L-2 Exhibits 07/03/2026

DRO Decision - Redacted

Download original
L-2.pdf · PDF · 40.9 KB · 2 pages
AI overviewWhat this document contains

This document is a ruling from the Dispute Resolution Officer (DRO) regarding a consumption and billing dispute between a customer and Nova Scotia Power. It covers the DRO's decision that Nova Scotia Power appropriately billed the customer based on estimated meter readings, which were later reconciled with actual readings, and references relevant Nova Scotia Energy Board regulations.

Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

Filed in: M12942 — NSPI DRO Appeal - Billing Issues - Kevin Lepage

Filing event: APPLICATION on 07/03/2026 · View digest →

2 pages
100%