Matter: Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q2 2026
1 passage 1 document

Rates And Money across all matters →

103207NSEB (NSPI) IR-2 to IR-6 1 passage
4 Request IR-3:
4 Request IR-3: - 5 Please explain why NS Power would be responsible for the cost of remediation work made - 6 necessary because the vendor made a mistake and misinterpreted the design requirements? 7

AI summary The request asks NS Power to explain why they would be responsible for remediation costs resulting from a vendor's error in misinterpreting design requirements.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →