25 Sep
DecisionNSEB dismissed Jennifer Eaton's land access complaint against Nova Scotia Power, finding it lacks jurisdiction to adjudicate prescriptive easement claims under the Land Registration Act.
-
09 Jul
DocumentComplainant Jennifer Eaton filed a late reply to NSPI's response in land access complaint M12298, disputing the utility's characterization of the electrical connection as a like-for-like replacement.
-
19 Jun
DocumentNova Scotia Power filed a response to a land access complaint from Jennifer Eaton, asserting prescriptive easement rights based on over 35 years of continuous infrastructure presence on her property.
-
11 Jun
DocumentNova Scotia Power requested a one-week extension to file its reply to the Jennifer Eaton land access complaint
-
28 May
CorrespondenceNSEB acknowledges Jennifer Eaton's land access complaint against Nova Scotia Power, setting June 11 deadline for NSPI response
-
27 May
DocumentJennifer Eaton filed a complaint alleging Nova Scotia Power entered her property on April 4, 2025 and installed a power line without an easement or permission.
The filings themselves
Documents
Key documents
1 file
- 99469 Board Decision Letter - redacted
Exhibits
2 files
- E-1 Complaint (Redacted
- E-2 NSPIs Response to Complaint (redacted)
Other documents
4 files
- 97827 Acknowledgment Letter
- 97994 NSPIs Extension Request
- 99104 Complainant's Comments re NSPI Response
- 99469 Board Decision Letter - redacted
What's discussed — click to drill in
Topics
Complaint Resolution
6 passages across 6 documents
Regulatory Approval Processes
5 passages across 4 documents
Legal Procedures
3 passages across 2 documents
Boards Regulatory Rules
2 passages across 1 documents
Energy And Regulatory Boards Act
2 passages across 2 documents
Regulatory Oversight
2 passages across 2 documents
Affordability
1 passages across 1 documents
Compliance Legislation
1 passages across 1 documents
Rate Smoothing Adjustment
1 passages across 1 documents