· Application · 08/24/2026
Nova Scotia Power responds to NSEB directives on interconnection process annual reporting, hosting capacity restoration, and network upgrade refund regulation
AI summary
- The Nova Scotia Energy Board issued findings on August 4, 2026 in Matter M12778, directing that future annual reporting on transmission interconnection issues be filed by Ieso Ns and distribution interconnection issues by Nova Scotia Power Incorporated, with both due March 31 each year.
- The Board accepted NS Power's proposal to consolidate Distribution Generation and Battery Resource Project reporting within the annual interconnection processes report, removing the previous requirement to include it in the annual Commercial Net Metering Program report.
- Regarding the Cybersecurity incident that suspended updates to the distribution hosting capacity table and interactive map, NS Power advises that GIS recovery and CYME Software integration have been restored, with public map updates on track for September 2026; ongoing updates will be provided via Matter M12273 Monthly Updates.
- On the Distribution network upgrade refund regulation, NS Power states it is conducting a comprehensive review of Board-approved regulations but cannot provide a specific timeline for filing proposed amendments, as scope and nature of changes remain under evaluation.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 103309 Letter from NSPI re directives reporting