Topic:"System Reliability" in M12516

Matter: NSP Maritime Link Inc. (NSPML) - 2025 Q3 Quarterly Report
4 passages 1 document

System Reliability across all matters →

N-1Q3 Report 2025 4 passages
3 2.1 Safety and Environment p. p. 10
3 2.1 Safety and Environment 4 5 Safety is a fundamental core value and integral part of every aspect of NSPML's 6 business. NSPML continues to be risk-focused on the assessment of all work activities. 7 There have been no internal recorda...

AI summary NSPML emphasizes safety as a core value, with no internal or environmental incidents recorded in 2025. Safety remains a priority, especially with upcoming rock protection work for the submarine cable, which has undergone thorough high-risk reviews involving management, external experts, and contractors.

1 & Labrador. NS Power continues to work with NLH to finalize the associated protocols. p. p. 10
1 Recommendation number 1 is closed. 1 & Labrador. NS Power continues to work with NLH to finalize the associated protocols. 2 and other updates as applicable to the Board and stakeholders through its Quarterly 3 Report. 4 5 2.5 Converters...

AI summary The document discusses the performance of NS Power's infrastructure, including converters, substations, and transmission lines, highlighting their reliability and maintenance efforts. It also mentions ongoing collaboration with NLH to finalize protocols related to the Maritime Link.

5. IE COMMENTS p. pp. 20-22
5. IE COMMENTS All sites are fully operational and in good order. Planned maintenance activities have been completed, with no reported safety or environmental issues. The 2025 Maintenance Plan is active, and maintenance outages have been s...

AI summary The document highlights the operational status of sites, completion of maintenance activities, and ongoing initiatives related to system performance and infrastructure management. It also mentions the need for vegetation clearance for drone inspections and the issue of corroded ground wires requiring further investigation.

Availability and Reliability: p. pp. 26-27
Availability and Reliability: - There was one forced bi-pole outage in 2024 resulting in 2 hours of forced unavailability (FEU). - Energy availability during the period was 97.10%, monopole availability was 99.99%. Record energy transfer o...

AI summary In 2024, there was one forced bi-pole outage resulting in 2 hours of forced unavailability. Energy availability was 97.10%, and monopole availability reached 99.99%. A record energy transfer of 291.3 GWh occurred in December.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →