N-1Integrated Resource Plan Action Plan Update 2025 1 passage
Hydrogen Roadmap Items 3 & 11 p. pp. 31-32
Hydrogen Roadmap Items 3 & 11 NS Power is engaged with the prospective H2 developers is to assess both the impacts of future development on the power system and assess future opportunities for the use of H2 as a green fuel source. - Hydrog...

AI summary NS Power collaborates with H2 developers to evaluate hydrogen's impact on the power system and its potential as a green fuel. A hydrogen tariff is under development for NSEB approval, while the Evergreen IRP assessed hydrogen's role, excluding it as a resource. Future hydrogen fuel pricing will be revisited via the Evergreen IRP process.

N-4NSPI (IG) RIR 1 to 10 1 passage
IR SIS Status COD p. p. 5
[nspi-combined-interconnection-request-queue(pdf).pdf](https://www.nspower.ca/docs/default-source/pdf-to-upload/nspi-combined-interconnection-request-queue(pdf).pdf?sfvrsn=d56d149_88) IR SIS Status COD 29 services. Due to the anticipated l...

AI summary The document discusses the development of a cost-based tariff and contribution to system fixed costs for a proposed hydrogen/ammonia customer. Efforts are being made in collaboration with EverWind Fuels and Bear Head Energy. The application process requires a complete and well-supported justification, including financial and operating assumptions, and will be subject to the Board's regulatory processes.

N-7NSPI (SBA) RIR 1 to 18 1 passage
NON-CONFIDENTIAL p. p. 12
NON-CONFIDENTIAL 1 Request IR-4: 19 modeled in the Evergreen IRP, but the procurement is aligned with the outcomes. 1 Request IR-16: 2 3 Refer to Exhibit N-1, 2025 Evergreen IRP, page. 33 of 42, regarding the development of the 4 hydrogen...

AI summary The document discusses Request IR-16, which asks about the status of the hydrogen tariff and NS Power's collaboration with hydrogen project developers. NS Power is currently developing a hydrogen/ammonia production facility tariff and is working with industry developers to understand their electricity needs and the implications for the power system.

98213SBA (NSPI) IR 1 to 18 1 passage
Request IR-16:
Request IR-16: Refer to Exhibit N-1, 2025 Evergreen IRP, page. 33 of 42, regarding the development of the hydrogen tariff. - a) What is the current status of the hydrogen tariff? - b) Has NS Power collaborated with hydrogen project develop...

AI summary Request IR-16 seeks information on the status of a hydrogen tariff, collaboration with developers, draft materials, and progress summaries. It references the 2025 Evergreen IRP, page 33 of 42, and focuses on NS Power's role in hydrogen tariff development.

98223IG (NSPI) IR 1 to 10 1 passage
1 2025 M12247
19 1 2025 M12247 11 12 (a) Please discuss the general structure of the hydrogen tariff under development. 13 (b) With whom is NSPI working to develop this tariff and cost structure? 14 15 16 (c) What are the pre-requisites before applying...

AI summary The document contains a series of questions directed at NSPI regarding the development of a hydrogen tariff, including its structure, collaboration partners, pre-requisites for approval, the need for overseas industrial buyers, expected filing dates, and the submission of relevant agreements with EverWind.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →