Home›System Reliability›M12961›Evidence
Topic/Matter Intersection

Topic:"System Reliability" in M12961

Matter: Nova Scotia Power Inc. - CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058 (ATO)
2 passages 2 documents

System Reliability across all matters →

N-4NSPI (NSEB) RIR 19 to 24 1 passage
CI C0061550 NSEB IR-20 Attachment 1 Page 1 of 1
CI C0061550 NSEB IR-20 Attachment 1 Page 1 of 1 Mobile Year Installation Date Removal Date Location Reason for Mobile Transformer Number Transformer Rating Voltage Level Number of Customers Affected 5P 2025 January February L-5031 Transmis...

AI summary NS Power uses a prioritization strategy based on system reliability risk, geographic coverage, and technical compatibility when deploying mobile transformers, particularly during shortages. The approach emphasizes maintaining system resilience and flexibility for emergency responses.

103567Letter re: RIRs and Request for Confidentiality 1 passage
Section 1
September 14, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: M12961 - C0061550 L5031 Replacements and Upgrades - Hubbards to East Chester - Board IRs 2nd Set Dear...

AI summary NS Power has submitted responses to information requests regarding distribution routines for the Hubbards to East project. NS Power is requesting confidential treatment for Attachment 1 of IR-11 due to system security concerns, citing the need to protect the power system and reduce risks from external threats.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →