Matter: CI# 38110 - P-128.10 - NSPI WO - 2010 Transmission Line Insulator Replacement - $2,236,168
1 passage 1 document

System Reliability across all matters →

N-2Responses from NSPI to IR-1 to IR-4 1/27/2011 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-2: 2 3 of Please explain why three the five circuits that showed no failures over the 2003 through 4 2009 period were included in the 2010 program. S 6 Response IR-2: 7 8 ofthe There were no failures on three...

AI summary The request asks why five circuits with no failures from 2003–2009 were included in the 2010 program. The response explains that NSPI proactively replaced insulators due to known cement growth risks, prioritizing reliability and system security as outlined in ACE 2010 IR-T4(d).

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →