Conclusions that can be Drawn from the IRP Analysis p. p. 0
A. Limitation on Conclusions that can be Drawn from the IRP Analysis The SBA has been supportive throughout the IRP process for a focus on recognizing that a resource plan must reflect the province's policies regarding decarbonization. Con...

AI summary The SBA cautions that the IRP analysis may underestimate costs and system investments needed for electrification, lacks rate design considerations, and assumes zero transmission/distribution costs. While acknowledging electrification's decarbonization benefits, the SBA stresses uncertainties in timing, cost allocation, and unaddressed infrastructure needs.

A. Comments on Analysis p. p. 0
A. Comments on Analysis The Findings, Roadmap, and Action Plan in the IRP report conclude that the Reliability Tie and Regional Integration strategy is a common component of top-performing plans and should be immediately pursued. The IRP s...

AI summary The IRP report recommends pursuing the Reliability Tie and Regional Integration strategy, supported by the SBA for further investigation. However, technical feasibility and capacity availability remain unvetted, with challenges in securing firm capacity from eastern Canada and the US. NSPI's inertia modeling and unexplored wind project potential for frequency response require additional analysis before investment.

B. Coordination with New Brunswick p. p. 0
B. Coordination with New Brunswick The prospect of Regional Integration is enticing, as it suggests the ability to efficiently manage our electricity needs, with a strong backup from New Brunswick and beyond. However, the term 'integration...

AI summary The text discusses challenges in regional electricity integration with New Brunswick, highlighting potential risks to Nova Scotia's Integrated Resource Plan (IRP) if New Brunswick declines participation. It emphasizes the need for stakeholder engagement and caution in relying on cross-provincial collaboration to ensure ratepayer interests are protected despite conflicting demands.

C. Concern about Risks p. p. 0
C. Concern about Risks The Reliability Tie and Regional interconnection are significant components of the initial modeling results and would represent substantial investments. Given the scope of the investment it is important to understand...

AI summary The text raises concerns about risks associated with the Reliability Tie and Regional interconnection investments, emphasizing the need to evaluate costs, commitments from energy suppliers, and study requirements. It urges NSPI to compare transmission upgrades with non-transmission alternatives and suggests parallel IRP strategies until clarity on the optimal path emerges.

A. NSPI/E3 Modeling p. p. 0
A. NSPI/E3 Modeling The SBA believes the Planning Reserve Margin ("PRM") study should include expanded analysis on interties. The initial PRM study included conservative assumptions related to tie benefits from interconnections with New Br...

AI summary The SBA argues that the PRM study should include expanded intertie analysis, criticizing conservative assumptions about New Brunswick interconnections and the Maritime Link. It highlights potential over-planning due to undervaluing interconnection reliability and calls for dynamic inertia requirement modeling to reflect changing load, DSM, and supply mix.

VIII. Specific Comments on Selected Key Findings p. p. 0
substitute for firm capacity resources is limited by its relatively short duration. Up to 120 MW of storage by 2045 is selected in the portfolios with deployments of 30-60 MW by 2025 in many plans. Battery storage was an integration method...

AI summary Battery storage's role in Nova Scotia's IRP is underrepresented, according to the SBA, which highlights its potential for reliability and renewable integration. Pre-IRP studies modeled storage with synchronous condensers, but IRP scenarios show limited deployment. The SBA argues for broader consideration of storage in future planning.

IX. Specific Comments on Action Plan p. p. 0
IX. Specific Comments on Action Plan The IRP Action Plan describes the key tasks to be undertaken in the next five years to implement the long-term electricity strategy. The IRP maintains that these action plan items are built on the items...

AI summary The IRP Action Plan outlines a five-year strategy to enhance Nova Scotia's electricity system through regional integration, including developing a Reliability Tie (2025-2029) and Regional Interconnection (2027-2035), alongside studies for firm imports and wind procurement. The plan is grounded in Key Findings and modeling results.

N-16Comments - HGL 4 passages
RE: M08929 – NSPI Integrated Resource Planning – IRP Report Comments p. p. 0
RE: M08929 – NSPI Integrated Resource Planning – IRP Report Comments Heritage Gas has reviewed the 2020 Integrated Resource Plan ("IRP"), distributed to stakeholders on November 27, 2020, and notes that the IRP foresees a significant incre...

AI summary Heritage Gas reviews the 2020 IRP, noting its projected increased reliance on natural gas for reliability during low renewable periods and peak loads. It emphasizes natural gas's role in providing ancillary services to support renewable integration, raising specific concerns about the IRP's assumptions.

Benefits of an Integrated Energy System p. pp. 0-2
Benefits of an Integrated Energy System Nova Scotia Power Inc.'s ("NSPI") 2020 IRP differs from prior IRP's in that it envisions electrification of segments of the economy that previously used others forms of energy to meet their needs. Th...

AI summary NSPI's 2020 IRP focuses on electrification but excludes non-electric energy alternatives. Heritage Gas highlights increased natural gas reliance in the IRP. An integrated energy system, combining natural gas and renewables, reduces costs and emissions while enhancing reliability. ICF International's study supports this approach, showing lower GHG reduction costs ($129/tCO2) compared to electricity-only strategies ($289/tCO2).

Regional Intertie/Integration p. pp. 6-8
Regional Intertie/Integration The IRP Report identified the need for further study on the Intertie to provide firm capacity and ancillary services: "Nova Scotia Power notes that any resource plans which go beyond the findings of the pre-IR...

AI summary The IRP Report highlights the need for further study on the Intertie for firm capacity and ancillary services. NSPI notes that resources beyond pre-IRP studies require analysis for reliability. Heritage Gas criticizes NSPI for lacking details on imported energy sourcing and carbon intensity. Quebec's growing demand may reduce surplus electricity, while climate change risks and grid reliability concerns are raised.

Combustion Turbine Fleet p. pp. 10-12
Combustion Turbine Fleet Throughout the IRP process, Heritage Gas has raised concerns regarding the continued reliance on the aging infrastructure of the 1970's-era Light Fuel Oil fired Combustion Turbine ("CT") fleet. NSPI has indicated t...

AI summary Heritage Gas raises concerns about NSPI's reliance on aging 1970s-era combustion turbines, while NSPI argues sustaining investments are cheaper than replacement. Bates White's FAM audit highlights reliability issues, uncertain performance improvements from repairs, and potential higher O&M costs if CTs are used more than modeled. Economic retirement of the fleet before 2045 is recommended.

N-18Response to Comments - NSPI 1 passage
IRP Final Report Comments – Bates White p. pp. 13-35
1 Planning Reserve Margin Findings (3f) Roadmap (8) A Planning Reserve Margin as low as 17.8% would allow NSPI to meet its reliability criteria; that [E3] study noted, in relevant part

AI summary The document discusses the Planning Reserve Margin (PRM) findings, noting that a PRM as low as 17.8% would allow NSPI to meet its reliability criteria, citing a relevant study.

75513Board letter re IRP process and M08059 - Generation Utilization and Optimization 1 passage
Integrated Resource Planning (IRP) and M08059 Generation Utilization and Optimization p. p. 0
to further increase wind penetration through transmission grid reinforcement. This should also recognize that the introduction of bulk scale battery storage as a possible capacity resource that can provide co-benefits associated with stabi...

AI summary The document outlines recommendations for enhancing wind energy integration through grid reinforcement and battery storage, inter-provincial coordination for reliability, coal retirement planning, and gas price monitoring. It emphasizes economic retirement analysis for thermal units and prioritizing coal alternatives post-Lingan 2.

80156Board letter re approves Terms of Reference 1 passage
The proposed TOR states: p. p. 0
The proposed TOR states: The IRP process will seek to identify the least-cost, least-risk portfolio. Traditionally, the primary decision criterion used for IRP modeling has been the minimization of the cumulative present value of the annua...

AI summary The proposed TOR outlines NS Power's approach to the Integrated Resource Plan (IRP), emphasizing least-cost, least-risk portfolios using cumulative revenue requirements as the primary metric. Additional metrics include reliability, grid services, and emissions reduction. Natural Forces supports broader criteria for dynamic planning, while NS Power reaffirms its commitment to the primary metric.

81474Letter from Bruce Cameron re reponse to initial run on scenarios 1 passage
Section 3 p. pp. 0-1
munity Solar PV Gardens. It would be useful to discuss whether this concept is the same as DERs from the model's perspective and, if not, how it may be considered as well. - 2. The model did not select several potential technologies such a...

AI summary Bruce Cameron raises questions about the IRP model's treatment of community solar PV gardens, unselected technologies like offshore wind, tidal, and hydrogen, reliance on natural gas (CCGT), and the economic impact on NS GDP. He seeks clarification on model assumptions, reliability risks, and sourcing of goods/services.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →