N-1Application - Redacted
46 passages
1 2 In preparing its capital plans, NS Power utilizes its established asset management approach, and 3 considers safety, reliability, climate change adaptation, and affordability, while incorporating the 4 Company’s decarbonization targets...
AI summary NS Power uses an asset management approach to prepare capital plans, focusing on reliability, resiliency, and affordability. The 2026 ACE Plan includes investments in reliability-focused improvements to the T&D system, addressing challenges from severe weather events through vegetation management, storm hardening, and grid modernization.
1 electricity from the generation plants to the distribution system throughout the province. 2 Transmission includes assets and equipment operating at 69 kV level or higher, and also 3 includes substation assets. 4 5 • Section 8.0 – Distri...
AI summary This section outlines the different categories of capital projects and expenditures, including transmission, distribution, general plant, and routine capital programs, with a focus on the Company’s ACE Plan and directives issued by the Board.
1,102,575 1,353,592 This project is for refurbishment of priority areas of the roof at the Sydney Coal Railway Transportation & Rail Maintenance Centre (Rail Centre). Total New Steam Spending for Subsequent Approval 10,402,603 24,560,654 T...
AI summary The text outlines various capital expenditure projects in Nova Scotia, including roof refurbishment, synchronous condensers, transmission tower rerouting, and network upgrades for wind farms. These projects aim to enhance infrastructure and support renewable energy integration.
CI# Project Title 2026 Budget ($) Project Total ($) C0071888 New Tidewater Substation 4,119,741 4,141,223 This project is to build a new Tidewater Substation to address increased residential electricity demand, improve system reliability,...
AI summary The document outlines several capital projects aimed at improving electricity infrastructure in Nova Scotia, including new substations, transformer replacements, and transmission line upgrades to enhance system reliability and meet growing demand.
or the replacement of the 10H-T2 transformer which serves the Victoria General Hospital and the IWK Children’s Hospital in Halifax. C0080108 L-5532 Replacements and Upgrades Phase 1 908,755 2,490,532 This project is for the replacement of...
AI summary The document outlines several transmission line replacement and upgrade projects, including the replacement of the 10H-T2 transformer serving key hospitals, upgrades to L-5532 and L-6043 transmission lines, and network upgrades for the Benjamin’s Mill Wind Farm. These projects are part of ongoing infrastructure planning and investment in Nova Scotia's power grid.
416,111 21,441,542 Gas Turbine Generation Plant G08 C0080135 CT - BGT2 Engine Refurbishment 2,147,663 2,462,664 Total Gas Turbine Generation Plant 2,147,663 2,462,664 Total Generation New Spending 16,563,774 23,904,206 5 Date: December 12,...
AI summary The document outlines NS Power's 2026 Annual Capital Expenditure (ACE) Plan, focusing on transmission investments from 2024 to 2028. The increased investment is attributed to Energy Storage and Synchronous Condenser projects. A figure illustrates historical, forecast, and budgeted transmission investments, highlighting a rising trend in spending.
1 2 The Board’s 2016 ACE Plan Order provided the following directive: 3 4 The Board directs that the Routine for Transmission widening be treated as a 5 separate project, and not a routine, in future ACE Plan Applications. NSPI is to 6 pro...
AI summary The Board's 2016 ACE Plan Order required NSPI to treat transmission widening as a separate project and provide annual progress reports. The last phase of the 69kV widening program was completed in 2024, and the transmission vegetation management program now includes only two initiatives. The T010 routine for 138kV, 230kV, and 345kV ROWs has increased in budget, reflecting ongoing efforts to improve system resilience.
l as a discussion paper on Transmission System Resiliency ahead of a Utility Resiliency 27 Workshop taking place at the 2025 CEATI T&D conference in November 2025 (attended by NS 28 Power). The discussion paper provides the initial finding...
