The following table outlines the current status of permits for the Project:
The following table outlines the current status of permits for the Project: Permit Name Status Letter of Offer for Easement on Crown Lands Raptor Nest Removal Permit Heritage Research Permits Received Wetland Alteration Permit Received App...

AI summary The document outlines the current status of permits for a project, noting that several permits have been received, while others remain pending. BTY Consultancy Group Inc. does not have concerns about any of the remaining permits.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →