M03622 Closed Electricity

CI# 38110 - P-128.10 - NSPI WO - 2010 Transmission Line Insulator Replacement - $2,236,168

Filed 10/15/2010 5 documents

What's happened

Filing Timeline

  • Decision
    NSEB predecessor board approved Nova Scotia Power's $2,236,148 capital expenditure for 2010 Transmission Line Insulator Replacement following staff information requests.
  • 22 Dec
    IR
    Board consultant Synapse Energy Economics issued four information requests to Nova Scotia Power regarding its 2010 Transmission Line Insulator Replacement work order (CI# 38110), with responses due January 12, 2011.
  • 18 Oct
    Document
    Nova Scotia Power filed a redacted work order application seeking NSEB approval for $2,236,168 in capital expenditures for the 2010 Transmission Line Insulator Replacement program (CI# 38110).

The filings themselves

Documents

Key documents 1 file
  • 06431 Board Decision Letter 2/18/2011 PDF
Exhibits 2 files
  • N-1 Redacted Work Order PDF · 10/18/2010
  • N-2 Responses from NSPI to IR-1 to IR-4 1/27/2011 PDF
Other documents 2 files
  • 06022 Information Requests issued by Board Consultants PDF · 12/22/2010
  • 06431 Board Decision Letter 2/18/2011 PDF