HomeMattersM12919
M12919 Open Electricity

Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q2 2026

Filed 06/29/2026 5 documents

What's happened

Filing Timeline

  • Document
  • 03 Sep
    RIR
    Nova Scotia Power responds to NSEB information requests on vendor defect and cost responsibility in Dispatch Study implementation
  • 13 Aug
    Document
    NSEB Board Staff issue second-round information requests to Nova Scotia Power on vendor misinterpretation and cost responsibility in Q2 2026 Dispatch Study Action Plan Update
  • 06 Aug
    RIR
    Nova Scotia Power responds to NSEB information requests on a vendor defect in the Dispatch Study model affecting hydro and Tufts Cove generation dispatch
  • 29 Jun
    Document
    Nova Scotia Power filed its Q2 2026 quarterly update on the Dispatch Study Action Plan, reporting near-complete milestones for the Economic Dispatch Optimization Solution and System Dispatch Dashboard with a revised go-live date of July 14, 2026.

The filings themselves

Documents

Exhibits 3 files
  • N-1 Update Report PDF · 06/29/2026
  • N-2 NSPI (NSEB) RIR 1 Processing…
  • N-3 NSPI (NSEB) RIRs 2-6 PDF · 09/03/2026
Other documents 2 files
  • 102799 NSEB (NSPI) IR 1 PDF · 07/16/2026
  • 103207 NSEB (NSPI) IR-2 to IR-6 PDF · 08/13/2026