Nova Scotia Power Inc. - CI C0080108 – L-5532 Replacements and Upgrades Phase 1 - $3,455,473
What's happened
Filing Timeline
-
01 Jun
DecisionNSEB approved Nova Scotia Power's $3,455,473 capital expenditure for Phase 1 replacements and upgrades to the 70-year-old transmission line L-5532.
-
21 May
RIRNova Scotia Power filed responses to three Board information requests on the $3.46M L-5532 transmission line replacement project, addressing scope, overtime labour, and contingency justification.
-
29 Apr
DocumentNSEB Board Staff issued three information requests to Nova Scotia Power regarding the $3,455,473 L-5532 transmission line replacements and upgrades application (M12798), probing cost breakdowns, overtime labour, and contingency justification.
-
09 Apr
DocumentNova Scotia Power filed a capital project authorization seeking NSEB approval for $3,455,473 to replace deteriorated assets on the 69 kV L-5532 transmission line in Phase 1 of a multi-year refurbishment program.
The filings themselves
Documents
Key documents
1 file
- 102238 Decision Letter
Exhibits
2 files
- N-1 Application - CI C0080108 L5532 Replacements and Upgrades Phase 1
- N-2 NSPI (NSEB) RIR 1 to 3
Other documents
4 files
- 101531 Letter NSPI re: Capital Items Filed Outside the Quater Package
- 101795 NSEB (NSPI) IR-1 to IR-3
- 102073 Letter NSPI re: RIRs
- 102238 Decision Letter
What's discussed — click to drill in
Topics
Capital Expenditures
16 passages across 6 documents
Infrastructure Planning
11 passages across 4 documents
Transmission Planning
6 passages across 1 documents
Cost Considerations
3 passages across 2 documents
Regulatory Approval Processes
3 passages across 3 documents
System Reliability
3 passages across 2 documents
2025 Ace Plan
2 passages across 2 documents
Asset Management
2 passages across 2 documents
Grid Modernization
2 passages across 2 documents
Depreciation Amortization
1 passages across 1 documents
Generator Interconnection
1 passages across 1 documents
Information Disclosure
1 passages across 1 documents
Performance Monitoring
1 passages across 1 documents
Regulatory Oversight
1 passages across 1 documents
Stakeholder Engagement
1 passages across 1 documents