Matter: P-884 - Nova Scotia Power Inc. (NSPI) - Integrated Resource Planning (IRP) Action Plan Update
2 passages 2 documents

Tariff Design across all matters →

N-1IRP Action Plan Update 1 passage
Demand Response Strategy p. p. 66
Demand Response Strategy IRP Action Plan Item 4 is: Create a Demand Response Strategy targeting 75 MW of capacity, for deployment by 2025. Available resource cost, flexibility, and reliability may inform pursuit of additional Demand Respon...

AI summary The Integrated Resource Plan (IRP) Action Plan Item 4 aims to create a Demand Response Strategy targeting 75 MW of capacity by 2025. The strategy will be linked to the Electrification Strategy and will leverage prior initiatives such as NS Power's Smart Grid Project and the ELIADC tariff.

N-4Evergreen IRP Action Plan & Roadmap Update 1 passage
ITEM 11: HYDROGEN TARIFF IMPACTS p. p. 19
ITEM 11: HYDROGEN TARIFF IMPACTS Monitor the development of the hydrogen industry in Nova Scotia, including tariff structures specific to hydrogen development. Assess the impacts as they relate to future modeling assumptions.

AI summary The document discusses the need to monitor the development of the hydrogen industry in Nova Scotia, including specific tariff structures for hydrogen development and assess their impacts on future modeling assumptions.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →