Matter: Procurement Administrator - Power Advisory - Application for Approval of the Green Choice Power Purchase Agreement
11 passages 7 documents

Tariff Design across all matters →

P-1Application 1 passage
2. OVERVIEW OF THE PPA p. p. 7
t out of this arrangement by indicating in its proposal that it was foregoing Network Upgrade Reimbursement and proceed with Network Upgrades and agree to reimburse NSPI for the Network Upgrade costs. The RFP now provides for deliverabilit...

AI summary The RFP process includes deliverability testing to identify projects requiring network upgrades, allowing system-wide planning and cost savings for proponents. Reciprocal tariff protection is discussed, particularly in the context of new federal steel tariffs impacting Nova Scotia's reliance on foreign wind tower suppliers.

P-1-(i)Appendix A - Green Choice PPA 2 passages
5.4 Metering p. pp. 41-42
5.4 Metering All Facility revenue class metering equipment shall be routinely tested by NSPI. At any time, either Party may request a test of the accuracy of the metering equipment at its own expense. The results of meter calibrations or t...

AI summary The text outlines procedures for testing and maintaining revenue class metering equipment, ensuring accuracy and compliance with standards. NSPI is responsible for testing, and financial adjustments may be required if meter accuracy exceeds 2% variance. Both parties have rights to be represented during meter sealing/unsealing and to request tests.

16.9 Adjustment for Post-Proposal Applicable Tariffs p. p. 76
is Agreement shall automatically be amended by replacing the amount of the Energy Rate set out in Commercial Terms with the Proposed Revised Energy Rate set out in the Seller Tariff Adjustment Notice. - g) If NSPI, acting reasonably, rejec...

AI summary The text outlines the process for amending an agreement based on a Proposed Revised Energy Rate and describes the dispute resolution mechanism involving an Independent Expert if NSPI rejects the proposed rate and a disagreement arises.

P-1-(ii)Appendix B - Green Choice PPA Blackline to PPA in M11455 1 passage
16.9 Adjustment for Post-Proposal Applicable Tariffs p. p. 86
is Agreement shall automatically be amended by replacing the amount of the Energy Rate set out in Commercial Terms with the Proposed Revised Energy Rate set out in the Seller Tariff Adjustment Notice. - g) If NSPI, acting reasonably, rejec...

AI summary The text outlines the process for amending an agreement based on a proposed revised energy rate and specifies the steps to be taken if there is a dispute over the rate, including the involvement of an Independent Expert appointed by the ADR Institute of Canada.

103545Comments - SWEB 1 passage
New Section 16.9 – Adjustment for Post-Proposal Applicable Tariffs
New Section 16.9 – Adjustment for Post-Proposal Applicable Tariffs The Minimum Threshold outlined in Section 16.9 b) - Adjustment for Post-Proposal Applicable Tariffs is set at 7.5%. Please be advised that we consider this threshold unreas...

AI summary The document argues that the 7.5% Minimum Threshold in Section 16.9 is unreasonably high, as it fails to adequately protect sellers from potential tariff impacts. It references a study showing that even a 25% steel surtax had an impact below 7.5%, and warns that developers will price in higher risks, leading to increased costs for ratepayers. The document suggests lowering the threshold to 2.5% and cautions against using Ontario’s procurement as a basis for Nova Scotia's threshold.

103713Reply Comments - Exhibit A - Procurement Administrator - Power Advisory 2 passages
Summary Stakeholder Comments Procurement Administrator Response p. p. 1
1 The previous Green Choice PPA had a Pre-COD Amount of $125,000/MW and post-COD Amount of $20,000/MW (Board order for M11455, dated June 6, 2024) Summary Stakeholder Comments Procurement Administrator Response 4. Cybersecurity It is prude...

AI summary The document discusses cybersecurity requirements and tariff adjustments in a regulatory proceeding. It references a previous Green Choice PPA with specific financial terms and mentions the need for an IESO-approved cybersecurity plan. Stakeholders have raised concerns about the feasibility of certain requirements, such as the Local Benefits Report, and the Procurement Administrator has responded regarding confidentiality and flexibility in proposal submissions.

p. pp. 5-8
11 https://www.novascotia.ca/sites/default/files/documents/1-3582/nova-scotia-clean-power-plan-presentation-en.pdf ratepayers to development -stage project abandonment. Ontario LT2(e -1) - $35,000/MW subject to a minimum of $500,000 and ma...

AI summary The text discusses performance security requirements for power projects in various jurisdictions, including Ontario, BC Hydro, and Quebec. It also outlines the removal of certain provisions in the PPA related to congestion management and network upgrade reimbursement, emphasizing the need for infrastructure investments that deliver clear system-wide value and represent the most economical long-term solution.

103714Reply Comments - Exhibit B Blackline Amended PPA - Procurement Administrator - Power Advisory 3 passages
1.8 Energy Reform (2024) Act p. pp. 24-25
1.8 Energy Reform (2024) Act - (a) Reference is made to the Energy Reform (2024) Act which came into effect on April 1, 2025 and pursuant to which certain Laws and Regulations were amended and pursuant to which the More Access to Energy Ac...

AI summary This section discusses the Energy Reform (2024) Act, which came into effect on April 1, 2025, and outlines changes to laws and regulations, including the transition of system operator functions from NSPI to the IESO, and the procurement of Ancillary Services by the IESO. It also addresses the governance of conflicts between the Act and the Agreement, and outlines arbitration procedures if parties cannot agree on amendments.

5.4 Metering p. p. 41
5.4 Metering All Facility revenue class metering equipment shall be routinely tested by NSPI. At any time, either Party may request a test of the accuracy of the metering equipment at its own expense. The results of meter calibrations or t...

AI summary This section outlines the procedures for testing and maintaining revenue class metering equipment, including requirements for calibration, financial adjustments for inaccuracies, and notification protocols between the Parties. NSPI is responsible for ensuring accuracy, and both Parties have rights to be involved in meter sealing and testing.

16.9 Adjustment for Post-Proposal Applicable Tariffs p. p. 76
the Independent Expert in accordance with this Section 16.9(g)(i) shall be final and binding on the Parties. - (ii) The Independent Expert shall be retained solely to determine a revised Energy Rate. - (iii) The following process shall gov...

AI summary This section outlines the process for determining a revised Energy Rate through an Independent Expert, including submission timelines, response periods, and cost allocation based on the Expert's determination. The resulting adjustment is referred to as a 'Tariff Adjustment'.

103715Reply Comments - Exhibit C Clean Amended PPA - Procurement Administrator - Power Advisory 1 passage
5.4 Metering p. pp. 40-41
5.4 Metering All Facility revenue class metering equipment shall be routinely tested by NSPI. At any time, either Party may request a test of the accuracy of the metering equipment at its own expense. The results of meter calibrations or t...

AI summary The section outlines procedures for testing and maintaining revenue class metering equipment by NSPI. It specifies that either party may request tests, and outlines the process for handling inaccuracies, including financial adjustments if meter accuracy exceeds a 2% variance.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →