Topic/Matter Intersection

Topic:"Regulatory Approval Processes" in M03622

Matter: CI# 38110 - P-128.10 - NSPI WO - 2010 Transmission Line Insulator Replacement - $2,236,168
4 passages 3 documents

Regulatory Approval Processes across all matters →

N-1Redacted Work Order 1 passage
UARB APPROVAL SHEET p. p. 1
UARB APPROVAL SHEET · upmitted on behalf of NC OVA SCOTIA POWER INC , Approved on behalt of NOVA S COTIA UTILITY AND REVIEW BOARD

AI summary This document is an approval sheet from the Nova Scotia Utility and Review Board (UARB) related to a submission made on behalf of Nova Scotia Power Inc. It outlines the approval process and the entities involved in the regulatory proceeding.

N-2Responses from NSPI to IR-1 to IR-4 1/27/2011 2 passages
CI 38110 - 2010 Transmission Line Insulator Replacement (NSDARB P-128.10) NSPI Responses to DARB Information Requests p. p. 0
CI 38110 - 2010 Transmission Line Insulator Replacement (NSDARB P-128.10) NSPI Responses to DARB Information Requests

AI summary NSPI responded to DARB's information requests regarding the 2010 Transmission Line Insulator Replacement project under NSDARB proceeding P-128.10.

CI 38110 - 2010 Transmission Line Insulator Replacement (NSUARB P-128.10) NSPI Responses to UARB Information Requests p. p. 0
CI 38110 - 2010 Transmission Line Insulator Replacement (NSUARB P-128.10) NSPI Responses to UARB Information Requests

AI summary This document outlines Nova Scotia Power Inc.'s (NSPI) responses to the Utility and Review Board (UARB) information requests regarding the 2010 Transmission Line Insulator Replacement project (CI 38110). The project falls under NSUARB P-128.10, focusing on infrastructure planning and regulatory compliance.

06431Board Decision Letter 2/18/2011 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Manager, Capital Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: Nova Scotia Power Inc. - CI# 38110 - 2010 Transmission Line Insulator Replacement -...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $2.2M capital expenditure to replace transmission line insulators, reduced from the original $2.9M due to internal staff use and fewer circuits. The Board approved the reduced amount, citing reliability benefits and cost justification under the 2010 ACE Plan.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →