Forecast Planning Reserve Margin With DSM Case No DSM Case 25 required to provide power system regulation and load following. 26 27 ii. The back-up adder was part of the 2009 IRP Update Basic Assumptions that were 28 developed jointly by N...
AI summary The text discusses the Forecast Planning Reserve Margin, including the evaluation of the back-up adder for wind energy in the Integrated Resource Plan (IRP), the involvement of NSPI in a Renewables Integration study, and the modeling of transmission costs for various projects. It also references confidential attachments for detailed financial data.