AI summary The text references a discussion paper on Transmission System Resiliency, prepared ahead of a 2025 CEATI T&D conference workshop attended by NS Power. It outlines initial findings, proposed deliverables, and key actions for 2026, including the development of unified definitions for resiliency terms. A related document, 'M12012, NS Power 2025 Annual Capital Expenditure Plan, Board Order, August 19, 2025' is also cited.
782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0080135 Attachment 1 Page 19 of 21 BGT2 BSI March 25, 2025 Date: December 12, 2025 Page 350 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C...
AI summary This document outlines a transmission line replacement project for L-7012, a 230 kV line built in 1982, requiring upgrades due to deteriorated assets identified through NS Power’s inspection program. The project involves replacing assets on 72 structures and is part of the 2026 ACE Plan.
mobile transformer connection capable of accommodating larger mobile units, addressing long-standing substation access challenges and eliminating the need for foreseeable future upgrades at the site. Summary of Related CIs +/- 2 years Purs...
AI summary The project involves adding a new 69kV-12kV transformer in Bridgewater to address aging infrastructure, increase capacity, and support long-term distribution planning. The existing 69-4.2kV transformer is over 68 years old and has exceeded its service life. The new transformer will operate in parallel with an existing one, providing redundancy and enabling the conversion of 4kV feeders to 12kV.
D) REDACTED 2026 ACE Plan C0070909 Attachment 1 Page 15 of 16 Bridgewater Area Planning Study Addendum Appendix B Economic Analysis Data W-AREA-2025-017 Nov 10, 2025 14 Date: December 12, 2025 Page 382 of 782 REDACTED REDACTED (CONFIDENTIA...
AI summary This document outlines the L7001 Replacements and Upgrades Phase 1 project, which involves replacing deteriorated transmission assets on 59 structures of a 230 kV transmission line built in 1979. The project is part of NS Power’s transmission line inspection program and is forecasted to cost $3,063,280.
required to complete the project within the available outage window, unforeseen material or contract cost increases, or unforeseen costs related to accessing structures in wet or remote locations. Date: December 12, 2025 Page 387 of 782 RE...
AI summary This document outlines the 76W-T1 Transformer Replacement project at Mahone Bay Substation, which involves replacing an aging transformer with a higher capacity unit, upgrading infrastructure, and improving safety standards. The project is part of the 2026 ACE Plan and has a forecasted cost of $2,818,855.
1,572,478 $ 1,572,478 $ - Deferred Generation 48913 HYD - Tusket Facility Refurbishment 2025 ACE Plan (for Subsequent Approval) $ 12,972,226 $ 1,078,895 Deferred Transmission C0011358 New Bridgewater Substation 2025 ACE Plan (for Subsequen...
AI summary The text presents a list of projects under the 2025 ACE Plan, including deferred and approved items related to generation and transmission, with associated costs and approval statuses. Key projects include the Tusket Facility Refurbishment, New Bridgewater Substation, and the Eastern Clean Energy Initiative (ECEI) - Transmission.
wherein single con ngencies can poten ally adversely affect the interconnected NPCC system, are designed and operated in accordance with NPCC Directory 1, Design and Opera on of the Bulk Power System. NS Power is required to follow the stan...
AI summary NS Power adheres to NERC and NPCC standards for its Bulk Electric System, ensuring compliance through regulatory approval processes. System design criteria, including transmission and clearance times, are updated to meet evolving standards and are documented in report NS Power-TPR-003-6.
he preserva ve reten on levels in the ground line area thereby maintaining acceptable toximetric thresholds necessary for protec on against fungal and insect a ack. Criteria for Wood Pole Retreatment Wood pole species found on the transmis...
AI summary NS Power outlines criteria for retreating wood poles on transmission and distribution systems, including testing based on DEP 7.51 and CSA standards, exceptions for environmental or landowner reasons, and data maintenance on a computerized database.
