Topic/Matter Intersection

Topic:"2025 Ace Plan" in M03622

Matter: CI# 38110 - P-128.10 - NSPI WO - 2010 Transmission Line Insulator Replacement - $2,236,168
3 passages 3 documents

2025 Ace Plan across all matters →

N-1Redacted Work Order 1 passage
Section 59 p. p. 1
7 8 Please refer to Attachment 1 - An update to information filed in response to ACE 2009 IR-9 T3(a) and work completed to date for 2010. 10 11 (b) The information for 2009 change-out information is included in the table below. Insulator 1...

AI summary The text references an attachment containing updated information filed in response to ACE 2009 IR-9 T3(a) and work completed for 2010. It also mentions the inclusion of 2009 change-out information in a table, with prior insulator changeout data provided for years before 2009 in response to IR-3(a) related to ACE 2009.

N-2Responses from NSPI to IR-1 to IR-4 1/27/2011 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-3: 2 Please provide the following information by circuit 4 5 3 (a) Estimated labor and material costs from 2010 ACE 6 (b) Actual labor and material costs 8 9 7 (c) Variance in labor and material costs from est...

AI summary The document requests information on estimated, actual, and variance in labor and material costs from the 2010 ACE program, along with the reasons for the variance.

06431Board Decision Letter 2/18/2011 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Manager, Capital Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: Nova Scotia Power Inc. - CI# 38110 - 2010 Transmission Line Insulator Replacement -...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $2.2M capital expenditure to replace transmission line insulators, reduced from the original $2.9M due to internal staff use and fewer circuits. The Board approved the reduced amount, citing reliability benefits and cost justification under the 2010 ACE Plan.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →