Wasoqonatl Transmission Incorporated (WTI) – Q2 2026 Independent Engineer Reporting: NS-NB Reliability Intertie Tie Project
What's happened
Filing Timeline
-
02 Sep
DocumentNSEB accepts Wasoqonatl's Q2 2026 independent engineer report confirming NS-NB Reliability Intertie Project remains on budget and on schedule
-
27 Aug
DocumentWTI files Q2 2026 Independent Engineer Status Reports (Reports #4–6) for the NS-NB Reliability Intertie Project, confirming the project remains on schedule and within budget
The filings themselves
Documents
Exhibits
2 files
- W-1 Report - Redacted
- W-1(C) Report - Confidential
Other documents
1 file
- 103405 Board letter re: accepted as filed
What's discussed — click to drill in
Topics
Infrastructure Planning
14 passages across 2 documents
Project Schedule
6 passages across 2 documents
Confidentiality
5 passages across 2 documents
Capital Expenditures
3 passages across 1 documents
Distribution Planning
3 passages across 1 documents
Financial Instruments
3 passages across 1 documents
Regulatory Approval Processes
3 passages across 2 documents
Afudc
2 passages across 1 documents
Cost Considerations
2 passages across 1 documents
Cost Recovery
2 passages across 1 documents
Financing Alternatives
2 passages across 1 documents
Ns Nb Reliability Intertie Project
2 passages across 2 documents
Right Of Way
2 passages across 1 documents
Affordability
1 passages across 1 documents
Boards Regulatory Rules
1 passages across 1 documents
Budgets And Targets
1 passages across 1 documents
Contract Terms
1 passages across 1 documents
Credit Ratings
1 passages across 1 documents
Cybersecurity
1 passages across 1 documents
Emergency Response
1 passages across 1 documents
Health And Safety
1 passages across 1 documents
Jurisdictional Questions
1 passages across 1 documents
Power Infrastructure
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents
System Reliability
1 passages across 1 documents
Transmission Planning
1 passages across 1 documents