C. Milligan 10-Apr-24 Updated to include Transient Voltage 2024/02/20 6 Criteria per NERC TPL-001 Month DD, 2025 Page 103 of 113 Date: December 12, 2025 Page 622 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan App...
AI summary Nova Scotia Power Inc. outlines criteria for capital expenditures on its transmission system, divided into four classifications. Criteria may be superseded by Northeast Power Coordinating Council (NPCC) standards. System studies must use existing protection system characteristics to ensure adequacy and investment requirements.
protec on opera on. The term “Breaker failure protecƟon” is used interchangeably in this document. 4. Single conƟngency is defined as loss of one system element with or without a fault. Month DD, 2025 Page 105 of 113 Date: December 12, 202...
AI summary Nova Scotia Power Inc. outlines criteria for capital expenditure justification, emphasizing redundancy in primary transmission system protection, adherence to industry standards, and fault clearing times. Deviations require approval from the system planning group, with reliance on transient stability studies for exceptions.
e the fault described in item (d), the fault contribu on clearing me will be 16 cycles. Breaker failure protecƟon will be applied to all Primary Transmission. The design criteria are: 1. From normal system condiƟons, the Interconnected Tra...
AI summary The document outlines breaker failure protection for Primary Transmission and specifies design criteria ensuring system stability post-faults. It references Nova Scotia Power Inc.'s 2026 ACE Plan Appendix D and a detailed capital expenditure justification document.
where calcula ons are not specifically conducted: a. Under system normal, loading is limited to 100% of the 65°C manufacturer nameplate MVA for summer and 110% for winter; b. Under con ngency, the 15 minute short me ra ng is limited to 110...
AI summary Nova Scotia Power Inc. outlines its radial transmission policy, detailing loading limits for transmission lines under normal and contingency conditions. The policy emphasizes the importance of auxiliary equipment ratings and specifies scenarios for overload management to ensure grid reliability.
adial transmission line results in loss of supply with no other way to connect the radial load to the grid. A single transmission line may have more than one radial load connected to it. A lone substa on, which is dedicated to a single cus...
AI summary The document outlines procedures for managing radial loads exceeding 40 MW, including planning studies, load reduction measures, line upgrades, and the evaluation of a second transmission line for loads over 60 MW to enhance reliability.
grows past 60 MW, a second transmission line will be evaluated regardless of performance. Month DD, 2025 Page 113 of 113 Date: December 12, 2025 Page 632 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix E...
AI summary The document discusses NS Power's Mersey Hydro Update, noting that if capacity exceeds 60 MW, a second transmission line will be evaluated regardless of performance. This is part of the 2026 ACE Plan Appendix E, dated December 12, 2025.
ruction support for both Network Upgrades and 25 Transmission Provider Interconnection Facilities. There has been significant progress in these 10 https://novascotiarbp.com/updates Page 16 of 55 Date: December 12, 2025 Page 669 of 782 REDA...
AI summary The document highlights progress in Network Upgrades and Transmission Provider Interconnection Facilities under the 2026 ACE Plan, part of a multi-year planning cycle toward 2030 goals. The text references an external update page and a non-confidential update document.
1 6.2.3 Grid Stability & Renewable Integration Resources 2 3 Transitioning from a traditional power system which is largely made up of synchronous generators 4 to a power system which will rely heavily on inverter-based resources (IBRs) su...
AI summary Transitioning to inverter-based resources (IBRs) like wind and solar requires grid stability measures such as synchronous condensers and FACTS devices. NS Power, following DOE directives, prioritizes inertial support projects at Benjamin’s Mill and Wedgeport. The NS-NB Reliability Intertie Project aims to enhance transmission reliability between Nova Scotia and New Brunswick.
ransmission line between Onslow, NS and 28 Salisbury, NB required to improve the reliability of Nova Scotia’s transmission link to the New 29 Brunswick Power (NB Power) system and the broader Eastern Interconnection, continues to 30 progre...
