Home M08604 Digest
AI-generated summary · Application · 05/07/2019

NSUARB grants EfficiencyOne a two-week extension to August 14, 2019 for filing the DSM Potential Study, rejecting a requested six-week delay

M08604 · E-ENS-R-18 - EfficiencyOne - 2019 Demand Side Management (DSM) Plan Application, 2017 Annual Progress Report  and 2017 Evaluation Reports
AI summary
  • Efficiencyone requested a six-week extension (to September 13, 2019) to file the Demand Side Management Potential Study, citing input from E1; the Board approved only a two-week extension to August 14, 2019 (Document 269117).
  • The original July 31, 2019 deadline was established by Board Order of July 23, 2018, which gave EfficiencyOne a full year to complete the study alongside meaningful stakeholder consultation.
  • The Board's October 5, 2018 letter in Matter M08059 had directed NS Power to complete all pre-Integrated Resource Plan analyses by the same July 31 date, treating the DSM Potential Study as a critical IRP input.
  • The Board declined the full extension to avoid delaying the broader IRP process, underscoring the DSM Potential Study's role as a prerequisite for IRP modeling and analysis targeted for mid-2020 completion.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • 77526 Letter to E1 approving extension for filing study other_documents