Matter: Nova Scotia Power Inc. - CI C0080108 – L-5532 Replacements and Upgrades Phase 1 - $3,455,473
2 passages 2 documents

2025 Ace Plan across all matters →

N-1Application - CI C0080108 L5532 Replacements and Upgrades Phase 1 1 passage
Reason for Variance p. p. 1
Reason for Variance The increase of $964,941 from the 2026 ACE Plan subsequent submittal estimate of $2,490,532 is due to the increase in anticipated work following engineering analysis of the LiDAR data. C0080108 Location: CI# : Steam Tit...

AI summary The increase of $964,941 in the 2026 ACE Plan is attributed to the anticipated increase in work following engineering analysis of LiDAR data, as outlined in the 'L5532 Replacements and Upgrades Phase 1' project.

101531Letter NSPI re: Capital Items Filed Outside the Quater Package 1 passage
Section 1 p. p. 0
April 9, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: Capital Items Filed Outside the Quarter Package Dear Ms. Henwood: Enclosed for your review and approval ar...

AI summary A letter from Lana Myatt to Crystal Henwood submits two capital items for the 2026 ACE Plan, detailing project names, costs, and funding allocations. Both items are non-confidential with no expenditures reported as of December 31, 2025.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →