AI overviewWhat this document contains
This document is an exhibit from a RIR batch filed with the Nova Scotia Energy Board, containing cost applications related to the replacement and upgrade of deteriorated transmission line assets. It covers project scope, cost breakdowns, structure-specific costs, voltage class-related differences, overtime labour allocation, and the use of contingency funds for transmission line projects.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M12798 — Nova Scotia Power Inc. - CI C0080108 – L-5532 Replacements and Upgrades Phase 1 - $3,455,473