. 3. Explain how AAR and DLR compliment each other, identify any potential conflicts, and clarify whether NS Power plans to operate them in parallel. 4. Provide the rationale to maintain both systems. In Matter M09508, NS Power’s response...
AI summary The text requests explanations on how AAR and DLR complement each other and potential conflicts, asks for updated data on transmission line interruptions, and seeks clarification on the role of DLR in reducing outages. It also inquires about the correlation between GET tools, DLR, and NS Power’s progress toward the 2030 renewable electricity target.