AI overviewWhat this document contains
This document is an exhibit containing a Board Decision Letter dated September 20, 2010, which includes administrative contact information for the Nova Scotia Utility and Review Board and a ruling approving a cost variance request by Nova Scotia Power Inc. for CI#35882 - 2009 Cutout Replacements. The topics covered include the approval of an increase in project costs and the reasons provided for the variance.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M03515 — CI# 35882 - P-510 - NSPI WO - 2009 Cutout Replacements - $1,642,511