NSEB accepts Wasoqonatl's Q2 2026 independent engineer report confirming NS-NB Reliability Intertie Project remains on budget and on schedule
AI summary
- BTY Consultancy Group Inc. filed Report Number 6 (issued August 20, 2026) covering the period ending June 30, 2026, concluding the Ns Nb Reliability Intertie Project can be completed within the total project budget of $684,684,600 (including Afudc and grants) with a Commercial In-service date prior to October 10, 2028.
- BTY was engaged by CIBC — the third-party market lender financing 40% of Capital Expenditures — to independently review the project during its construction phase, per the Board's earlier direction in M13059.
- The Board approved Confidentiality treatment for commercially sensitive, non-public third-party, and system-security-related portions of the BTY reports under Rule 12 of the Board's Regulatory Rules; the previously approved Confidentiality Undertaking from Matter M12217 continues to apply.
- By April 23, 2026 approval, Wasoqonatl Transmission Incorporated was permitted to submit BTY's monthly reports on a quarterly basis; Q2 2026 reports were filed August 27, 2026 and accepted as filed on September 2, 2026.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 103405 Board letter re: accepted as filed