AI summary A transmission line project between Onslow, NS and Salisbury, NB aims to enhance Nova Scotia’s grid reliability by Q4 2028. Progress updates mention Q1 2025 activities by Wasoqonatl Transmission. The text references the 2026 ACE Plan Appendix F and the 'Path to 2030 – 2025 Update' as non-confidential documents.
1 The Decision Gate 3 (DG3) governance milestone is planned for December 2025. Advancement 2 of the project through DG3 enables project sanction, with kickoff of the construction contract in 3 Q1 2026. This will be followed by the mobiliza...
AI summary The document outlines project milestones for the Reliability Intertie, including Decision Gate 3 (DG3) in December 2025 and Stage 2 transmission planning. It also highlights the need for 300MW of new fast-acting generation by 2030, as per the 2030 Clean Power Plan and Evergreen IRP analysis. NS Power is not currently engaged with NB Power on Stage 2 but plans to collaborate with stakeholders on interregional transmission expansion.
1 The following are existing and future milestones to enable this: 2 3 • NRCan and the NS DOE designated Wind Energy Areas (WEA), which will be managed 4 by the Canada Nova Scotia Offshore Energy Regulator (CNSOER), in July 2025. 5 6 • A s...
AI summary Nova Scotia's offshore wind development includes milestones like WEA designation in 2025, strategic direction letters, and a 2026 bid process. While not part of the 2030 Clean Power Plan, NS Power monitors progress. The NZA-led study (2024-2026) evaluates offshore wind's potential for decarbonization, hydrogen, and export opportunities, with transmission planning phases ongoing.
ission expansion plan to support OSW, respectively. Ultimately, this study is 26 anticipated to be completed in Q1 2026 and will provide a thorough understanding of the 27 opportunities and challenges for integrating OSW into the Atlantic...
AI summary The document discusses a study on integrating offshore wind (OSW) into the Atlantic Canadian grid, led by NZA with NS Power's participation. The study, anticipated to complete in Q1 2026, will assess opportunities and challenges for provincial and regional integration, including domestic and export considerations.
1 8.0 PROJECT ACCOUNTABILITIES, COORDINATION, AND RISK 2 MANAGEMENT 3 4 NS Power believes that the Nova Scotia 2030 Clean Power Plan is a comprehensive and 5 appropriate clean energy transition plan. It is based on extensive studies and st...
AI summary NS Power asserts the Nova Scotia 2030 Clean Power Plan is comprehensive, based on stakeholder engagement and studies. It outlines roles: Province manages renewable projects until 2030 RES targets, NS Power handles fuel conversions and transmission, and IESO-NS oversees battery storage and fast-acting generation.
gets. projects. customers. studies for • Transition transmission responsibility for connected system impact resources from NS studies to IESO-NS Power. for transmission connected resources. Page 47 of 55 Date: December 12, 2025 Page 700 of...
AI summary The document outlines a transition of responsibility for system impact studies related to transmission-connected resources from Nova Scotia Power to the Independent Electricity System Operator - Nova Scotia (IESO-NS). This shift is part of the 2026 ACE Plan Appendix F and the 'Path to 2030 – 2025 Update' initiative.
2030 Accountability NS Power Key Action IESO-NS NS Government Partner Key Projects Items Action Items Key Action Items Action Items • Implementation of TPIF and associated Network Upgrades. Battery IESO-NS and • Procure and finance • Procu...
AI summary The document outlines key actions by NS Power and IESO-NS for 2030, including implementing TPIF and network upgrades, procuring 150 MW/600 MWh battery storage via regulated utility models, and transitioning grid stability responsibilities. Partnerships with IPPs and the NS Government are emphasized for energy storage procurement and grid-scale projects.
complete work to regulated model, review and enable including issuance of transmission competitive required connection to procurements for authorizations. Salisbury, NB. required products • Advocate for and services. federal support • Work...
AI summary The text outlines initiatives for transmission expansion, competitive procurements, and collaboration with the NB Government on projects like Salisbury, NB, and Point Lepreau. It emphasizes the role of IESO-NS in implementing TPIF and Fast-Acting Generation resources, along with regulatory coordination.
. 26 17 4.5 Trimming and Removal of Trees Around Existing Power Lines .......................... 27 18 5.0 STORM HARDENING – TARGETED EQUIPMENT REPLACEMENTS AND 19 UPGRADES .....................................................................
AI summary The document outlines infrastructure upgrades for Nova Scotia's power grid, including tree trimming, storm hardening, equipment replacements, and grid modernization programs. It is part of the 2026 Annual Capital Expenditure (ACE) Plan, focusing on distribution, transmission, and substation improvements.
1 LIST OF FIGURES 2 3 Figure 1: Forecast Investment by Reliability Program 2025-2029 ($ millions) ............................. 7 4 Figure 2: Contribution to CHI by Outage Cause (2020 – 2024) Performance Standards ............11 5 Figure 3...
AI summary The document outlines a list of figures related to reliability programs, vegetation management, corridor widening, and rights-of-way establishment in Nova Scotia. Key themes include reliability investments, outage cause analysis, customer interruption metrics (CHI), SAIDI improvement targets, and infrastructure planning initiatives for 2025.
1 Figure 26: In Progress Construction of New Mount Uniacke Substation .................................... 42 2 Figure 27: 2025/2026 Advanced Grid Modernization Progress Overview ................................. 44 3 Figure 28: 2025 Plann...
AI summary The document outlines infrastructure projects and planning for grid modernization, reliability, and expansion in Nova Scotia, including substation construction, remote terminal unit installations, vegetation management, right-of-way widening, and conductor upgrades for 2025/2026.
ments 8 detailed in year one of the Plan. The Plan has a goal of reducing the overall duration and frequency 9 of outages while balancing the affordability of these investments for customers. 10 11 1.1 Five-Year Reliability Plan Commitment...
AI summary NS Power's Five-Year Reliability Plan aims to reduce outage duration and frequency through three core programs: vegetation management, storm hardening, and grid modernization. The plan balances reliability improvements with customer affordability, focusing on infrastructure upgrades and advanced grid technologies.
2026 ACE Plan Appendix G Page 15 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 • Addition of six RTUs improving substation communication and control, supporting 2 quicker response and restoration of service in the e...
AI summary NS Power's 2026 ACE Plan Appendix G outlines infrastructure upgrades to enhance grid reliability, including RTU additions, substation transformer replacements, new substation construction in Mount Uniacke, transmission structure work, and reconductoring of 33.7 km of transmission lines to improve resilience and winter peak capacity.
Complete in Remainder of Year Distribution 297 kms 183 kms 59 kms 242 kms (Revised due to Corridor Wildfire Mitigations) 1 Widening with Managed Distribution ROWs Vegetation Establish 330 kms 229 kms 89 kms 318 kms (Revised due to Manageme...
AI summary The document outlines vegetation management activities for distribution and transmission corridors, noting revisions to project distances due to wildfire mitigation measures. Additional controls by the Department of Natural Resources reduced work efficiency, with details in the Storm Hardening – Vegetation Management section.
Planned Completed (Due to Wildfire on Track Kms YTD Mitigation) Kms (Y/N) Distribution Corridor 297 183 242 Widening with Managed Rights-of-Way 19 20 Figure 10 below illustrates the locations where distribution rights-of-way have been wide...
AI summary The document outlines NS Power's infrastructure projects to widen distribution and transmission corridors with managed rights-of-way, aiming to improve reliability by increasing separation between conductors and forest edges. It details $15 million in 2025-2029 forecast investments for transmission corridor widening, with $3 million anticipated for 2025 year-end spending.
2026 ACE Plan Appendix G Page 25 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 As of October 31, approximately 87 percent of the 2025 program has been completed and is on 2 track to have the full project work comple...
AI summary NS Power reports that 87% of the 2025 program has been completed and is on track for full completion by year-end. Figure 11 outlines vegetation transmission widening projects, including the L-6503-added line from Onslow to Trenton, which has 17 km completed year-to-date.
2026 ACE Plan Appendix G Page 31 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 5.0 STORM HARDENING – TARGETED EQUIPMENT REPLACEMENTS AND 2 UPGRADES 3 4 2024-2029 Forecast Investment: $916 million 5 Forecasted Perfor...
AI summary NS Power's 2024-2029 Storm Hardening Plan includes $916 million for distribution, transmission, and substation upgrades to enhance grid reliability and comply with regulations. Investments target aging equipment, aiming to reduce SAIDI by 0.13–0.24 hours.
ge 746 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix G Page 39 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 2 Figure 23: 2025 Completed Padmount Transformer Replacements and Upg...
AI summary NS Power outlines its 2025-2029 transmission system upgrade plan, allocating $196 million over five years and $32.6 million for 2025 alone. Projects focus on replacing structures, reinforcing conductors, and realigning lines to enhance reliability and resiliency, informed by risk profiles and past performance.
Non-Confidential 1 Figure 24: Transmission System Program - 2025 Overview Category # Transmission Line Upgraded Replacements and Upgrades 29 Line Rebuilds 3 Asset Life Extension Province Wide Water Crossing Upgrades 3 Line Realignment 2 2...
AI summary NS Power outlines its 2025 Transmission System Program, including 29 replacements/upgrades, 3 line rebuilds, province-wide asset life extension, and 3 water crossing upgrades. These investments aim to strengthen transmission reliability through infrastructure management, as detailed in the 2025 ACE Plan and illustrated in Figure 25.
ribution Establish New ROWs 377 kms Vegetation Management Trimming and Removal of Trees 192 kms Transmission Transmission Corridor Widening 121 kms Vegetation Management Distribution System Equipment 15 Trip Saver Additions Targeted Upgrad...
AI summary The document outlines infrastructure projects for Nova Scotia Power's reliability plan, including new right-of-way establishment, vegetation management, transmission corridor widening, and distribution system upgrades. Specific initiatives include conductor replacements, substation transformer replacements, and targeted equipment additions to enhance grid reliability.
Transmission System Upgrades 28 lines Substation Upgrades and 8 Transformers Replacements Remote Terminal Units (RTUs) 8 RTUs Downline Connectivity 35 Devices Advanced Grid Modernization Fault Location Isolation and 24 Devices Service Rest...
AI summary The 2026 ACE Plan Appendix G outlines NS Power's priority transmission system upgrades, including substation upgrades, RTUs, and FLISR devices. The 2026 priority feeder list includes 40 feeders, 31 newly identified and 9 carried over from 2025, based on outage data and load growth analysis. The list may be revised following full 2025 outage data analysis.
theast 847 48 West 2,389 133 Total 5,261 293 3 4 7.1.2 Transmission Corridor Widening with Managed Rights-of-Way (ROW) > 69KV 5 6 2026 Forecast Investment: $3.3 million 7 8 NS Power’s transmission vegetation management plan is strategicall...
AI summary NS Power's 2026 transmission vegetation management plan uses growth modeling, IVM, LiDAR, and inspection data to optimize forestry crew focus, with a $3.3M investment forecast. The plan is part of a five-year reliability initiative, emphasizing predictive planning and hazard mitigation in transmission corridors.
2026 ACE Plan Appendix G Page 60 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 7.2.2 Transmission System Upgrades and Replacements 2 3 2026 Forecast Investment: $43.0 million 4 5 In 2026, NS Power plans to invest ap...
AI summary NS Power plans to invest $43.0 million in 2026 for transmission system upgrades and replacements, including traditional infrastructure work, site-specific projects, and ongoing upgrade programs to enhance reliability and resiliency.