EfficiencyOne filed its Q2 2026 DSM Report showing the 2023-2026 Plan on track to meet all four Performance Targets, while the Residential Behaviour program component is being wound down after a cybersecurity-linked data outage at NS Power
AI summary
- E1's cumulative four-year forecast projects 537.6 GWh of energy savings (102% of the 528.7 GWh target), 99.7 MW of peak demand savings (102% of target), 16.2 MW of available demand response capacity (99.6% of the 16.3 MW target), and 22.6 GWh of affordable/equity program savings (114% of target), per Table 1 of Exhibit E-1
- The Residential Behaviour program component has been paused since May 2025 due to unavailability of Advanced Metering Infrastructure data from NS Power following its cybersecurity incident (M12273); with customer data not expected until end of Q3, E1 has decided not to resume the component in 2026 and has begun winding it down — no energy savings and only ~$0.2M in residual costs are forecast for the year
- Demand Response achieved 16.2 MW of available capacity for the 2025/2026 season (December 1, 2025 – February 28, 2026), representing significant recovery from 6.8 MW in 2025; BNI Demand Response participants fell from 143 to 98 facilities but available capacity per participant surged from 42 kW to 129 kW as E1 prioritized more active enrollees
- Year-to-date expenditures through Q2 are $30.3 million (48% of the $63.75M 2026 Plan), with a revised year-end forecast of $61.1M — slightly below the Plan — reflecting savings from the Residential Behaviour wind-down, partially offset by higher Demand Response incentive costs
- E1's Q3 2026 DSM Report is scheduled to be filed with the Nova Scotia Energy Board on November 25, 2026
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- E-1 Q2 2026 Demand Side Management Report