Nova Scotia Power Inc. General Plant Routines - P028 – Telecommunications Systems Replacements & Modifications (ATO) $320,826
What's happened
Filing Timeline
-
25 Jul
Decision—
-
18 Jul
RIR—
-
26 Jun
Document—
-
09 Jun
Document—
The filings themselves
Documents
Key documents
1 file
- 98698 Board Decision Letter
Exhibits
2 files
- N-1 Application
- N-2 NSPI (NSEB) RIR-1 to RIR-3
Other documents
4 files
- 97972 Letter NSPI re: Capital Items Filed Outside the Quarter Package
- 98271 NSEB (NSPI) IR 1 to 3
- 98596 Letter from NS Power enclosing IR responses
- 98698 Board Decision Letter
What's discussed — click to drill in
Topics
Capital Expenditures
11 passages across 5 documents
2025 Ace Plan
6 passages across 3 documents
Cost Considerations
5 passages across 3 documents
Budgets And Targets
3 passages across 3 documents
Affordability
2 passages across 2 documents
Infrastructure Planning
2 passages across 2 documents
Rates And Money
2 passages across 2 documents
Regulatory Approval Processes
2 passages across 2 documents
Accounting Policies
1 passages across 1 documents
Asset Management
1 passages across 1 documents
Boards Regulatory Rules
1 passages across 1 documents
Cost Recovery
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Forecasting Methodology
1 passages across 1 documents
System Reliability
1 passages across 1 documents