spring helicopter inspection of the overhead transmission was completed in May. In the Q4 report, NSPML stated that the company completed a second helicopter inspection of the Newfoundland and Labrador transmission lines, and that the insp...
AI summary NSPML completed helicopter inspections of transmission lines in Newfoundland and Labrador, with the Nova Scotia inspection scheduled for completion by year-end 2025. An independent engineer found some deficiencies in Newfoundland assets, including vegetation issues and corroded wires, and noted that a sonar unit was missing. The Labrador Island Link test was postponed to 2026, and several outages occurred on the link in late 2025.