Matter: Wasoqonatl Transmission Incorporated (WTI) – Q2 2026 Independent Engineer Reporting: NS-NB Reliability Intertie Tie Project
3 passages 1 document

Capital Expenditures across all matters →

W-1Report - Redacted 3 passages
2.4 COMMERCIAL ISSUES
2.4 COMMERCIAL ISSUES Financial Close occurred on December 19, 2025. BTY did not receive a draw request for the current period. BTY understands that costs incurred to date will be funded from other sources.

AI summary The Financial Close occurred on December 19, 2025. BTY did not receive a draw request for the current period and will fund incurred costs from other sources.

2.5 CONCLUSIONS
2.5 CONCLUSIONS Based on the information received by BTY and reported within this Independent Engineer Status Report, BTY is of the opinion that the Project can be completed for the total Project Budget of $684,684,600 (including AFUDC and...

AI summary BTY concludes that the Project can be completed within the total budget of $684,684,600, including AFUDC and grants, with a Commercial In-service date before October 10, 2028.

4.2 VARIATIONS
4.2 VARIATIONS ID Title Schedule Impact Capital Cost Total 4.3 VARIATION FUNDING

AI summary The section discusses variations and their funding, though specific details are missing due to incomplete tables. It references the need for funding mechanisms and potential impacts on capital costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →