Matter: Nova Scotia Power Inc. General Plant Routines - P028 – Telecommunications Systems Replacements & Modifications (ATO) $320,826
2 passages 2 documents

Affordability across all matters →

97972Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
Commercial Information p. p. 0
Commercial Information Item 2: Partial confidentiality was applied to costs associated with consulting details provided in the capital work order. To protect value for customers and mitigate the risk of prospective proponents having access...

AI summary NS Power applies partial confidentiality to certain commercial and system security information to protect customer interests and maintain competitive bidding. The information includes supplier pricing arrangements and a one-line diagram to prevent competitive advantages and ensure system reliability.

98271NSEB (NSPI) IR 1 to 3 1 passage
Request IR-2:
Request IR-2: - The 2024 actual expenditure for this routine is approximately 34% higher than the 2025 ACE Plan - budget and almost 18% higher than the 2024 forecast included in NS Power's 2025 ACE Plan - (Matter M12012). - a) Does NS Powe...

AI summary The 2024 actual expenditure for a routine is significantly higher than the 2025 ACE Plan budget and 2024 forecast. The request asks NS Power to explain whether the 2025 expenditure will stay within budget, what changes may affect this, and what interim measures are in place to control budget deviations.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →