Nova Scotia Power filed its Q2 2026 quarterly update on the Dispatch Study Action Plan, reporting near-complete milestones for the Economic Dispatch Optimization Solution and System Dispatch Dashboard with a revised go-live date of July 14, 2026.

M12919 · Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q2 2026
AI summary
  • NS Power submitted the update pursuant to the NSUARB's October 12, 2022 Decision (M10453), which directed quarterly progress reports on the Dispatch Study Action Plan beginning March 31, 2023.
  • The Other Economic Dispatch Optimization Solution (EDOS) reached 100% completion across all execution milestones as of Q2 2026, following a major vendor defect discovered during User Acceptance Testing in May 2026 that pushed the go-live date from June 16 to July 14, 2026; final UAT was confirmed successfully completed June 25.
  • The System Dispatch Dashboard (SDD), which will make dispatch metrics publicly available via Oatt OASIS, also reached 100% on all milestones and is planned for production deployment the week of July 20, 2026.
  • Additional workstreams completed include battery and AGC Wind asset class configuration, ad hoc query and reporting capabilities, and operational support model development, with a Hyper Care period running July 14 to August 11 before handoff to operational support.
  • The update was shared in conjunction with a Fuel Adjustment Mechanism FAM Small Working Group meeting held June 26, 2026, consistent with the Board's direction to continue stakeholder engagement on dispatch optimization.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • N-1 Update Report exhibits