98572 Other documents 07/17/2025

Submissions - Midgard

Download original
98572.pdf · PDF · 958.0 KB · 13 pages
AI overviewWhat this document contains

This document is an exhibit submitted as part of a regulatory application batch to the Nova Scotia Energy Board. It contains a report by Midgard Consulting Inc. reviewing Nova Scotia Power Inc.'s application for authorization to overspend on the Ruth Falls Main Dam refurbishment, including details on cost estimates, project schedule, Fisheries Act Authorization, economic analysis comparing refurbishment and decommissioning options, and revisions to project costs following receipt of the Fisheries Act Authorization.

Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

Filed in: M11927 — Nova Scotia Power Inc. - CI 50518 – HYD Ruth Falls Main Dam Refurbishment – $15,445,508 (ATO)

Filing event: APPLICATION on 07/17/2025

13 pages
100%