05462Board Decision Letter
1 passage
Bye-mail and courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 2010 ACE Plan Work Order - CI# 38878 - 2010 Substation...
AI summary Nova Scotia Power Inc. requests regulatory approval for a 2010 ACE Plan work order (CI# 38878) related to substation cutout and insulator replacements under Matter No. 03509. The Board has reviewed the confidential request for approval.
05462Board Decision Letter
1 passage
Bye-mail and courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 2010 ACE Plan Work Order - CI# 38878 - 2010 Substation...
AI summary Nova Scotia Power Inc. (NSPI) requests regulatory approval for a 2010 ACE Plan work order involving substation cutout and insulator replacements. The Board has reviewed the request, which is associated with Matter No. 03509.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →