MATERIAL DELIVERIES x New breakers for Onslow Substation have been delivered and stored on site.
AI summary New breakers for the Onslow Substation have been delivered and stored on site as part of material deliveries.
MATERIAL DELIVERIES x New breakers for Onslow Substation have been delivered and stored on site.
AI summary New breakers for the Onslow Substation have been delivered and stored on site as part of material deliveries.
TRANSMISSION LINE - x ROW clearing from Onslow Substation to NS-NB border nearing completion; - x Mobilization complete; - x Marshalling yard access road complete; and - x Access road construction ongoing.
AI summary The transmission line project is progressing with ROW clearing nearing completion, mobilization complete, marshalling yard access road complete, and access road construction ongoing.
3.7 UNFORESEEN SITE CONDITIONS At the Salisbury Substation, larger than expected boulders were discovered during the excavation process. Additional hydrovac resources were brought in to mitigate this.
AI summary During excavation at the Salisbury Substation, larger than expected boulders were discovered, leading to the use of additional hydrovac resources to address the issue.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →