AI-generated summary · Application · 06/29/2026

NSEB Board Staff issued two information requests to complainant Malcolm Mills seeking documentation and clarification on billing dispute related to heat pump installation under Efficiency Nova Scotia program

M12845 · NSPI Complaint - Billing Issues - Malcolm Mills
AI summary
  • The Nova Scotia Energy Board issued IR-1 and IR-2 to complainant Malcolm Mills on June 29, 2026, with responses due July 21, 2026, in Matter M12845 concerning a billing complaint against Nova Scotia Power Inc.
  • IR-1 seeks clarification on whether the charges Mills alleges were excessive relate to Efficiency NS program costs, post-installation electricity charges from NS Power, or both, and requests supporting documentation including contracts, invoices, and debt collection correspondence.
  • IR-1 also asks whether Mills has pursued or is willing to pursue a payment arrangement with NS Power or Efficiency NS to resolve his outstanding balance.
  • IR-2 asks Mills to explain the sequence of events underlying his allegations that Efficiency NS exploited seniors, inflated prices, and encouraged debt customers could not afford.
  • NS Power previously responded on May 26, 2026, stating it does not administer Efficiency NS programs and has no role in setting heat pump equipment costs, rebates, or incentives; Mills did not respond to NS Power's submission by the June 9, 2026 deadline.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • 102554 NSEB (MILLS) IR-1 to IR-2 - Redacted other_documents