HomeProject ScheduleM13059Evidence
Topic/Matter Intersection

Topic:"Project Schedule" in M13059

Matter: Wasoqonatl Transmission Incorporated (WTI) – Q2 2026 Independent Engineer Reporting: NS-NB Reliability Intertie Tie Project
6 passages 2 documents

Project Schedule across all matters →

W-1Report - Redacted 5 passages
2.2 KEY INPUTS
2.2 KEY INPUTS Site Visit Details Comments Date of site visit N/A BTY did not visit the site as there were no active construction activities ongoing. Project Schedule Financial Close December 19, 2025 Achieved Onslow Substation Constructio...

AI summary The document outlines the key inputs for a project, including the project schedule, financial close dates, substation construction completion dates, and transmission line completion dates. The project is on schedule, and the original budget matches the current forecast final cost. The Borrower will fund project costs using alternative sources of funding.

3.2 SCHEDULE AND PROGRESS
3.2 SCHEDULE AND PROGRESS BTY understands that the Borrower and the Construction Contractor are in the process of finalizing their respective construction contracts, as well as the baseline schedule, which should be developed further in Ma...

AI summary BTY acknowledges that the Borrower and Construction Contractor are working on finalizing their construction contracts and baseline schedule, which will be further developed in May 2026. The schedule table will be expanded in future report versions once the baseline schedule is complete.

The Project Lenders on behalf of Wasoqonatl Transmission Incorporated Wasoqonatl Transmission Line Report Number 4 June 17, 2026
The Project Lenders on behalf of Wasoqonatl Transmission Incorporated Wasoqonatl Transmission Line Report Number 4 June 17, 2026 Activity ScheduledDate Status Line L8006 (Onslow to NS/NB Border) Substantial Completion On Schedule Line L322...

AI summary The document outlines the scheduled completion dates and current status of various transmission line and substation projects by Wasoqonatl Transmission Incorporated. BTY Consultancy Group Inc. believes the schedule is achievable.

2.5 CONCLUSIONS
2.5 CONCLUSIONS Based on the information received by BTY and reported within this Independent Engineer Status Report, BTY is of the opinion that the Project can be completed for the total Project Budget of $684,684,600 (including AFUDC and...

AI summary BTY concludes that the Project can be completed within the total budget of $684,684,600, including AFUDC and grants, with a Commercial In-service date before October 10, 2028.

The Project Lenders on behalf of Wasoqonatl Transmission Incorporated Wasoqonatl Transmission Line Report Number 6 August 20, 2026
The Project Lenders on behalf of Wasoqonatl Transmission Incorporated Wasoqonatl Transmission Line Report Number 6 August 20, 2026 Activity ScheduledDate Status Financial Close 19-Dec-25 Achieved Material Procurement Substation Breakers De...

AI summary The document outlines the current status of various activities related to the Wasoqonatl Transmission Line project, indicating that some tasks have been completed or are on schedule, while others are delayed. BTY Consultancy Group Inc. believes the schedule is achievable.

103405Board letter re: accepted as filed 1 passage
Section 1
September 2, 2026 [[email protected]](mailto:[email protected]) Mary Ellen Greenough Director, Legal and Regulatory, ECEI Projects Nova Scotia Power Inc. PO Box 910 Halifax, NS B3J 2W5 Dear Ms. Greenough: M13059 –...

AI summary Nova Scotia Power Inc. submitted a quarterly report from BTY Consultancy Group Inc., the independent engineer for the NS-NB Reliability Intertie Project, which concluded the project can be completed within budget and before the deadline. The report was filed in response to a directive from the Nova Scotia Energy Board due to the involvement of the Canada Infrastructure Bank.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →