Matter: Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q2 2026
2 passages 1 document

Infrastructure Planning across all matters →

N-1Update Report 2 passages
EDOS Execution Milestones p. p. 4
EDOS Execution Milestones E Milestone Planned Status Q1 2026 Status Q2 2026 Requirements & Design 2024 Q4 100% 100% D Technical Realization 2025 Q1 95% 100% O System Integration Testing 2025 Q2 90% 100% S End-User Testing 2025 Q2 50% 100%...

AI summary The EDOS Execution Milestones table outlines the progress of various milestones in the implementation of the Economic Dispatch Optimization Solution, including requirements and design, technical realization, system integration testing, end-user testing, and training and deployment planning as of Q1 and Q2 2026.

Additional Progress Notes p. pp. 7-8
Additional Progress Notes Enablement of Battery Asset Class configuration and interface updates Enablement of AGC Wind asset class configuration and interface updates Final Dispatch Dashboard development Ad Hoc Query and reporting capabili...

AI summary This section outlines various project progress notes, including the enablement of battery and AGC Wind asset class configurations, development of the Final Dispatch Dashboard, ad hoc query and reporting capabilities, extensive testing and training, hyper care preparations, operational support model development, and post-project FAM recommendations reporting.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →