103715Reply Comments - Exhibit C Clean Amended PPA - Procurement Administrator - Power Advisory 1 passage
5.4 Metering p. pp. 40-41
5.4 Metering All Facility revenue class metering equipment shall be routinely tested by NSPI. At any time, either Party may request a test of the accuracy of the metering equipment at its own expense. The results of meter calibrations or t...

AI summary The section outlines procedures for testing and maintaining revenue class metering equipment by NSPI. It specifies that either party may request tests, and outlines the process for handling inaccuracies, including financial adjustments if meter accuracy exceeds a 2% variance.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →